McLean Contracting Company v. Great American Insurance Company

CourtDistrict Court, N.D. Indiana
DecidedMay 24, 2023
Docket2:20-cv-00439
StatusUnknown

This text of McLean Contracting Company v. Great American Insurance Company (McLean Contracting Company v. Great American Insurance Company) is published on Counsel Stack Legal Research, covering District Court, N.D. Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McLean Contracting Company v. Great American Insurance Company, (N.D. Ind. 2023).

Opinion

UNITED STATES DISTRICT COURT NORTHERN DISTRICT OF INDIANA HAMMOND DIVISION

MCLEAN CONTRACTING COMPANY, ) Plaintiff, ) ) v. ) CAUSE NO.: 2:20-CV-439-JVB-JEM ) GREAT AMERICAN INSURANCE ) COMPANY and FIGG BRIDGE BUILDERS, ) LLC, ) Defendants. ) ) ) FIGG BRIDGE BUILDERS, LLC, ) Counter Claimant, ) ) v. ) ) MCLEAN CONTRACTING COMPANY, ) Counterclaim Defendant. )

OPINION AND ORDER This matter is before the Court on Defendant Great American Insurance Company’s Motion for Summary Judgment [DE 58] filed on January 12, 2023. For the reasons below, the Court denies the motion. PROCEDURAL BACKGROUND On November 2, 2020, McLean Contracting Company (“McLean”) filed a complaint against Figg Bridge Builders LLC (“Figg”) and Great American Insurance Company (“Great American”) in Lake County Superior Court. Great American removed the case to federal court on December 1, 2020, on the basis of diversity jurisdiction. McLean brings claims against Great American for failure to honor payment bond obligations and for unjust enrichment. McLean also brings claims against Figg for breach of contract and unjust enrichment. Figg, in turn, counterclaims against McLean for breach of contract and a demand for indemnity. In broad terms, McLean was a subcontractor on a construction project for general contractor Figg, whose payment bond surety was Great American. The principal, Cline Avenue

Bridge, LLC (“CAB”), terminated its contract with Figg, and McLean seeks, in this lawsuit, to recoup costs it incurred as a result of the cessation of work at the project site. Great American’s motion for summary judgment pertains only to McLean’s claims against Great American. Great American argues that it has honored all of its payment bond obligations. The motion, supporting brief, statement of material facts, and designated evidence in support were filed on January 12, 2023. McLean filed its response brief, designated evidence, and response to the statement of material facts on March 1, 2023. Great American filed its reply on March 29, 2023, and its reply to the material facts on April 12, 2023. The motion for summary judgment is now ripe for ruling. SUMMARY JUDGMENT STANDARD

A motion for summary judgment must be granted “if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” Fed. R. Civ. P. 56(c). Rule 56(c) further requires the entry of summary judgment, after adequate time for discovery, against a party “who fails to make a showing sufficient to establish the existence of an element essential to that party’s case, and on which that party will bear the burden of proof at trial.” Celotex Corp. v. Catrett, 477 U.S. 317, 322 (1986). The party seeking summary judgment bears the initial responsibility of informing a court of the basis for its motion and identifying the evidence, if any, which it believes demonstrates the lack of a genuine issue of material fact. Celotex, 477 U.S. at 323. If the moving party supports its motion for summary judgment with affidavits or other materials, the burden shifts to the non- moving party to showing that an issue of material fact exists. Keri v. Bd. of Tr. of Purdue Univ., 458 F.3d 620, 628 (7th Cir. 2006). Rule 56(e) specifies that once a properly supported motion for

summary judgment is made, “the adverse party’s response, by affidavits or as otherwise provided in this rule, must set forth specific facts to establish that there is a genuine issue for trial.” Fed. R. Civ. P. 56(e). In viewing the facts presented on a motion for summary judgment, a court must construe all facts in a light most favorable to the non-moving party and draw all legitimate inferences and resolve all doubts in favor of that party. Keri, 458 F.3d at 628. A court’s role is not to evaluate the weight of the evidence, to judge the credibility of witnesses, or to determine the truth of the matter, but instead to determine whether there is a genuine issue of triable fact. Anderson v. Liberty Lobby, 477 U.S. 242, 249-50 (1986). MATERIAL FACTS

