United States v. Zurich American Insurance

99 F. Supp. 3d 543, 2015 U.S. Dist. LEXIS 30968, 2015 WL 1137053
CourtDistrict Court, E.D. Pennsylvania
DecidedMarch 13, 2015
DocketCivil Action No. 14-4581
StatusPublished
Cited by8 cases

This text of 99 F. Supp. 3d 543 (United States v. Zurich American Insurance) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Zurich American Insurance, 99 F. Supp. 3d 543, 2015 U.S. Dist. LEXIS 30968, 2015 WL 1137053 (E.D. Pa. 2015).

Opinion

MEMORANDUM OPINION

WENDY BEETLESTONE, District Judge.

This ease involves a payment dispute between a government contractor, Nason Construction, Inc. (“Nason”); its surety, Zurich American Insurance Company (“Zurich”); and a subcontractor, Marenalley Construction, LLC (“Marenalley”), with respect to a construction project for the United States Department of Veterans Affairs (the “VA”) located in Philadelphia, Pennsylvania (the “Project”). Marenalley claims it is owed compensation for certain additional work it performed on the Project. Nason currently is pursuing additional payment from the VA relating to Marenalley’s and other claims in an administrative dispute resolution process set out in its contract with the VA. To date, the VA has not approved payment for the additional work.

Marenalley filed this action pursuant to the Miller Act, 40 U.S.C. §§ 3131-33, to recover against Zurich’s surety bond for the additional work. The Miller Act provides a subcontractor the right to bring suit against the prime contractor’s surety bond if the subcontractor is not paid within ninety days of the completion of its work. Id. § 3133(b)(1). Nason and Zurich have moved to dismiss, arguing that Marenalley agreed in its subcontract with Nason to pursue any claims it may have involving the VA through the administrative disputes resolution process set out in Nason’s prime contact with the VA prior to bringing suit against the bond. In the alternative, Nason and Zurich request this action be stayed pending completion of that process.

The issues before the Court are: (1) whether the terms of the subcontract between Nason and Marenalley effectively require Marenalley to await the resolution of the administrative dispute resolution process provided for by the prime contract between Nason and the VA before pursuing a claim against Nason’s bond; (2) whether this action should be dismissed pending resolution of the administrative process; and (3) whether, in the alternative, this action should be stayed pending the resolution of the administrative process. The answer to each of these questions is no. The Court finds that the subcontract provisions on which Nason and Zurich rely do not waive Marenalley’s Miller Act rights and, thus, will deny the motion to dismiss. Neither, for the reasons set forth below, will it stay this action pending completion of the administrative process.

[546]*546I. BACKGROUND

The VA awarded a contract to Nason on December 18, 2009, for the construction of a parking garage at the VA Medical Center in Philadelphia, Pennsylvania (the “Prime Contract”). Compl. ¶ 5. Zurich issued a bond on behalf of Nason to guarantee payment to those who furnished labor or materials to the Project (the “Payment Bond”). Id. ¶ 6. On or about May 3, 2010, Marenalley entered into a subcontract with Nason to perform work on the Project in exchange for a lump sum payment of $1,330,000 (the “Subcontract”). Id. ¶ 8. In the course of contract performance, the VA added additional work for Marenalley, and Marenalley encountered unexpected conditions that added to the costs of its work' (together, the “Additional Work”). Id. ¶¶ 10-11. Marenalley submitted proposed change orders and requests for equitable adjustment to Nason to compensate it for the Additional Work. Id. 8 ¶ 11; Opp’n. at 4.

On August 7, 2014, Nason sought additional compensation from the VA pursuant to the terms of the Prime Contract (Na-son’s “Certified Claim”). Mot. 18 at 6. Included along with its own claims and the claims of other subcontractors, Nason sought compensation for the Additional Work performed by Marenalley. Opp’n at 4-5, 14-15. Marenalley assisted Nason in the preparation of the claim to the VA that Nason submitted with respect to Marenal-ley’s Additional Work. Id. at 7. The VA has yet to issue a decision on Nason’s request for additional compensation. Mot. at 6. While Nason’s Certified Claim remains pending, Marenalley filed this action against Zurich, seeking to recover from the surety bond. Marenalley seeks $590,345.91 in compensation for labor and materials it furnished in completing the Additional Work. Nason intervened as a party to this action.

The Prime Contract contains a disputes-resolution clause incorporating the terms of the Contracts Disputes Act of 1978 (41 U.S.C. §§ 601-613). Mot. Ex. 2 ¶ 4.31(a). The Contract Disputes Act (the “CDA”) provides for an administrative process in which Nason first was required to submit its claims for payment to the government’s contracting officer. 41 U.S.C. § 605(a) (1978), amended by 41 U.S.C. § 7103. The statute requires that the officer issue a decision “within a reasonable time, ... taking into account such factors as the size and complexity of the claim and the adequacy of the information in support, of the claim provided by the contractor.” Id. § 605(c)(3).1 If the contractor chooses to do so, it may appeal the contracting officer’s decision to the Board of Contract Appeals, id. § 606, amended by 41 U.S.C. § 7104 (2011), or to the United States Court of Federal Claims, id. § 609, amended by 41 U.S.C. § 7104.

Nason and Zurich contend that various provisions in the Subcontract — Section 1.1., Article 2 and Sections 5.3, 6.1.1, and 6.2 — incorporate the Prime Contract’s dispute resolution provision into the Subcontract. They argue that such incorporation requires Marenalley to wait until the resolution of Nason’s CDA disputes resolution process with the VA before bringing this action against Nason’s bond with Zurich. For that reason, they argue that this action should be dismissed or stayed pending resolution of the CDA process.

B. The Relationships Between Mare-nalley, Nason and the VA

Marenalley has no privity of contract with the VA. Therefore, it has no [547]*547right to pursue its claim directly against the VA for additional compensation due it for changes made by the VA or by Nason to its work under the Subcontract. United States v. Blair, 321 U.S. 730, 737, 64 S.Ct. 820, 88 L.Ed. 1039 (1944). “The Government does not recognize or deal with the subcontractor and owes no obligation to him for the work he performs.” United States ex rel. B’s Co. v. Cleveland Elec. Co. of S.C., 373 F.2d 585, 588 (4th Cir.1967). The prime contractor “and only the [prime contractor] has the right to submit factual issues to the Contracting Officer.... ‘There is no procedure by which the claim of a subcontractor can be presented against the United States except as it may become a claim of the prime contractor, since there is no contract, express or implied, between the subcontractor and the government.’ ” Beacon Constr. Co. of Mass. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
99 F. Supp. 3d 543, 2015 U.S. Dist. LEXIS 30968, 2015 WL 1137053, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-zurich-american-insurance-paed-2015.