Camacho Family Partnership v. Patricia I. Romero, Inc.

CourtDistrict Court, D. Guam
DecidedMarch 21, 2018
Docket1:13-cv-00026
StatusUnknown

This text of Camacho Family Partnership v. Patricia I. Romero, Inc. (Camacho Family Partnership v. Patricia I. Romero, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Guam primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Camacho Family Partnership v. Patricia I. Romero, Inc., (gud 2018).

Opinion

1 IN THE DISTRICT COURT 2 FOR THE TERRITORY OF GUAM

3 CAMACHO FAMILY PARTNERSHIP d/b/a CIVIL CASE NO. 13-00026 (lead case) 4 “DIRT DOKTOR,” 5 Plaintiff/Counterclaim Defendant, ORDER ON POST-TRIAL MOTIONS 6 v. 7 PATRICIA I. ROMERO, INC., d/b/a 8 “PACIFIC WEST BUILDERS,”

9 Defendant/Counterclaim Plaintiff, ____________________________________ 10

11 AND ALL RELATED ACTIONS.

12 13 I. INTRODUCTION 14 The parties, Plaintiff Camacho Family Partnership (doing business as Dirt Doktor) and 15 Defendant/Counterclaim Plaintiff Patricia I. Romero, Inc. (doing business as Pacific West Builders 16 (“PWB”)), have filed numerous post-trial motions in this case, following a verdict that the jury 17 returned on May 9, 2017. Dirt Doktor’s motions (Plaintiff’s Post-Trial Motions, May 26, 2017, 18 ECF No. 195) include a motion for prejudgment interest, a motion for attorney fees, a motion for 19 reconsideration of the Court’s interlocutory order concerning PWB’s counterclaim for liquidated 20 damages, motion for a new trial on the demolition and replacement cost claim and on the Military 21 Working Dog (“MWD”) claim, and a motion to dismiss Counterclaim Defendant FirstNet 22 23 Insurance. In its own omnibus motion (Defendant/Cross-Complain[an]t Pacific West Buil[d]ers’ 24 and Defendant Travelers Surety and Casualty Company’s Post-Trial Motion, June 9, 2017, ECF 25 No. 203), PWB likewise moves for prejudgment interest and for attorney fees, and for a declaration 26 1 of the parties’ rights with respect to the delay caused by Dirt Doktor. The motions were heard on 2 July 6, 2017. Having considered the arguments of the parties at the hearing and in the briefing 3 papers and accompanying documents, the Court now rules on the motions. 4 II. BACKGROUND 5 Dirt Doktor agreed to serve as a subcontractor for PWB to build the Red Horse Cantonment 6 Operation Facility at Anderson Air Force Base. Under the contract, Dirt Doktor was required, 7 among other things, to place concrete slabs for the building. In exchange for the work, PWB agreed 8 to pay a total of $1,315,518.00 in installments. (Subcontract ¶ III, Plaintiff’s Ex. 991.) To obtain 9 periodic progress payments, Dirt Doktor was required to submit estimates for “work actually 10 11 performed.” (Id.) PWB then had to make the progress payments within seven working days of 12 receipt of payment from the United States Navy. (Id.) However, if the Navy withheld any payments 13 from PWB, then PWB could “at its sole and complete discretion, withhold a retention in equal 14 percent” from Dirt Doktor’s payments, and the retained funds were not “considered monies due 15 and owing until” PWB received final payment from the Navy. (Id.) 16 The general conditions incorporated into the contract stated that “time is of the essence” 17 and therefore that Dirt Doktor must “complete all work according to the schedule” decided on by 18 PWB. (General Condition Clauses ¶ 2, Plaintiff’s Ex. 991.) Any requests for an extension of time 19 to complete work were required to be submitted in writing within ten days of Dirt Doktor’s learning 20 that a delay may occur. (Id.) 21 If Dirt Doktor failed to “correct, replace or re-execute faulty or defective work” on 22 23 schedule, PWB was required to give 48 hours’ notice of the failure, and if the issue was not 24 resolved, PWB could obtain a substitute subcontractor or provide the needed materials or labor 25 and charge Dirt Doktor the costs plus any extra overhead and profit “at a combined rate of 15% of 26 1 the cost.” (General Condition Clauses ¶ 9.) Further, if Dirt Doktor did not properly perform and 2 caused the project to be delayed, PWB was entitled to “all loss and damages (direct or indirect),” 3 including liquidated damages. (Id. ¶ 10.) Pursuant to PWB’s contract with the U.S. Navy, the 4 liquidated damages owed to the Government for delay was $5,850 per day, as set forth in N40192- 5 10-D-2810. (See Contract, Defendant’s Ex. ZD.) Dirt Doktor agreed to be bound to the contract 6 with the Navy, including the work specifications and terms in N40192-10-D-2810. (See 7 Addendum No. 3, Plaintiff’s Ex. 991.) 8 Prior to trial, the Court found that PWB wrongfully retained $42,855.02 from the 9 December 2012 through February 2013 payment applications submitted by Dirt Doktor because 10 11 the Navy had not begun withholding a 10 percent retention at that time. (Order on Motion for 12 Partial Summary Judgment 13, ECF No. 126.) 