Lasco Enterprises, Inc. v. Kohlbrand
This text of 819 So. 2d 821 (Lasco Enterprises, Inc. v. Kohlbrand) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
LASCO ENTERPRISES, INC., Appellant/Cross-Appellee,
v.
Ronald KOHLBRAND and Kathleen Kohlbrand, et al., Appellee/Cross-Appellant.
District Court of Appeal of Florida, Fifth District.
*823 Michael R. Riemenschneider and William H. Cantwell, II of O'Brien Riemenschneider, *824 P.A., Melbourne, for Appellant/Cross-Appellee.
David H. Simmons and Kenneth P. Hazouri of Drage, de Beaubien, Knight, Simmons, Mantzaris & Neal, Orlando, for Appellee/Cross-Appellant.
PALMER, J.
In this residential construction lawsuit Lasco Enterprises, Inc. appeals, and Ronald and Kathleen Kohlbrand cross-appeal, the final order entered by the trial court which, in accordance with the jury's verdict, awarded neither party any damages on their countervailing claims. We affirm.
The parties entered into a contract whereby Lasco agreed to construct a home for the Kohlbrands. During construction, disputes arose between the parties regarding the construction schedule, the quality of the construction, and the amounts owed under the contract. Before construction was completed, but well beyond the date on which the contract was to have been completed, the Kohlbrands terminated the contract and refused to pay the monies demanded by Lasco as being due under the contract. Lasco responded to such refusal by filing a claim of lien against the Kohlbrands' home.
Lasco subsequently filed the instant action seeking to foreclose on its construction lien and asserting claims of breach of contract and quantum meruit. The Kohlbrands denied liability, asserted affirmative defenses, and set forth counterclaims alleging the recording of a fraudulent claim of lien, breach of contract based on construction deficiencies, breach of contract based on delay in the construction, negligent misrepresentation, and unjust enrichment.
During a nine day jury trial, Lasco abandoned its claim for quantum meruit and the trial court directed verdicts against the Kohlbrands on their claims for negligent misrepresentation and unjust enrichment. Accordingly, the claims which were submitted to the jury for resolution were Lasco's claims for lien foreclosure and breach of contract, and the Kohlbrands' counterclaims for fraudulent lien and breach of contract. The jury returned a special verdict finding that the Kohlbrands did not breach the contract with Lasco, that Lasco's claim of lien was not fraudulent, and that the amount of damages which the Kohlbrands sustained as a result of any breach of contract by Lasco was $0. After the verdict was returned but before the final judgment was entered, the trial court conducted a hearing on each party's motion for attorney's fees. Attorney's fees were sought based upon the applicable lien statute[1] and the prevailing party attorney fee provision in the parties' construction contract. The trial court ruled that the Kohlbrands were entitled to recover fees in connection with their defense of the lien foreclosure claim and that Lasco was entitled to recover its costs with regard to the Kohlbrands' fraudulent lien claim. The court further found that since the jury's verdict could be interpreted as meaning that neither party had been found to have breached the terms of the construction contract, neither party was entitled to recover prevailing party attorney's fees. Lasco filed a timely notice of appeal and the Kohlbrands timely filed their notice of cross-appeal.
Lasco raises three issues on appeal: 1) whether the trial court erred in denying its motion for a directed verdict on the Kohlbrands' counterclaims; 2) whether the trial court erred in instructing the jury regarding the duty of care owed to the Kohlbrands under the parties' contract; and 3) *825 whether the trial court erred in denying its claim for attorney's fees on the breach of contract claims.
As to the denial of the motion for directed verdict, Lasco contends it was entitled to receive a directed verdict as to all three counts of the Kohlbrands' counterclaim. However, Lasco has failed to provide this court with a record to support this claim.
"A party moving for a directed verdict admits the truth of all facts in evidence and every reasonable conclusion or inference which can be drawn from such evidence favorable to the non-moving party." Williamson v. Superior Insurance Co., 746 So.2d 483 (Fla. 2d DCA 1999). In challenging a trial court's denial of a motion for a directed verdict, the burden is on the appellant to show that the trial court erred in so ruling. See Applegate v. Barnett Bank of Tallahassee, 377 So.2d 1150, 1152 (Fla.1979). Lasco has failed to sustain its burden of proving error on this issue due to the fact that it failed to provide this court with a complete copy of the trial transcript. See All American Soup & Salad, Inc. v. Colonial Promenade, 652 So.2d 911 (Fla. 5th DCA 1995)(holding that, by failing to provide complete transcript, appellant failed to meet burden of establishing reversible error to overcome presumption of correctness afforded to trial court's decision).
Lasco maintains that, even without a trial transcript, this court can properly review the trial court's decision denying Lasco's directed verdict motion because the ruling involves a question of law, not a question of fact. Lasco explains that its motion for a directed verdict was based in part, upon the following remedy provision set forth in the parties' contract:
D. Default by Builder. If a builder fails to perform under this Contract then Owner may proceed in equity to enforce Owner's rights under this Contract by an action for specific performance; or Owner may elect to receive the return of earnest money deposit.
Lasco contends that it was entitled to receive a directed verdict on the Kohlbrands' counterclaims because, pursuant to this provision, the Kohlbrands were prohibited from seeking recovery of money damages. We disagree.
First, the remedy provision was not applicable to the Kohlbrands' fraudulent lien claim, because the claim did not arise "under this contract." In addition, as to all of the Kohlbrands' breach of contract claims, the language of paragraph D did not place a limitation upon their available remedies, but instead, simply provided that the Kohlbrands "may" proceed in equity to enforce its rights or "may" elect to receive the return of earnest money deposit. The provision does not state that the Kohlbrands "shall" limit themselves to such remedies.[2]
Lasco next argues that the trial court reversibly erred in instructing the jury regarding the duty of care which it owed to the Kohlbrands under the terms of the parties' contract. We find no reversible error.
Decisions regarding jury instructions are within the sound discretion of the trial court and should not be disturbed on appeal absent a showing of prejudicial error. Klipper v. Gov't. Employees Ins. Co., 622 So.2d 1141 (Fla. 2d DCA 1993). The jury instruction in dispute here read as follows:
*826 The contractor is not responsible for errors or omissions in design supplied by owner or on owner's behalf unless he knew or had reason to know of such errors.
(Emphasis added).
Lasco contends that by including the language which is highlighted in bold print, the trial court misstated the applicable facts and the applicable law.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
819 So. 2d 821, 2002 WL 832021, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lasco-enterprises-inc-v-kohlbrand-fladistctapp-2002.