Kellogg & Kimsey, Inc. A Florida Corporation v. Progressive Plumbing, Inc.

CourtUnited States Bankruptcy Court, M.D. Florida
DecidedSeptember 30, 2019
Docket6:17-ap-00044
StatusUnknown

This text of Kellogg & Kimsey, Inc. A Florida Corporation v. Progressive Plumbing, Inc. (Kellogg & Kimsey, Inc. A Florida Corporation v. Progressive Plumbing, Inc.) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, M.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kellogg & Kimsey, Inc. A Florida Corporation v. Progressive Plumbing, Inc., (Fla. 2019).

Opinion

ORDERED.

Dated: September 30, 2019 C) oP Ae A of, are S. Jennemann United States Bankrupt ke

UNITED STATES BANKRUPTCY COURT MIDDLE DISTRICT OF FLORIDA ORLANDO DIVISION www.flmb.uscourts.gov In re ) ) PROGRESSIVE PLUMBING, INC., ) Case No. 6:15-bk-07275-KSJ PROGRESSIVE SERVICES, LLC and ) Chapter 11 GRACIOUS LIVING DESIGN ) CENTER, INC. ) ) JOINTLY ADMINISTERED Debtors. ) Case No.: 6:15-BK-07276-KSJ ) Case No.: 6:15-BK-07277-KSJ ) ) KELLOGG & KIMSEY, INC., ) A Florida Corporation, Plaintiff, ) ) VS. ) Adversary No. 6:17-ap-00044-KSJ ) PROGRESSIVE PLUMBING, INC., ) A Florida Corporation, ALLIED WORLD _ ) SPECIALTY INSURANCE COMPANY, _ ) a Foreign Profit Corporation, ) ) ) Defendants. ) ) ) ) PROGRESSIVE PLUMBING, INC., Counter- Plaintiff, )

) KELLOG & KIMSEY, INC., ) ) Counter-Defendant. ) ) ) PROGRESSIVE PLUMBING, INC., ) ) Counter-Plaintiff, ) ) vs. ) ) ALLIED WORLD SPECIALTY ) INSURANCE COMPANY, ) ) Cross-Defendant. ) ) ) ALLIED WORLD SPECIALTY ) INSURANCE COMPANY, ) ) Cross-Plaintiff, ) ) vs. ) ) PROGRESSIVE PLUMBING, INC., ) ) Cross-Defendant. ) ) )

MEMORANDUM OPINION

The primary issue is who breached a construction contract and what are the damages in this dispute between a general contractor, Plaintiff Kellogg & Kimsey, Inc. (“K&K”), and its plumbing subcontractor, the Debtor Progressive Plumbing, Inc. (“Progressive”). After a five day trial,1 at least two failed attempts at mediation, reviewing hundreds of exhibits, and reading 19 deposition transcripts, I conclude that both K&K and Progressive breached the agreement and K&K owes Progressive $175,840.13, but that neither party prevailed or may recover attorneys’ fees or pre-judgment interest. K&K brought this adversary proceeding against Progressive and Allied World Specialty Insurance Company (“Allied”), who issued the underlying payment and performance bond (the

“Bond”), claiming it is owed damages of approximately $450,000 arising from a breach of a construction subcontract and the Bond. Progressive filed a counterclaim against K&K alleging breach of contract, violation of Tennessee’s Prompt Pay Act, Ten. Code § 66-34-101, et seq., and tortious interference with a business relationship seeking around $300,000. Allied filed a counterclaim seeking subrogation and declaratory judgment.2 Progressive is a commercial plumbing company based in Clermont, Florida. In February 2013, Progressive subcontracted (“Subcontract”)3 with Sarasota, Florida based general contractor K&K to provide plumbing services and materials to a new construction project already underway in downtown Nashville, Tennessee (the “Project”).4 The Project involved building two adjacent Marriott-branded hotels—a Residence Inn and a Springhill Suites. Allied issued its Bond to

guarantee Progressive’s performance of the Subcontract for $1,750,000.5 The Project broke ground in January 2013. Progressive signed the Subcontract in February 2013. And Progressive employees arrived on site and into a construction maelstrom in March 2013.6 The Project was jinxed from the start with forces outside the control of either K&K or Progressive. Nashville was experiencing a building boom in 2013. The city was returning to prosperity after the recession of 2008, but with a greatly reduced labor pool. Skilled construction

2 Allied and Progressive also have crossclaims against each other. Doc. Nos. 12, 20, 35. Because these crossclaims are dependent on the resolution of the issues between K&K and Progressive, they were not ripe for resolution during the trial. Doc. No. 147. A future status conference will address these remaining issues and crossclaims will be held at 2:00 p.m. on January 7, 2020. 3 Progressive’s Exh. 1. The Subcontract was signed on February 22, 2013. 4 K&K signed the primary construction contract with the owner, Ace Hospitality, Inc., on October 1, 2012. K&K’s Exh. 1. 5 K&K’s Exh. 4. The Bond was issued on March 26, 2013. talented workers often settling for inferior labor options. And, just as this Project was about to break ground in early 2013, Nashville experienced

extreme winter weather causing significant construction delays. On top of this, the City of Nashville was a difficult working partner and was slow to issue permits or to inspect work. Utility service connections were delayed. Marriott also caused further delays by failing to timely specify design and material requirements causing change orders and design alterations late in the construction process. For example, the plans did not include details and Marriott’s design team did not timely specify acceptable shower heads until Progressive already had purchased its choice. Every construction project is unique and brings unexpected problems. But this Project was fraught with an extraordinary number of hurdles. Neither K&K nor Progressive responded as quickly or professionally as needed to stop these problems from snowballing into a catastrophe, which is what ensued.

