United States ex rel. T.M.S. Mechanical Contractors, Inc. v. Millers Mutual Fire Insurance

942 F.2d 946, 1991 WL 172936
CourtCourt of Appeals for the Fifth Circuit
DecidedSeptember 25, 1991
DocketNo. 90-8292
StatusPublished
Cited by21 cases

This text of 942 F.2d 946 (United States ex rel. T.M.S. Mechanical Contractors, Inc. v. Millers Mutual Fire Insurance) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States ex rel. T.M.S. Mechanical Contractors, Inc. v. Millers Mutual Fire Insurance, 942 F.2d 946, 1991 WL 172936 (5th Cir. 1991).

Opinion

GOLDBERG, Circuit Judge:

The facts in this Miller Act case present a question of law: whether the delay and termination components of the subcontractor’s Miller Act claim constitute “labor or material [furnished] in the prosecution of the work provided for in [the] contract.” 40 U.S.C.A. § 270b(a) (1986).

Plaintiff T.M.S. Mechanical Contractors, Inc., subcontractor on a government construction project, appeals from a judgment denying its delay and termination claims against Miller Act surety Millers Mutual Fire Insurance Company of Texas. Defendant Millers Mutual Fire Insurance Company of Texas cross-appeals from a judgment of $100,104.19 plus interest and costs awarded to the Plaintiff on its contract work claim.

I. FACTS AND PROCEDURAL HISTORY

The Craftsmen, Inc. (“Craftsmen”) contracted with the Veterans Administration (“Government”) on April 5,1984 to perform fire and safety corrections on the Veterans Administration Medical Center in Waco, Texas (“Contract”). Craftsmen secured a payment bond from Millers Mutual Fire Insurance Company of Texas (“Millers”), as required by 40 U.S.C.A. § 270a(a) (1986)1 (“Bond”).

Craftsmen subcontracted all the mechanical work under the Contract to T.M.S. Mechanical Contractors, Inc. (“TMS”) on May 4, 1984 (“Subcontract”). The Subcontract incorporated the Contract’s plans, specifications, and general conditions of the specifications. TMS based its Subcontract price of $727,000 on a bid that considered the value of the labor and materials necessary to complete the Subcontract work, overhead, profit, tools and equipment, labor burden, insurance costs, food, and shelter.

[b]efore any contract, exceeding $25,000 in amount, for the construction, alteration, or repair of any public building or public work of the United States is awarded to any person, such person shall furnish to the United States the following bonds, which shall become binding upon the award of the contract to such person. ... (2) A payment bond with a surety or sureties satisfactory to such officer [awarding the contract] for the protection of all persons supplying labor and material in the prosecution of the work provided for in said contract for the use of each such person.

After discovering asbestos in some of the buildings involved in the performance of the Contract, the Government issued change orders enlarging the scope of the Contract work to include asbestos abatement. The' Government partially terminated the Contract on October 10, 1985 pursuant to paragraph 18 of the Contract, entitled “Termination for Convenience of the Government.”2

Upon receipt of a Notice of Termination from the Government, Craftsmen in turn terminated the Subcontract. At that time, TMS had provided $387,735.00 worth of labor and materials in the performance of the Subcontract and $485,845.90 in the performance of the change orders. TMS, however, continued to provide labor and materials until March of 1986.

TMS subsequently sued Craftsmen as prime contractor and principal on the Bond and Millers as surety on the Bond,3 and, at trial, claimed $201,580.00 for completed contract and change order work, $467,738.00 for expenses caused by construction delay, and $251,580.00 for expenses caused by the partial termination. Millers paid TMS $101,040.81 of its contract work claim, $48,150.08 of its termination claim, and $27,000.00 in interest. After a bench trial, the district court awarded TMS $100,104.19, roughly the balance of its contract and change order work [949]*949claim, plus pre- and post-judgment interest against Millers,4 but concluded that TMS could not recover either its delay or termination claim against the Miller Act surety. TMS now appeals from that judgment.5 Based upon our independent appellate review, United States ex rel. Gulf States Enterprises, Inc. v. R.R. Tway, Inc., 938 F.2d 583, 586 (5th Cir.1991) (per curiam), we reverse as to the delay claim and affirm as to the termination claim.6

