Garco Indus. Equipment Co., Inc. v. Mallory

485 N.E.2d 652, 1985 Ind. App. LEXIS 2976
CourtIndiana Court of Appeals
DecidedNovember 26, 1985
Docket1-285A34
StatusPublished
Cited by22 cases

This text of 485 N.E.2d 652 (Garco Indus. Equipment Co., Inc. v. Mallory) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Garco Indus. Equipment Co., Inc. v. Mallory, 485 N.E.2d 652, 1985 Ind. App. LEXIS 2976 (Ind. Ct. App. 1985).

Opinion

RATLIFF, Presiding Judge.

STATEMENT OF THE CASE

Garco Industrial Equipment, Inc. appeals the trial court's denial of its motion for summary judgment and the granting of summary judgment in favor of Sherman Mallory and Indiana Insurance Company in Gareo's attempt to recover on a performance bond. We affirm.

FACTS

On April 22, 1981, Mallory Construction Company (Mallory) and Indiana Gas Company (Indiana Gas) entered into a contract for the construction of a water line at Indiana Gas' new Danville, Indiana facility. The contract required Mallory to obtain a performance bond in the amount of $43,-800.96, the full amount of the contract. Additional conditions of the agreement, attached to the contract, reiterate this requirement, one specifically stating: "2. Prior to the commencement of the work hereunder, the Contractor shall furnish to the Company a bond covering the faithful performance of this contract and the payment of all obligations arising hereunder. Such performance bond shall be in the amount of $48,800.96 with such surety as is agreeable to both parties." Record at 358A, Exhibit G-1, p. 4. Pursuant to this requirement of the contract, Mallory obtained a performance bond from Indiana Insurance Company (Indiana Insurance) wherein Mallory is named principal, Indiana Insurance is named surety, and Indiana Gas is designated obgligee. The work was to be completed within 120 days.

On June 15, 1981, Mallory entered into an agreement with Harco Leasing Co., Inc. (Harco) to lease a backhoe loader and an excavator. The lease was to run for a sixty (60) month period. Forty-five (45) monthly payments of $4,420.00 were to commence on June 15, 1981, and continue throughout the course of the agreement, with the exception of January, February, and March. Mallory had possession of the equipment from June 1, 1981, through August 6, 1981, and used it on the Danville job. The record indicates that Harco intended to purchase the equipment from Garco but abandoned this intention when Mallory defaulted on its initial lease payment. Record at 87. Subsequently, on June 15, 1981, Harco appears to have assigned all of its rights, regarding the contract with Mallory, to Gareo.

Garco repossessed the equipment on August 6, 1981, when Mallory failed to make its first payment and failed to pay several material suppliers. Garco sued Mallory in the Johnson Circuit Court and obtained a default judgment in the amount of $24,-750.51. Thereafter, Indiana Gas paid approximately $40,801.98 on the claims of the various suppliers of materials and was subsequently reimbursed by Indiana Insurance. However, Garco was not paid for the rental of the equipment. On September 16, 1982, Mallory declared bankruptcy and obtained discharge of the judgment debt owed to Gareo.

Garco then brought this action against Mallory and Indiana Insurance, as surety, for the value of the construction equipment *654 over the two month period together with repair costs totaling $24,791.51. Both sides filed motions for summary judgment. The trial court granted Indiana Insurance's motion for summary judgment declaring Indiana Gas to be the sole obligee under the bond and finding no intention in the bond or the contract that the bond should run to the benefit of laborers, materialmen, subcontractors, or lessors of machinery. The court stated that Garco was neither an obligee nor a third party beneficiary under the bond. In addition, the court found that Mallory had not entered into a rental agreement with Garco and therefore Garco was not a party with an enforceable claim under the bond. Appellant then perfected this appeal.

ISSUE

Whether Garco has any grounds upon which it may recover the rental and repair value of its backhoe and excavator from the performance bond executed by Mallory and Indiana Gas.