Both parties, however, soldiered on with the Project. K&K was frustrated with the speed and quality of Progressive’s plumbing work (and the work of other subcontractors) but K&K never asked Progressive to leave the site. No default was declared until November 26, 2014,8 when construction was almost complete. K&K obtained a temporary certificate of occupancy for the two hotels on January 28, 2015.9 So, the Project was completed; but Progressive’s outstanding change orders and contract balance was never paid. This end-of-project accounting and reconciliation remained unfinished when Progressive filed its Chapter 11 bankruptcy petition on August 24, 2015.10 K&K filed an unsecured proof of claim [Claim 35-1] for an outlandishly overstated amount of $813,547.94.11 Parties went to

7 Progressive’s Exh. 48; 51; 54; 57; 61. 8 K&K’s Exh. 414. 9 9/24/18 Tr. at 102. 10 Doc. No. 1 in Main Case No. 6:15-bk-07275-KSJ. of the Subcontract and the Bond and seeks $451,822.60.12 Progressive filed a counterclaim also alleging breach of the Subcontract and seeks $303,087.01.13 Progressive also objected to K&K’s Claim 35-1,14 which was consolidated with the trial. The parties submitted post-trial closing

arguments,15 and the job now falls to the Court to determine who breached the Subcontract and what damages are due and by whom. I first will find that both K&K and Progressive breached the Subcontract and then delve into the details of the damage award. K&K Failed to Maintain a Practicable Schedule K&K, as the general contractor, had and breached its primary responsibility to maintain a practicable schedule so the trades working on the Project did not overcrowd one another and so they could access work areas in a proper sequence. The source of K&K’s duty is in paragraph 5 of the Subcontract that confirms that K&K is to prepare, maintain, and update the work schedule for the Project.16 And, if Progressive violated this work schedule, the Subcontract allowed K&K to

declare a default and impose damages.17 Article 3.10.1 of the prime contract between the Owner, ACE Hospitality, Inc. and K&K, which is referenced in the Subcontract, similarly confirms K&K’s obligation to properly and timely schedule the work of all trades completing work on the Project.18 K&K did prepare work schedules at the beginning of the Project. The Subcontract, for example, attached the initial work schedule, Schedule D, dated January 17, 2013. This original schedule contemplated a completion date of July 16, 2014.19 The Project, as discussed earlier, was marked by a “volume of large anomalies never before encountered.”20 By the time Progressive

12 K&K’s Post-Trial Submission, Doc. No. 257 at 20. 13 Doc. No. 160, Exh. 2. 14 Doc. No. 157, ¶1(a); Doc. No. 448 in Main Case No. 6:15-BK-07275-KSJ. See also Progressive’s Closing Argument Brief, Doc. No. 259; Allied’s Closing Argument Brief, Doc. No. 258. 15 Doc. Nos. 257; 258; 259. 16 Progressive’s Exh. 1, ¶ 5. 17 Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Blasland, Bouck & Lee, Inc. v. City of North Miami
283 F.3d 1286 (Eleventh Circuit, 2002)
Sholkoff v. BOCA RATON COMMUNITY HOSP.
693 So. 2d 1114 (District Court of Appeal of Florida, 1997)
Trytek v. Gale Industries, Inc.
3 So. 3d 1194 (Supreme Court of Florida, 2009)
KCIN, INC. v. Canpro Investments, Ltd.
675 So. 2d 222 (District Court of Appeal of Florida, 1996)
Gibbs Const. Co. v. SL Page Corp.
755 So. 2d 787 (District Court of Appeal of Florida, 2000)
Brevard County Fair Ass'n, Inc. v. Cocoa Expo, Inc.
832 So. 2d 147 (District Court of Appeal of Florida, 2002)
Merchants Bonding Co. v. City of Melbourne
832 So. 2d 184 (District Court of Appeal of Florida, 2002)
Hutchinson v. Hutchinson
687 So. 2d 912 (District Court of Appeal of Florida, 1997)
Broward County v. Finlayson
555 So. 2d 1211 (Supreme Court of Florida, 1990)
Federal Ins. Co. v. Exel of Orlando, Inc.
685 So. 2d 896 (District Court of Appeal of Florida, 1996)
Lasco Enterprises, Inc. v. Kohlbrand
819 So. 2d 821 (District Court of Appeal of Florida, 2002)
System Components Corp. v. Florida Deparment of Transportation
14 So. 3d 967 (Supreme Court of Florida, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
Kellogg & Kimsey, Inc. A Florida Corporation v. Progressive Plumbing, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/kellogg-kimsey-inc-a-florida-corporation-v-progressive-plumbing-inc-flmb-2019.