Fanderlik-Locke Co. v. United States

285 F.2d 939, 40 Lab. Cas. (CCH) 66,547
CourtCourt of Appeals for the Tenth Circuit
DecidedNovember 30, 1960
DocketNo. 6144
StatusPublished
Cited by30 cases

This text of 285 F.2d 939 (Fanderlik-Locke Co. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fanderlik-Locke Co. v. United States, 285 F.2d 939, 40 Lab. Cas. (CCH) 66,547 (10th Cir. 1960).

Opinions

PICKETT, Circuit Judge.

This is a Miller Act case, 40 U.S.C.A. § 270a, et seq., in which a subcontractor1 seeks to recover, from a prime contractor and its bondsman, the value of labor performed and materials installed in addition to that provided for in the subcontract. It was alleged that, during the performance of the subcontract, required labor and materials were furnished, together with extras and additional work, at the request of the prime contractor, to the aggregate amount of $183,259.20; that the subcontractor had received $53,-371; and that the balance due was $129,-888.20. The court found that there was due and owing to the subcontractor the sum of $110,713.60, for the performance of the subcontract and for additions and extras furnished at the request of the prime contractor. Judgment was entered accordingly, together with interest. Upon consideration of an appeal, we reversed the judgment upon the ground that the subcontractor had not exhausted its administrative remedies as required by the “disputes clause” in the prime contract. We have reconsidered this question on rehearing, and the former opinion is hereby withdrawn.

Fanderlik entered into a contract with the United States wherein it agreed to construct 175 dwelling units at Clovis Air Force Base in Curry County, New Mexico. As required by the Miller Act, Fanderlik delivered to the United States a payment bond, executed by Grand American Indemnity Company, which guaranteed the payment of all sums due to persons supplying labor and materials in the performance of the requirements of the contract. Thereafter, for a consideration of $63,630, a subcontract was awarded to the plaintiff, M. B. Morgan, d/b/a M. B. Morgan, Painting Contractor, wherein Morgan agreed to furnish all labor, materials and equipment necessary to complete the painting requirements of the prime contract. During the performance of the subcontract, there were failures of paint which had been applied to both interior and exterior surfaces and all of the surfaces upon which the paint failed were repainted by Morgan upon the demand of Fanderlik and the architects supervising the job. There was also considerable repainting required because of storm damage and for other reasons. Morgan submitted claims to Fanderlik for this additional work.

The prime contract was the standard form of government construction contract in general use at the time of its execution. Section 6 of the general provisions thereof, states:

“Except as otherwise provided in this contract, any dispute concerning a question of fact arising under this contract which is not disposed of by agreement shall be decided by the Contracting Officer, who shall reduce his decision to writing and mail or otherwise furnish a copy thereof to the Contractor. Within 30 days from the date of receipt of such copy, the Contractor may appeal by mailing or otherwise furnishing to the Contracting Officer a written appeal addressed to the head of the department, and the decision of the head of the department or his duly authorized representatives for the hearings of such appeals shall, unless determined by a court of competent jurisdiction to have been fraudulent, arbitrary, capricious, or so grossly erroneous as necessarily to imply bad faith, be final and conclusive: Provided, That, if no such appeal to the head of the department is taken, the decision of the Contracting Officer shall be final and conclusive * *

Upon receipt of Morgan’s claims, the prime contractor, following the procedure of Section 6, submitted corresponding claims to the Contracting Officer at Clovis Air Force Base. They were all [942]*942denied by the Contracting Officer, and, at the time of the trial, an appeal was pending before the Board of Contract Appeals of the Air Force. The Fanderlik claims to the Contracting Officer included those upon which recovery is sought in this action.

The subcontract provided that the subcontractor should furnish material and perform labor in accordance with the general conditions of the contract between the owner and the contractor and .“in accordance with the Drawings and the Specifications attached hereto which form a part of a Contract between the Contractor and the Owner * * * and hereby become a part of this Contract.” The parties to the subcontract agreed “to be bound by the terms of this Agreement, the A.I.A. General Conditions attached, the drawings and specifications attached as far as apprehensible to this subcontract * * It was further provided that the subcontractor should be bound to the contractor “by the terms of the Agreement, General Conditions, Drawings and Specifications, and to assume toward him all the obligations and responsibilities that he, by those documents, assumes toward the Owner.”

It is contended that by these references, Section 6 of the general provisions of the prime contract was incorporated in the subcontract, and that a suit under the Miller Act cannot be maintained by the subcontractor until there is a final determination of the claims submitted under Section 6. While we express no opinion as to the right of the parties to enter into an agreement which might circumvent the Miller Act, we hold that it was not the intention of the parties to the subcontract that the subcontractor was required to comply with the provisions of Section 6 before it could maintain an action under the Miller Act.

The purpose of the Miller Act is to provide- security for those who furnish labor and material in the performance of government contracts, and a liberal construction should be given the Act to accomplish this purpose. United States for Benefit of Sherman v. Carter, 353 U.S. 210, 77 S.Ct. 793, 1 L.Ed. 2d 776; St. Paul-Mercury Indem. Co. v. United States, 10 Cir., 238 F.2d 917; Fourt v. United States, 10 Cir., 235 F.2d 433; Commercial Standard Ins. Co. v. United States, 10 Cir., 213 F.2d 106. The benefits of the Act are not intended for the prime contractor who is required by the Act to furnish a bond to effectuate its provisions. If a prime contractor is dissatisfied with the administrative disposition of a claim submitted under the “disputes clause” of the prime contract, it may seek a remedy in the Court of Claims. The liability of the United States is to the prime contractor, and the “disputes clause” provides only for administrative consideration of claims made by the prime contractor.

There is no procedure by which the claim of a subcontractor can be presented against the United States except as it may become a claim of the prime contractor, since there is no contract, express or implied, between the subcontractor and the government. United States v. Blair, 321 U.S. 730, 737, 64 S.Ct. 820, 88 L.Ed. 1039. The subcontractor has no standing before the Contracting Officer or the Board of Contract Appeals, and no provision is made for the hearing of disputes between a prime contractor and a subcontractor. The remedy for one seeking to recover for labor and materials furnished on a government contract is under the Miller Act, and ordinarily the fact that a prime contractor has a claim for the same amounts pending under the “disputes clause” of the prime contract, does not affect Miller Act cases.2

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Zurich American Insurance
99 F. Supp. 3d 543 (E.D. Pennsylvania, 2015)
Shutts v. Phillips Petroleum Co.
732 P.2d 1286 (Supreme Court of Kansas, 1987)
No. 76-1594
574 F.2d 497 (Tenth Circuit, 1978)
Keller v. California Liquid Gas Corporation
363 F. Supp. 123 (D. Wyoming, 1973)
Hensel Phelps Construction Co. v. United States
413 F.2d 701 (Tenth Circuit, 1969)
Fett Roofing & Sheet Metal Co. v. Seaboard Surety Co.
294 F. Supp. 112 (E.D. Virginia, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
285 F.2d 939, 40 Lab. Cas. (CCH) 66,547, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fanderlik-locke-co-v-united-states-ca10-1960.