Continental Casualty Co. v. Schaefer

173 F.2d 5, 1949 U.S. App. LEXIS 3672, 16 Lab. Cas. (CCH) 64,984
CourtCourt of Appeals for the Ninth Circuit
DecidedFebruary 11, 1949
Docket11707
StatusPublished
Cited by84 cases

This text of 173 F.2d 5 (Continental Casualty Co. v. Schaefer) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Continental Casualty Co. v. Schaefer, 173 F.2d 5, 1949 U.S. App. LEXIS 3672, 16 Lab. Cas. (CCH) 64,984 (9th Cir. 1949).

Opinion

DENMAN, Chief Judge.

The several Macris, hereafter so called, contractors on a government contract under the Miller Act, 1 appeal from a judgment in favor of Schaefer, their subcontractor, for labor and materials furnished in the performance of a subcontract and modification thereof.

Continental Casualty Company, hereafter called Continental, appeals from a judgment against it as surety on the contract between the Macris and the United States, described infra, in favor of Schaefer for the amount of the judgment against the Macris.

The Macris do not contend that they are not liable for an unpaid balance on the *7 contract price included in the judgment, but contend they are not liable for more than the contract price. They contend that the evidence does not support the court’s finding that they breached the subcontract and, on the contrary, that the extra work done by Schaefer was in the performance of that contract. Continental’s appeal urges these grounds and, in addition, that in any event a surety under the Miller Act is not liable for more than the value of the labor and materials to be supplied under the contract. Continental also seeks to recover here additional attorney’s fees for prosecuting this appeal.

The dispute between Schaefer and the Macris arises out of the performance of a subcontract tO' do the cement work on the federal irrigation project known as the Roza Division, Yakima Project, near Yakima, Washington. Schaefer sued to recover $57,618.87 as the alleged unpaid balance of the reasonable value of the work, labor and expenses on a quantum meruit theory after the alleged breach of a contract by the Macris. The subcontract between Schaefer and the Macris provided that Schaefer was to furnish “all labor and necessary equipment to do all of the concrete work, form work, cut, bend and install all reinforcing steel, all such work as shown on the plans as specified [in certain numbered specifications].”

The trial court, sitting without a jury, found that the Macris were to perform all of the excavating and to furnish all of the materials necessary for the performance of the subcontract with the exception of form wire, nails and curing materials. The excavating and materials were to be furnished in accordance with specifications and in proper time for the performance of the subcontract by Schae-fer. The court further found that Schae-fer’s performance was diligent, but that the Macris had breached the subcontract in that they failed to make the excavations in the proper manner so that Schaefer’s carpenters had to make extra excavations in order to install the forms. The Macris also failed to do the fine grading in the proper manner and in time for Schaefer to proceed with prompt progress of the work. The Macris also failed to furnish the proper quality and quantity of lumber required, which hindered and delayed Schaefer in the performance of his work. Macris’ breaches were found willful and negligent and they continued and persisted throughout the entire performance of the subcontract.

The court further found that Schaefer had made many complaints to the Macris regarding the latter’s defaults; that the Macris induced Schaefer to continue performance and to perform some of the work the Macris were to do, and that Schaefer would be compensated for the additional expense because of the adverse conditions created by the Macris. The court found that “there was an implied agreement or quasi-contract that * * * Schaefer was to be paid the fair and reasonable value of his subcontract under the conditions and with the extra burdens imposed upon [Schaefer by the Macris’ breaches].”

The subcontract contained a provision that in order to obtain extra compensation written notices and statements were required. The court found that the Macris had waived this provision by their conduct toward Schaefer by accepting and acting upon the oral notices given.

Judgment was rendered in favor of Schaefer against the Macris and Continental for $56,764.97, with interest from date of judgment. Also, a judgment in that same amount was rendered in favor of Continental against the Macris, plus $1750 for Continental’s attorneys’ fees. Continental and the Macris both appeal from the judgments, and Continental asks for additional attorneys’ fees from the Macris to cover the prosecution of this appeal.

A. The Law Governing the Several Issues.

On the issue of the Macris’ liability to Schaefer, we think that the Washington law should govern. While federal jurisdiction is conferred by the Miller Act and not by diversity of citizenship, we feel that the reasons underlying the doctrine of Erie Ry. Co. v. Tompkins, 304 U.S. 64, 58 S.Ct. 817, 82 L.Ed. 1188, 114 A.L.R. 1487, are applicable *8 here, where the issue does not involve construction or application of a federal statute. Blair v. United States, 8 Cir., 147 F.2d 840, 849. Cf. Goerig v. Continental Casualty Co., 9 Cir., 167 F.2d 930. The rights and liabilities of the parties under the subcontract should not depend on the choice of forum sought to enforce these rights. Cf. Guaranty Trust Co. v. York, 326 U.S. 99, 109, 65 S.Ct. 1464, 89 L.Ed. 2079, 160 A.L.R. 1231. Hence we should decide this issue as would a state court sitting in Washington. Since all the relevant facts regarding this subcontract have occurred in Washington, the Washington substantive law of contracts is applicable. Hatcher v. Idaho Gold & Ruby Mining Co., 106 Wash. 108, 113, 179 P. 106.

On the issue of Continental’s liability on the payment bond, the federal law should control because the determination of the extent of the liability involves the construction of • a federal statute, the Miller Act, under which it was created, Liebman v. United States, 9 Cir., 153 F.2d 350.

B. Macris’ Liability to Schaefer.

The district court held that there was an “implied agreement or quasi-contract” to the effect that the Macris would pay Schaefer the fair and reasonable value of his subcontract under the conditions and with the extra burdens imposed upon Schaefer by the Macris’ breach and failure to perform their part of the subcontract. The Macris claim there is no substantial evidence to support the finding that they breached the subcontract. While the testimony is conflicting, the record contains sufficient evidence to support the finding, and this court will not weigh the evidence in such a case. Federal Rules of Civil Procedure, rule 52 (a), 28 U.S.C.A. We cannot say that this finding is clearly erroneous.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Blakeslee Arpaia Chapman, Inc. v. EI Constructors, Inc.
687 A.2d 506 (Supreme Court of Connecticut, 1997)
Mai Steel Service Inc. v. Blake Construction Co.
981 F.2d 414 (Ninth Circuit, 1992)
W.F. Magann Corp. v. Diamond Manufacturing Co.
580 F. Supp. 1299 (D. South Carolina, 1984)
United States v. Mountain States Construction Co.
588 F.2d 259 (Ninth Circuit, 1978)
Richmond Elks Hall Ass'n v. Richmond Redevelopment Agency
389 F. Supp. 486 (N.D. California, 1975)
Glassman Const. Co., Inc. v. Maryland City Plaza, Inc.
371 F. Supp. 1154 (D. Maryland, 1974)
Elte, Inc. v. S. S. Mullen, Inc.
469 F.2d 1127 (Ninth Circuit, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
173 F.2d 5, 1949 U.S. App. LEXIS 3672, 16 Lab. Cas. (CCH) 64,984, Counsel Stack Legal Research, https://law.counselstack.com/opinion/continental-casualty-co-v-schaefer-ca9-1949.