DISCUSSION AND DECISION

A surety's liability is measured by the strict terms of his contract. Stewart v. Knight & Jillson Co. (1906), 166 Ind. 498, 76 N.E. 743; 26 I.L.E. Suretyship sec. 22 (1960). Usually, a suretyship contract is construed in accordance with the rules governing other contracts. 26 LLE. Surety-ship see. 23 (1960). Where the suretyship contract is entered into in relation to another agreement, both instruments must be construed together. National Surety Co. v. Rochester Bridge Co. (1925), 83 Ind.App. 195, 198-99, 146 N.E. 415, 416, trans. denied. While sureties are not "favorites of the law," gratuitous or accommodation sureties are entitled to a strict construction of the contract in their favor, so as not to impose a greater burden on them than they agreed to. This rule, however, does not apply in the case of a surety for hire. Instead, the contract of a surety for hire is viewed as analogous to an insurance contract, 1 and is construed most strictly against the surety and in favor of the person to be protected. Knight & Jillson Co. v. Castle (1909), 172 Ind. 97, 109, 87 N.E. 976, 981; London & Loncashire Indemnity Co. of America v. Community Savings & Loan Ass'n. (1936), 102 Ind.App. 665, 675-76, 4 N.E.2d 688, 693; National Surety, 183 Ind.App. at 198, 146 N.E. at 416. Therefore, any contractual ambiguities are resolved in favor of the beneficiary. London, 102 Ind.App. at 675-76, 4 N.E.2d at 693; National Surety, 188 Ind.App. at 198, 146 N.E. at 416.

Usually, only parties to a contract or those in privity with them have the right to recover under a contract. Gonzales v. Kil Nam Chun (1984), Ind.App., 465 N.E.2d 727, 729; State ex rel. Lawson v. Warren Bros. Roads Co. (1945), 115 Ind.App. 452, 458, 59 N.E.2d 912, 915. Those not a party to a contract may enforce the contract by demonstrating that they are third party beneficiaries who were intended to be protected under the agreement by the imposition of a duty in their favor. Gonzales, at 729; Knight, 172 Ind. at 101, 87 N.E. at 977. As third party beneficiaries, they may recover under the contract even though they had no knowledge of the agreement at the time it was made. Knight, at 101, 87 N.E. at 977. The intent of the parties to benefit the third party is the controlling factor and this may be shown "by specifically naming the third party or by other evidence." Gonzales, at 729.

*655 In Indiana, construction bonds have been found to benefit certain unnamed third persons despite a lack of privity. Lawson, 115 Ind.App. at 461, 59 N.E.2d at 915; Nash Engineering Co. v. Marcy Realty Corp. (1944), 222 Ind. 396, 54 N.E.2d 263; Knight & Jillson Co. v. Castle (1909), 172 Ind. 97, 87 N.E. 976, Ochs v. M.J. Carnahan Co. (1906), 42 Ind.App. 157, 76 N.E. 788, petition on rehearing, 80 N.E. 163. If one brings himself within a class of persons intended to be protected by the bond, he may seek his remedy against the bond. Lawson, 115 Ind.App. at 462, 59 N.E.2d at 915. The difficulity is in determining whether a claimant is such a benefi-clary. Id. In Title Guaranty Co. v. State (1915), 61 Ind.App. 268, 109 N.E. 237, trans.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BMD CONTRACTORS v. Fidelity and Deposit Co. of Md.
679 F.3d 643 (Seventh Circuit, 2012)
BMD Contractors, Inc. v. Fidelity & Deposit Co.
828 F. Supp. 2d 978 (S.D. Indiana, 2011)
American Motorists Insurance Co. v. Worker's Compensation Board
819 N.E.2d 485 (Indiana Court of Appeals, 2004)
In Re Kemper Ins. Companies
819 N.E.2d 485 (Indiana Court of Appeals, 2004)
Bailey v. Holliday
806 N.E.2d 6 (Indiana Court of Appeals, 2004)
Orthodontic Affiliates, P.C. v. Orthalliance, Inc.
210 F. Supp. 2d 1054 (N.D. Indiana, 2002)
Luhnow v. Horn
760 N.E.2d 621 (Indiana Court of Appeals, 2001)
Donnelley & Sons Co. v. North Texas Steel Co., Inc.
752 N.E.2d 112 (Indiana Court of Appeals, 2001)
Centennial Mortgage, Inc. v. Blumenfeld
745 N.E.2d 268 (Indiana Court of Appeals, 2001)
Dow-Par, Inc. v. Lee Corp.
644 N.E.2d 150 (Indiana Court of Appeals, 1994)
Blakeslee Arpaia Chapman v. U.S. F. G. Co., No. 520348 (Mar. 4, 1994)
1994 Conn. Super. Ct. 2215 (Connecticut Superior Court, 1994)
Kirtley v. McClelland
562 N.E.2d 27 (Indiana Court of Appeals, 1991)
Barth Electric Co. v. Traylor Bros., Inc.
553 N.E.2d 504 (Indiana Court of Appeals, 1990)
Vanek v. Indiana National Bank
540 N.E.2d 81 (Indiana Court of Appeals, 1989)
Estate of Carnahan v. ISM, Inc.
510 N.E.2d 748 (Indiana Court of Appeals, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
485 N.E.2d 652, 1985 Ind. App. LEXIS 2976, Counsel Stack Legal Research, https://law.counselstack.com/opinion/garco-indus-equipment-co-inc-v-mallory-indctapp-1985.