Dow-Par, Inc. v. Lee Corp.

644 N.E.2d 150, 1994 Ind. App. LEXIS 1783, 1994 WL 693288
CourtIndiana Court of Appeals
DecidedDecember 12, 1994
Docket49A04-9310-CV-372
StatusPublished
Cited by8 cases

This text of 644 N.E.2d 150 (Dow-Par, Inc. v. Lee Corp.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dow-Par, Inc. v. Lee Corp., 644 N.E.2d 150, 1994 Ind. App. LEXIS 1783, 1994 WL 693288 (Ind. Ct. App. 1994).

Opinions

OPINION

RILEY, Judge.

Plaintiff-Appellant Dow-Par, Inc., appeals from a summary judgment in favor of Defendants-Appellees the Lee Corp., Construction Design of Indiana, Inc., and United States Fidelity and Guaranty Company.

We affirm.

ISSUES1

We address the following issues:

1. Does _ IND.CODE - 36-1-12-18.1 (19983) give a lessor of equipment to a subcontractor the right to assert a claim under a statutorily required payment bond?
2. Notwithstanding I.C. 86-1-12-18.1, does a lessor of equipment to a subcontractor have an actionable claim pursuant to the terms of the contractor's payment bond?

[152]*152FACTS

In May, 1990, the Town of Fishers, Indiana, entered into a contract with the Lee Corporation (Lee) to act as general contractor for the building of the Fishers Town Complex (Fishers Complex). In compliance with LC. 86-1-12-13.1, Lee secured a Labor and Material Payment Bond (the Bond) from United States Fidelity and Guaranty Company (USF & G) which provides, in part, that Lee and USF & G

hereby jointly and severally agree with the [Town of Fishers] that every claimant as herein defined, who has not been paid in full before the expiration of a period of ninety (90) days after the date on which the last of such claimant's work or labor was done or performed, or materials were furnished by such claimant, may sue on this bond for the use of such claimant, prosecute the suit to final judgment for such sum or sums as may be justly due claimant.

(R. 158). Claimants are defined as "one having a direct contract with the Principal, or with a sub-contractor of the Principal for ... rental of equipment directly applicable to the contract." Id. Payment to claimants under the Bond is limited by the following provision:

The amount of this bond shall be reduced by and to the extent of any payment or payments made in good faith hereunder, inclusive of the payment by Surety of me-chanies' liens which may be filed of record against said improvement, whether or not claim for the amount of such lien be presented under and against this bond.

Id.

In June, 1990, Lee subcontracted with Construction Design of Indiana, Inc. (CDI) to provide earth moving services on the Fishers Complex construction site. The agreement provided that Lee would pay CDI $235,-053.00 for the performance of the subcontract.

CDI entered into a series of equipment leases with Dow-Par, Inc. (Dow-Par), an Indiana corporation which buys, sells, and leases construction equipment. None of the rental agreements specified a particular project site at which CDI would operate the leased equipment; however, CDI used the equipment at the Fishers Complex site as well as various other building sites.

During the course of the project, Lee paid $208,480.00 to CDI; however, before the project was completed, CDI became insolvent and could not fulfill its obligations under its subcontract. Lee incurred additional costs of $102,663.78 completing the project, thus, pursuant to the subcontract between Lee and CDI, CDI owes Lee $76,091.64, the difference between the contract price and the actual cost of completion. CDI also failed to pay Dow-Par $77,400 in monthly lease payments, fuel, freight, and interest.

In November of 1990, Dow-Par filed a notice of claim before the Fishers Town Hall Board and later initiated a suit against Lee, CDI, and USF & @ seeking the monies owed to it by CDI. Lee and USF & G moved for summary judgment which was granted.2 It is from this judgment that Dow-Par appeals.

DISCUSSION

In our review of an entry of summary judgment, we consider the same issues and conduct the same inquiry as the trial court. O'Donnell v. American Employers Ins. (1993), Ind.App., 622 N.E.2d 570, 572, reh'g denied, trans. denied. Summary judgment is only appropriate where the moving party demonstrates by properly designated eviden-tiary matter that no genuine issue of material fact exists and that the party is entitled to judgment as a matter of law. See Ind.Trial Rule 56(E). All evidence must be construed favorably to the nonmoving party, and all doubts as to the existence of a material issue must be resolved 'against the moving party. Oelling v. Rao (1992), Ind., 593 N.E.2d 189, 190; J.A.W. v. Loretta Roberts (1994), Ind.App., 627 N.E.2d 802, 807. We will affirm a trial court's grant of summary judgment if it is sustainable on any theory or basis found in the evidentiary matter designated to the trial [153]*153court. TR. 56(C); Stowers v. Norwest Bank Indiana (1993), Ind.App., 624 N.E.2d 485, 488, reh'g denied.

Whether a person who furnishes labor or materials to a subcontractor on a public works project is within the seope of the payment bond furnished by the general contractor to the principal depends upon the terms of the applicable statute and the terms of the bond. 17 Am.Jur2d Contractor's Bond Section 19 (1990). Thus, initially, we examine whether Dow-Par, a lessor of equipment to a subcontractor, is protected under 1.C. 86-1-12-18.1 which governs payment bonds secured on public works projects.

1.C. 86-1-12-18.1 is part of a public works statutory scheme which provides for the payment of those who work on public works projects. Carpenters Pension Fund v. Seaboard (1992), Ind.App., 601 N.E.2d 352, 357, reh'g denied, trans. denied, (1993), Ind., 615 N.E.2d 892; See Concrete Steel v. Metropolitan Casualty Ins. (1930), 95 Ind.App. 649, 653, 178 N.E. 651, 652. The scheme secures payment for subcontractors, laborers, materi-almen, and service providers in relation to or in connection with public works construction where mechanics liens are unavailable because they cannot be acquired or enforced upon or against property held for public uses. Carpenters Pension Fund, 601 N.E.2d at 357 (citing MacDonald v. Calumet Supply Co. (1939), 215 Ind. 536, 543, 19 N.E.2d 567, 570, reh'g denied, 215 Ind. 536, 21 N.E.2d 400); Townsend v. Cleveland Fire-Proofing (1897), 18 Ind.App. 568, 571, 47 N.E. 707, 708.

Although the payment bonds required by section 18.1 are said to replace mechanics liens in the public work projects situation, "a mechanic's lien provides relief to laborers which is in direct conflict with the rights of a landowner, while the public work statutes provides a remedy against a surety which has been compensated for assuming that risk." - Carpenters Pension Fund, 601 N.E.2d at 356. Thus, where the mechanics liens statute serves the dual function of narrowing a claimant's rights in order to protect the landowner while providing a remedy for unpaid laborers, the primary purpose of the statutory payment bond is to protect suppliers of labor or materials, not the general contractor or the public body or principal that owns the property.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
644 N.E.2d 150, 1994 Ind. App. LEXIS 1783, 1994 WL 693288, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dow-par-inc-v-lee-corp-indctapp-1994.