Effective June 8, 2017, Figg and CAB entered into a contract for the design and construction of the Cline Avenue bridge over Indiana Harbor and Ship Canal in East Chicago, Indiana (the “Project”). (Compl. Ex. B. Subex. G at 7, 63, ECF No. 4-1). At Figg’s request, Great American issued1 a payment bond (Bond No. 1517337) effective June 14, 2017, naming CAB as Owner. (Mot. Ex. B, ECF No. 61-2). The bond is modified by a “dual obligee rider” that has not been presented to the Court. Id. The bond names Figg as the principal, Great American as the surety, and CAB as the owner. Id.

1 The parties do not dispute that the bond was issued, though the document before the Court is unsigned by Figg and Great American. On January 4, 2019, Figg and McLean entered into a written subcontract for work on the Project. (Compl. Ex. B at 1, ECF No. 4-1). Section 9.6 of the subcontract addresses the procedures allowable if the contractor provides written instruction to the subcontractor to suspend work. (Resp. Ex. C § 9.6, ECF No. 67-3). Section 9.4 of the subcontract provides that if the prime

contract is terminated, then the contractor will notify the subcontractor in writing within three business days of the termination and that the subcontract terminates upon the written notification. (Resp. Ex. C. § 9.4, ECF No. 67-3). The parties agree that McLean commenced work under the subcontract on or about January 23, 2019. On April 7, 2020, CAB terminated the construction contract with Figg and instructed Figg to leave the Project site. (Mot. Ex. C at 4, ECF No. 61-3). A panel of arbitrators hearing the dispute between CAB and Figg found that CAB had insufficient grounds to terminate the agreement and breached its agreement with Figg by failing to give Figg notice with an opportunity to cure, which, in combination, constituted an Owner Event of Default. Id. at 29-30. McLean was not a party to the arbitration. Id.

Following CAB’s termination of the construction contract with Figg, CAB entered into a prime contract with Granite Construction (“Granite”) on April 13, 2020, to complete Figg’s remaining work on the Project. (Mot. Ex. A at ¶ 8, ECF No. 61-1; Mot. Ex. D, ECF No. 61-4). Granite entered into a subcontract with McLean effective June 1, 2020, to perform work in completion of the Project. (Mot. Ex. A at ¶ 9, ECF No. 61-2; Mot. Ex. E, ECF No. 61-5 (contract proposal)). The parties agree that McLean subsequently made a claim on the payment bond. Great American maintains that the disputed amount of McLean’s payment bond claim is $802,040.15 and asserts that this amount represents rental charges for McLean’s equipment (standby costs) on site between April 7, 2020 and June 1, 2020. (Mot. Ex. G Nos. 3-4, ECF No. 61-7; Mot. Ex. F Subex. A, ECF No. 61-7 (line items “Stand[b]y thru 4/30” and “Standby thru 5/31”)). McLean agrees it is owed for rental charges for the standby costs on site between April 7, 2020 and June 1, 2020. However, McLean disagrees with the claim amount, contending that the proper figure is

$781,851.83, plus interest and costs. (Resp. Ex. A ¶ 27, ECF No. 67-1; Mot. Ex. F Subex. A, ECF No. 61-7 (current balance remaining)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Gabe Keri v. Board of Trustees of Purdue University
458 F.3d 620 (Seventh Circuit, 2006)
BMD CONTRACTORS v. Fidelity and Deposit Co. of Md.
679 F.3d 643 (Seventh Circuit, 2012)
Garco Indus. Equipment Co., Inc. v. Mallory
485 N.E.2d 652 (Indiana Court of Appeals, 1985)
Evans v. Medical & Professional Collection Services, Inc.
741 N.E.2d 795 (Indiana Court of Appeals, 2001)
Meyer v. Building and Realty Service Co., Inc.
196 N.E. 250 (Indiana Supreme Court, 1935)
Blakeslee Arpaia Chapman, Inc. v. EI Constructors, Inc.
687 A.2d 506 (Supreme Court of Connecticut, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
McLean Contracting Company v. Great American Insurance Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mclean-contracting-company-v-great-american-insurance-company-innd-2023.