Lee & Mayfield, Inc. v. Lykowski House Moving Engineers, Inc.

489 N.E.2d 603, 1986 Ind. App. LEXIS 2351
CourtIndiana Court of Appeals
DecidedFebruary 26, 1986
Docket3-385A54
StatusPublished
Cited by19 cases

This text of 489 N.E.2d 603 (Lee & Mayfield, Inc. v. Lykowski House Moving Engineers, Inc.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lee & Mayfield, Inc. v. Lykowski House Moving Engineers, Inc., 489 N.E.2d 603, 1986 Ind. App. LEXIS 2351 (Ind. Ct. App. 1986).

Opinions

STATON, Presiding Judge.

Lee and Mayfield, Inc. (Lee) plaintiff, appeals from a partial summary judgment and from judgment for damages on counterclaims filed by the defendants, Lykow-ski Construction Co. (Lykowski) and John A. Levy, Charles C. Davis and Timothy E. Mathias (Levy). Lee presents five issues for our review:

I. Did the trial court err in granting summary judgment to Levy on the issue of Lee's purported "Retain-age" Lien?
II. Was there sufficient evidence of slander of title?
IIl. Was there sufficient evidence that Lee tortiously interferred with the contract between Lykowski and Levy?
IV. Was there sufficient evidence to support the trial court's award of damages?
V. Was there sufficient evidence to support the trial court's award of attorney fees?

Lykowski Construction Company is in the business of moving buildings. In 1981 Lykowski decided to design a new system of wheel dollies with a weight capacity of 100 tons each for use in its own business as well as for sale or rental to others. Ly-kowski engaged a design engineer to design the wheel assemblies, perform stress analysis, determine specifications and tolerances, and verify the weight capacity. Ly-kowski had preliminary discussions in November, 1981, with Lee and Mayfield, Inc., a machine shop, regarding the fabrication and machining of certain component parts [606]*606of the wheel assemblies. In June, 1982 Lykowski entered into negotiations with Levy, Davis and Mathias, the owners of a structure they desired to relocate to a parcel of property they owned. Southhold Heritage Foundation, Inc., as interim lender and construction manager was also involved in the negotiations. These negotiations resulted in a written contract dated July 12, 1982, under which Lykowski was to receive $30,000.00 in advance, $15,000.00 when the structure was moved to the new site, and $15,000.00 when the job was completed.

In anticipation of the $80,000.00 payment from Levy, Lykowski decided to proceed with building six (6) wheel dollies pursuant to the original design. Lykowski orally agreed with Lee in June, 1982 to a time and materials contract for the machining of certain parts for six wheel dollies and three spare wheels. Lykowski planned to use the wheel dollies initially in the move of Levy's structure and later in moving other structures or for rental to other house movers.

As the work progressed Lykowski complained about defects, the quality of workmanship and the failure to conform to specifications and permitted tolerances. A number of parts were rejected and returned to Lee for reworking. Lykowski employees did some machining when Lee failed to do so. When Lykowski completed assembly of the wheel dollies in preparation for the Levy move, Lykowski employees were forced to "jerry rig" spacer rings because they had been machined smaller than specified. During the move on August 26, 1982 the tires on twelve (12) of the wheel assemblies would not hold air at the required pressure because of a machining defect. On July 22, 1982 Lykowski made an initial payment to Lee of $10,000.00, but because of the dispute over workmanship, Lykowski made no further payments. Due to the dispute between Lykowski and Lee, Levy and Southhold withheld payment of the second and third payments due Lykow-ski although the move had been completed on September 28, 1982 and accepted by Levy and Southhold.

On September 29, 1982 Lee filed a mechanic's lien1 for $27,569.88 on the real estate owned by Levy. Thereafter, Lee filed a notice to hold the owners personally liable against Levy.2 As a result of Lee's mechanic's lien on the real estate, Lykow-ski filed a lien on the real estate for the remaining $30,000.00 owing to it for the moving job. On December 1, 1982 Lykow-ski sent notice to Lee to commence suit on the mechanic's lien within thirty (80) days of the correspondence.3 On February 14, 1983 Lee filed suit against Levy, Lykowski and Southhold seeking, among other things, to foreclose on the mechanic's lien filed September 29, 1982. The trial court subsequently granted summary judgment against Lee on the mechanic's lien, holding it to be null and void for failure to commence suit within 30 days of demand to do so.4 Lee does not appeal from that judgment.

