Eichberger v. Folliard

523 N.E.2d 389, 169 Ill. App. 3d 145, 119 Ill. Dec. 781, 1988 Ill. App. LEXIS 629
CourtAppellate Court of Illinois
DecidedMay 6, 1988
Docket2-87-0681
StatusPublished
Cited by3 cases

This text of 523 N.E.2d 389 (Eichberger v. Folliard) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eichberger v. Folliard, 523 N.E.2d 389, 169 Ill. App. 3d 145, 119 Ill. Dec. 781, 1988 Ill. App. LEXIS 629 (Ill. Ct. App. 1988).

Opinion

JUSTICE REINHARD

delivered the opinion of the court:

Plaintiffs, Anthony and Frances Eichberger, filed suit, in the circuit court of Lake County seeking damages allegedly arising out of the construction of their new home by defendant, Kenneth J. Folliard, d/b/a K.J.F. Builders. Defendant filed, a counterclaim seeking damages for unpaid amounts on the construction contract. The trial court granted defendant’s motion for directed verdict on plaintiff’s action, and the jury returned a verdict in favor of plaintiff on defendant’s counterclaim. Plaintiff appeals the granting of the directed verdict in favor of defendant, and defendant cross-appeals the jury verdict in favor of plaintiff.

The two issues presented in this appeal are whether the trial court erred in directing a verdict in favor of defendant and whether the jury verdict in favor of plaintiff was against the manifest weight of the evidence.

Plaintiffs filed the instant action in the circuit court of Lake County. Following dismissal of two counts of their second amended complaint, the remaining count of the second amended complaint alleged that defendant breached express warranties of the construction contract in that he failed to construct the home in a workmanlike manner and in conformance with local building codes. Defendant filed a counterclaim seeking as damages payment for the full contract price plus payment for extra work performed under the contract.

Plaintiffs purchased two adjacent lots in late 1983 or early 1984 for the purpose of having a home built on the lots. The lots abut a channel of water and are in a flood plain. There are various homes built on neighboring property on both sides of the channel.

In January 1984, plaintiff Anthony Eichberger contacted defendant after he learned that defendant was constructing a home on the opposite side of the channel. Plaintiff subsequently met with defendant for the purpose of discussing the construction of a home on plaintiffs’ lots. Upon inquiry by plaintiff, defendant stated that he had been building in the area for approximately 10 years.

Following their initial meeting, plaintiff and defendant met on several occasions. Plaintiffs obtained building plans for a residence which they liked and asked defendant to change them to suit their desires. Eventually, defendant supplied plaintiff with modified building plans which both parties agreed would be used in building the home. On June 6, 1984, the parties entered into a written contract to build a home on plaintiffs’ property. The contract contained the express warranty that “[w]e agree to perform all work as shown on the drawing in a workmanlike manner.” The contract, which was prepared by defendant, prescribed 24-inch-wide footings.

During the preparation of the land and the construction of the home, plaintiff made numerous visits to the construction site. Plaintiff testified on direct examination that he visited the site while it was being cleared and graded and that he felt the ground shake during the leveling process. He asked defendant, “Is this going to be suitable for a house?” to which defendant replied, “Don’t worry about it. We put in an extra-wide footing, and you will have no problems with the house, you know, sinking or anything.” Approximately three to four days later, plaintiff again visited the home site and expressed concern to defendant about the suitability of the soil for building a home. According to plaintiff, defendant responded that he was aware of building in the area and that the house might sink, and that is why they used extra-wide footings.

Construction on the home continued into August 1984. At that time, workers who were installing carpet and floor tile advised plaintiff that the floors were sloping in some of the rooms of the home. Plaintiff testified that the home was about 90% complete at this time. Plaintiff proceeded to check the floors with a carpenter’s level and discovered a slope in all rooms of the home, with the most severe being a SVa-inch slope in the front room.

Plaintiff contacted defendant the following day to advise him of the problem. Defendant responded that he was aware of the problem and would fix it. Plaintiff testified that defendant raised up the floor to level it, but that resulted in one of the walls being four inches shorter than the opposite wall. According to plaintiff, defendant took no other measures to remedy the sloping problem. Plaintiff also observed cracks in the foundation, cracks and slanting in the kitchen counter top, slanting of the oven and refrigerator, cracks in the wall board, cracks in the ceiling, difficulty in closing some doors, rain gutters that flowed away from the drain pipe, and inside drains that did not drain properly.

Plaintiff stated that he made all payments on the contract except the last two. As a result, on several occasions, defendant demanded full payment, but plaintiff refused to pay until the problems were corrected. According to plaintiff, defendant did no more work on the home, and plaintiff never made the final two payments under the contract.

In addition to the foregoing, plaintiff also presented two expert witnesses. Mr. Gerald Kissner, a soil engineer, stated that, based upon two soil boring samples taken from plaintiffs’ property, the soil was not suitable for building a home unless pile foundations were used. He also stated that soil boring testing is necessary to determine if pile foundations are needed.

Mr. William Hooper, a structural engineer and architect, also testified on behalf of plaintiffs. Mr. Hooper conducted a physical examination of the home and stated at trial that the home had undergone differential settling which had caused the various problems which plaintiffs complained of. He also opined that the type of foundation utilized by defendant is not suitable for the soil types present on plaintiffs’ property and, therefore, the house was not constructed in a workmanlike manner.

Following completion of plaintiffs’ case, the trial court directed a verdict in favor of defendant. In doing so, the court stated that no evidence was presented as to the issue of conformity with local building codes. Furthermore, the court explained that the evidence offered by plaintiff failed to establish that defendant did not build the home in a workmanlike manner. The court noted that evidence of deficiencies in the soil composition, absent a contractual agreement that defendant have the soil tested, did not prove a lack of workmanlike performance under the contract.

The case continued on defendant’s counterclaim, and the jury returned a verdict in favor of plaintiffs. Plaintiffs now appeal the directed verdict on the issue of whether defendant performed in a workmanlike manner, but do not appeal the issue of whether the home conforms to local building codes. Defendant cross-appeals the jury verdict in favor of plaintiffs on the counterclaim.

We begin with defendant’s cross-appeal. Defendant raises this point in a short two-sentence paragraph that is devoid of any citation of authority or reasoned argument. As such, we find this cursory statement of the issue does not sufficiently present the question for review, and the contention is waived pursuant to Supreme Court Rule 341(e)(7) (113 Ill. 2d R. 341(e)(7); see People ex rel. Aldworth v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lasco Enterprises, Inc. v. Kohlbrand
819 So. 2d 821 (District Court of Appeal of Florida, 2002)
Groenings v. City of St. Charles
574 N.E.2d 1316 (Appellate Court of Illinois, 1991)
Shorr Paper Products, Inc. v. Aurora Elevator, Inc.
555 N.E.2d 735 (Appellate Court of Illinois, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
523 N.E.2d 389, 169 Ill. App. 3d 145, 119 Ill. Dec. 781, 1988 Ill. App. LEXIS 629, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eichberger-v-folliard-illappct-1988.