Edgerock Development, LLC v. C.H. Garmong & Son Inc

Indiana Supreme Court·Decided June 3, 2025·No. 24S-PL-00184·Published

Opinion

IN THE

Indiana Supreme Court Supreme Court Case No. 24S-PL-184

EdgeRock Development, LLC, ZPS Westfield, LLC, FILED and First Bank Richmond, Jun 03 2025, 2:16 pm Appellants/Defendants, CLERK Indiana Supreme Court Court of Appeals and Tax Court –v–

C.H. Garmong & Son, Inc., Signworks, Inc., and Fox Contractors Corp., Appellees/Plaintiffs.

Argued: September 5, 2024 | Decided: June 3, 2025

Appeal from the Hamilton Superior Court 5 No. 29D05-1912-PL-11500 The Honorable David K. Najjar, Judge

On Petition to Transfer from the Indiana Court of Appeals No. 22A-PL-1968

Opinion by Justice Molter Chief Justice Rush and Justices Massa, Slaughter, and Goff concur. Molter, Justice.

EdgeRock Development, LLC transformed five undeveloped lots into the Trails of Westfield—a planned unit development in Westfield, Indiana, comprising retail and residential projects. It still owns two of the lots; it sold two lots to ZPS Westfield, LLC; and it sold one lot to a nonparty. EdgeRock contracted with C.H. Garmong & Son, Inc. and Fox Contractors Corp. to develop all five lots.

When EdgeRock first fell behind in its payments to Garmong, Garmong recorded construction liens that EdgeRock satisfied by obtaining a loan from First Bank Richmond, which the bank secured with a mortgage on EdgeRock’s lots. Then, when EdgeRock fell behind again, Garmong and Fox each recorded construction liens on all five lots in the development. And the liens were redundant: Each lien stated a cumulative debt covering the contractor’s work on all five lots, not just a debt for the work benefiting the owner of the lot to which the lien attached. That meant the contractors were using multiple properties with different owners to secure the same debt.

Recording the liens didn’t prompt payment that time. So the contractors sued EdgeRock for money damages on breach of contract claims and sued the other property owners, including ZPS, to foreclose the construction liens that secured the outstanding debts. Following a bench trial, the trial court awarded the contractors most of the relief they sought. But the Court of Appeals concluded the construction liens were overstated because they were not limited to the debts for the improvements directly benefiting the properties to which the liens attached. And it reversed the portion of the judgment foreclosing the construction liens.

We granted transfer to answer questions of first impression related to: (1) the validity and scope of the contractors’ construction liens, and (2) the priority between the construction liens and First Bank’s mortgage lien on EdgeRock’s property. In short, we conclude that a construction lien secures only the debt for improvements directly benefiting the property to which the lien attaches. So the contractors can foreclose the liens on each

Indiana Supreme Court | Case No. 24S-PL-184 | June 3, 2025 Page 2 of 41 property to recover only those amounts, not amounts for work to improve a different owner’s property.

We also conclude that First Bank’s mortgage lien is senior to the construction liens for the amount the bank loaned to satisfy Garmong’s prior construction lien. But the mortgage lien is junior for the remaining amounts, including the amount the bank loaned EdgeRock to pay off a prior mortgage held by the project’s investors.

Facts and Procedural History

I. Trails of Westfield Development EdgeRock undertook to commercially develop seventeen acres of property on the southeast corner of State Road 32 and Oak Ridge Road in Westfield, Indiana. The property began as one parcel, and then EdgeRock subdivided it into five lots, which the parties refer to as Lots 1 through 5. The project was to build a mixed use, planned unit development known as the Trails of Westfield, with Lot 4 zoned for multi-family apartments and the rest zoned for retail businesses. This is how the property appeared before it was developed:

Indiana Supreme Court | Case No. 24S-PL-184 | June 3, 2025 Page 3 of 41 At that point, the land had no water or sanitary service, it had homes on it that had to be demolished, and there was limited road access and quality. The Anna Kendall Drain and stream ran through where 175th Street was going to be built, and all five lots were in floodplains or floodways. Thus, significant infrastructure and earthmoving work, including moving the Anna Kendall Drain and stream, was required before the property could be put to commercial use.

EdgeRock treated construction on all lots as one project with a single, overarching infrastructure plan executed through a web of contracts.

EdgeRock-Garmong Contract (All Lots). EdgeRock hired C.H. Garmong & Son, Inc. to construct common infrastructure (including grading, sewer, and water) on all the lots and to construct buildings on Lots 1 and 2. Fox Contractors Corp. was Garmong’s infrastructure subcontractor for the EdgeRock-Garmong contract, enlisted to perform earthwork and infrastructure installation. That entailed work on all five lots, including utility work, earthwork on Lot 3 to raise its elevation, and building a retention pond on Lot 5 to collect runoff from the area.