II. THE MILLER ACT

This is a Miller Act7 case, and, thus, this is a lien case. A mechanic’s lien under state law against improved property provides security for suppliers of labor and material to private construction projects, but a mechanic’s lien cannot attach to government property. F.D. Rich Co. v. United States ex rel. Industrial Lumber Co., 417 U.S. 116, 122, 94 S.Ct. 2157, 2161, 40 L.Ed.2d 703 (1974) (citation omitted). The Miller Act requires that a contractor on a federal construction project furnish “a payment bond ... for the protection of all persons supplying labor and material in the prosecution of the work provided for in [the] contract.” 8 40 U.S.C.A. § 270a(a)(2) (1986). The payment bond, “intended ... to protect the rights of these suppliers” who furnish labor or materials to government construction projects, thus provides an alternative to a mechanic’s lien, F.D. Rich, 417 U.S. at 122, 94 S.Ct. at 2161, because it permits the supplier to sue the Miller Act surety on the payment bond. Specifically, the Act provides that

[e]very person who ... furnish[es] labor or material in the prosecution of the work provided for in [the] contract ... who has not been paid in full therefor before the expiration of a period of ninety days after the day on which the last of the labor was done ... or material was [950]*950furnished ... for which such claim is made, shall have the right to sue on such payment bond for the amount ... unpaid at the time of institution of such suit and to prosecute said action to final execution and judgment for the sum or sums justly due him.

40 U.S.C.A. § 270b(a) (1986).

The Supreme Court has instructed us to liberally interpret the Miller Act “to effectuate the purpose of Congress.” Illinois Surety Co. v. John Davis Co., 244 U.S. 376, 380, 37 S.Ct. 614, 616, 61 L.Ed. 1206 (1917).9 For example, the Court “has repeatedly refused to limit the application of the act to labor and materials directly incorporated into the public work.” Brogan v. National Surety Co., 246 U.S. 257, 261, 263, 38 S.Ct. 250, 251, 252, 62 L.Ed. 703 (1918) (holding that groceries supplied to a contractor who was compelled to provide board and lodging for its laborers “[were] used exclusively in the performance of the work”).

Certain limitations, however, stem from the language of the Miller Act. The Act extends the right to sue on the payment bond “to those who ha[ve] a contractual agreement with the prime contractor or with a ‘subcontractor.’ ” 10 F.D. Rich, 417 U.S. at 122, 94 S.Ct. at 2161 (citation omitted); see J.W. Bateson Co. v. United States ex rel. Board of Trustees of National Automatic Sprinkler Industry Pension Fund, 434 U.S. 586, 589-90, 98 S.Ct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Diamond Services v. RLB Contracting
113 F.4th 430 (Fifth Circuit, 2024)
Elliot Dickson v. Fidelity and Deposit Company
67 F.4th 182 (Fourth Circuit, 2023)
United States v. Hirani Eng'g & Land Surveying, P.C.
345 F. Supp. 3d 11 (D.C. Circuit, 2018)
United States ex rel. Kitchens to Go v. John C. Grimberg Co.
283 F. Supp. 3d 476 (E.D. Virginia, 2017)
R L Acoustics v. Liberty Mutual Ins., No. Cv00 0380506s (Sep. 27, 2001)
2001 Conn. Super. Ct. 13161 (Connecticut Superior Court, 2001)
United States Ex Rel. Maris Equipment Co. v. Morganti, Inc.
163 F. Supp. 2d 174 (E.D. New York, 2001)
Blakeslee Arpaia Chapman, Inc. v. EI Constructors, Inc.
687 A.2d 506 (Supreme Court of Connecticut, 1997)
Chapman v. Ei Constructors, Inc., No. Cv 0040938 (Feb. 21, 1995)
1995 Conn. Super. Ct. 1702 (Connecticut Superior Court, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
942 F.2d 946, 1991 WL 172936, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-tms-mechanical-contractors-inc-v-millers-mutual-ca5-1991.