13 Following the trial, the jury found that Dirt Doktor did not substantially perform all of its 14 material obligations under the Red Horse Subcontract but was legally excused. (Verdict 2, ECF 15 No. 189.) Further, the jury found that PWB breached a material provision of the subcontract and 16 awarded Dirt Doktor $733,020.55 in damages for total value of work completed minus amounts 17 already paid. (Id. at 3; see Plaintiff’s Ex. 1584.) On PWB’s counterclaim, the jury found that Dirt 18 Doktor had breached the contract, and awarded PWB $246,672.94 in damages for the cost to finish 19 Dirt Doktor’s work and extended overhead that PWB had to pay. (Id. at 4–5.) Further, the jury 20 found Dirt Doktor to be liable to PWB for liquidated damages, if any, for 56.5 days. (Id.) At $5,850 21 per day, the liquidated damages award totals $330,525.00. 22 23 /// 24 // 25 / 26 1 III. PREJUDGMENT INTEREST 2 A. Legal Standard 3 Guam law, which controls in this diversity case involving contract claims, states that a 4 “person who is entitled to recover damages certain, or capable of being made certain by 5 calculation” is entitled to prejudgment interest from the date the claim accrued until judgment. 20 6 G.C.A. § 2110. Damages that are certain or capable of being made certain are those where “the 7 defendant actually knows the amount owed or from reasonably available information” could have 8 calculated the amount owed. Guam Top Builders, Inc. v. Tanota Partners, 2012 Guam 12 ¶ 68 9 (2012). Thus, “where there is a dispute between the parties concerning the basis of computation of 10 11 damages” and the amount depends on resolution of conflicting evidence, “prejudgment interest is 12 not allowable.” Id. The prejudgment interest rate under Guam law is 6 percent unless the parties 13 have agreed to a different amount. See 18 G.C.A. § 47106; Yoshida v. Guam Transp. and 14 Warehouse, Inc., 2013 Guam 5 ¶ 84 (2013). 15 B. Whether Dirt Doktor Is Entitled to Prejudgment Interest 16 Dirt Doktor contends that it is entitled to prejudgment interest pursuant to 20 G.C.A. § 17 2110 at the statutory rate of 6 percent per annum. (Post-Trial Motion 5–6, ECF No. 195.) After 18 taking into account the damages awarded, the Court’s determination that Defendant wrongfully 19 withheld 10 percent of the first three pay applications, and the damages owed to Defendant, Dirt 20 Doktor claims it is owed $606,098.08 in damages plus prejudgment interest. (Id. at 8.) PWB argues 21 that Dirt Doktor is not entitled to prejudgment interest because the damages awarded were not 22 23 “certain” as required by statute due to the conflicting evidence on “whether Dirt Doktor caused 24 project delays, the total project delay caused by Dirt Doktor, and the damages caused to PWB by 25 Dirt Doktor that offset Dirt Doktor’s claimed damages.” (Def’s. Brief 7, ECF No. 203.) 26 1 PWB’s arguments do not resolve whether Dirt Doktor is entitled to prejudgment interest. 2 Although the Guam Supreme Court has not explicitly ruled on the issue of whether offsets or 3 counterclaims affect a plaintiff’s entitlement to prejudgment interest, this Court finds that the 4 Guam Supreme Court would likely hold that the certainty of offsets does not affect whether a 5 plaintiff is entitled to prejudgment interest.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Boyajian v. Gatzunis
212 F.3d 1 (First Circuit, 2000)
Wine & Spirits Retailers, Inc. v. Rhode Island
481 F.3d 1 (First Circuit, 2007)
Fanderlik-Locke Co. v. United States
285 F.2d 939 (Tenth Circuit, 1960)
Chia-Lee Hsu v. Abbara
891 P.2d 804 (California Supreme Court, 1995)
KCIN, INC. v. Canpro Investments, Ltd.
675 So. 2d 222 (District Court of Appeal of Florida, 1996)
Zhang v. DBR Asset Management, Inc.
878 So. 2d 386 (District Court of Appeal of Florida, 2004)
Bank of Brewton, Inc. v. INTERN. FIDELITY INS. COMPANY
827 So. 2d 747 (Supreme Court of Alabama, 2002)
Lasco Enterprises, Inc. v. Kohlbrand
819 So. 2d 821 (District Court of Appeal of Florida, 2002)
Great Western Drywall, Inc. v. Roel Construction Co., Inc.
166 Cal. App. 4th 761 (California Court of Appeal, 2008)
Uzyel v. Kadisha
188 Cal. App. 4th 866 (California Court of Appeal, 2010)
Continental Heller v. AMTECH MECHANICAL SERV.
53 Cal. App. 4th 500 (California Court of Appeal, 1997)
Mid-State Surety Corp. v. Thrasher Engineering, Inc.
575 F. Supp. 2d 731 (S.D. West Virginia, 2008)
Enterprise Capital, Inc. v. San-Gra Corp.
284 F. Supp. 2d 166 (D. Massachusetts, 2003)
Mountain States Broadcasting Co. v. Neale
783 P.2d 551 (Court of Appeals of Utah, 1989)
Crowley v. Black
2007 UT App 245 (Court of Appeals of Utah, 2007)
Cook v. Liberty Life Assurance Co.
320 F.3d 11 (First Circuit, 2003)
Craig Milhouse v. Travelers Commercial Insurance
641 F. App'x 714 (Ninth Circuit, 2016)
United States v. Zurich American Insurance
99 F. Supp. 3d 543 (E.D. Pennsylvania, 2015)
Murphy v. City of Long Beach
914 F.2d 183 (Ninth Circuit, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
Camacho Family Partnership v. Patricia I. Romero, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/camacho-family-partnership-v-patricia-i-romero-inc-gud-2018.