I.

Summary Judgment

Our standard of review for the granting of summary judgment has been stated many times. We apply the same standard as that applied by the trial court and will affirm if the prevailing party was entitled to judgment as a matter of law. Integrity Insurance Co. v. Lindsey (1983), Ind.App., 444 N.E.2d 345, 347. Summary judgment is appropriate if no genuine issue of material fact exists and the moving party is entitled to judgment as a matter of law. Indiana Rules of Procedure, Trial Rule 56(C). The facts here are not in dispute, the only issue is whether the trial court correctly applied the law.

In granting Levy's motion for summary judgment on Lee's owner's liability claim [607]*607under 1.0. 32-8-3-9, the trial court held that the provision was not identical to the statutory provision for a mechanic's lien, IC 82-8-3-1, but that the class of individuals entitled to relief under either provision was the same and that Lee was not within the class of person's entitled to the remedy. We agree with the trial court insofar as subcontractors, journeymen and laborers are concerned; however, we note that contractors are afforded the protection of the mechanic's lien provision, but they are not included in the personal liability provision, presumably because a contractor would already have a personal right of action against an owner under the contract.

There appears to be some confusion among the parties on the distinctions between the two statutory provisions. We emphasize that we are not dealing with a mechanic's lien on the real estate, the remedy permitted under IC 82-8-8-1. We are concerned only with IC 32-8-3-9 which allows:

Any subcontractor, lessor leasing construction and other equipment and tools, whether or not an operator is also provided by the lessor, journeyman or laborer employed or leasing any equipment or tools used by the lessee in erecting, altering, repairing or removing any house ... other building ... or in furnishing any material or machinery therefor, may give to the owner thereof, ... notice in writing particularly setting forth the amount of his claim and services rendered, for which his employer or lessee is indebted to him, and that he holds the owner responsible for the same; and the owner shall be liable for such claim, but not to exceed the amount which may be due and may thereafter become due, from him to the employer or lessee.

The provision preserves for a subcontractor or materialman a right of action against an owner even though the subcontractor has no contract with the owner. There is a conflict among the cases construing this provision and its predecessor provisions as to whether a lien, per se, is even created by giving notice to the owner. A line of early Indiana Supreme Court decisions holds that no lien is intended or created by compliance with the personal liability section. See Barker v. Buell (1871), 35 Ind. 297; O'Halloran v. Leachey (1872), 39 Ind. 150; Colter v. Frese (1873), 45 Ind. 96.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dalton M, LLC v. North Cascade Trustee Services, Inc.
Court of Appeals of Washington, 2022
Walsh & Kelly, Inc. v. International Contractors, Inc.
943 N.E.2d 394 (Indiana Court of Appeals, 2011)
Wilcox Lumber Co. v. Andersons, Inc.
848 N.E.2d 1169 (Indiana Court of Appeals, 2006)
Burk v. Heritage Food Service Equipment, Inc.
737 N.E.2d 803 (Indiana Court of Appeals, 2000)
John Wendt & Sons v. Edward C. Levy Co.
685 N.E.2d 183 (Indiana Court of Appeals, 1997)
Dow-Par, Inc. v. Lee Corp.
644 N.E.2d 150 (Indiana Court of Appeals, 1994)
Kern v. City of Lawrenceburg
625 N.E.2d 1326 (Indiana Court of Appeals, 1993)
Coplay Cement Co. v. Willis & Paul Group
983 F.2d 1435 (Seventh Circuit, 1993)
Coplay Cement Company, Inc. v. Willis & Paul Group
983 F.2d 1435 (Seventh Circuit, 1993)
Edwards v. Bethlehem Steel Corp.
517 N.E.2d 430 (Indiana Court of Appeals, 1988)
Hansford v. State
490 N.E.2d 1083 (Indiana Supreme Court, 1986)
Lee & Mayfield, Inc. v. Lykowski House Moving Engineers, Inc.
489 N.E.2d 603 (Indiana Court of Appeals, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
489 N.E.2d 603, 1986 Ind. App. LEXIS 2351, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lee-mayfield-inc-v-lykowski-house-moving-engineers-inc-indctapp-1986.