ZPS-EdgeRock Contract (Lots 1 and 2). ZPS Westfield, LLC bought undeveloped Lots 1 and 2 from EdgeRock, and the parties entered a development agreement requiring EdgeRock to construct retail buildings and common infrastructure on those lots (which EdgeRock fulfilled through a portion of its EdgeRock-Garmong contract). ZPS’s contract with EdgeRock required work only on Lots 1 and 2, and ZPS agreed to pay EdgeRock a total of $1,720,000, which ZPS did. After EdgeRock developed Lot 1, ZPS leased it to Starbucks, and after EdgeRock developed Lot 2, ZPS leased one portion to a Penn Station sandwich shop and another portion to Forum Credit Union.

EdgeRock-Dahm Contract (Lot 3). EdgeRock sold Lot 3 to a nonparty, Dahm No. 49, LLC, which Dahm developed into a Crew Carwash.

Lots 4 and 5. EdgeRock still owns Lots 4 and 5, which it intended to develop into apartments and mixed-use retail shops, although it has not yet done so.

Indiana Supreme Court | Case No. 24S-PL-184 | June 3, 2025 Page 4 of 41 EdgeRock-Fox Contract. EdgeRock also had a separate, direct contract with Fox to move the Anna Kendall Drain, to construct 175th Street between Lots 1–3 and Lots 4–5, and to install related infrastructure. Fox’s work on the 175th Street Project stretched from the southern portion of Lot 2 east, benefiting all lots adjoining 175th Street. The 175th Street Project was to be funded by Road Impact Fee Credits (“RIF Funds”) issued by the City of Westfield.

This is what the area looked like after development through these contracts:

II. First Bank Richmond Loan As the project was progressing, EdgeRock stopped paying Garmong’s invoices, leading Garmong to record a construction lien for $2,140,722.51. At that point, Oak Ridge Investments, LLC owned Lots 4 and 5, and EdgeRock was one of the company’s members, with Birch Dalton serving as both companies’ manager. Oak Ridge’s investors held promissory notes for the lots’ purchase price, which the investors secured through a mortgage on the property.

EdgeRock satisfied Garmong’s lien by borrowing $4.9 million from First Bank Richmond and using some of those funds to pay all of Garmong’s overdue invoices. But EdgeRock used most of the loan proceeds for its own general use or to pay the project’s investors, and it

Indiana Supreme Court | Case No. 24S-PL-184 | June 3, 2025 Page 5 of 41 did not put any of the rest of the loan into the project.

Free access — add to your briefcase to read the full text and ask questions with AI

Edgerock Development, LLC v. C.H. Garmong & Son Inc, (Ind. 2025).

Edgerock Development, LLC v. C.H. Garmong & Son Inc (Edgerock Development, LLC v. C.H. Garmong & Son Inc) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Neu v. Gibson
928 N.E.2d 556 (Indiana Supreme Court, 2010)
Johnson v. Johnson
920 N.E.2d 253 (Indiana Supreme Court, 2010)
Bank of New York v. Nally
820 N.E.2d 644 (Indiana Supreme Court, 2005)
Gill v. Pollert
810 N.E.2d 1050 (Indiana Supreme Court, 2004)
Greene v. Thompson
554 So. 2d 376 (Supreme Court of Alabama, 1989)
Saint Joseph's College v. Morrison, Inc.
302 N.E.2d 865 (Indiana Court of Appeals, 1973)
Beneficial Finance Co. v. Wegmiller Bender Lumber Co.
402 N.E.2d 41 (Indiana Court of Appeals, 1980)
Harold McComb & Son, Inc. v. JPMorgan Chase Bank, NA
892 N.E.2d 1255 (Indiana Court of Appeals, 2008)
Stanray Corporation v. Horizon Construction, Inc.
342 N.E.2d 645 (Indiana Court of Appeals, 1976)
Greyhound Financial Corp. & Terre Haute v. Rlc, Inc.
637 N.E.2d 1325 (Indiana Court of Appeals, 1994)
Abbey Villas Development Corp. v. Site Contractors, Inc.
716 N.E.2d 91 (Indiana Court of Appeals, 1999)
Lee & Mayfield, Inc. v. Lykowski House Moving Engineers, Inc.
489 N.E.2d 603 (Indiana Court of Appeals, 1986)
Johnson v. Blankenship
679 N.E.2d 505 (Indiana Court of Appeals, 1997)
Premier Investments v. Suites of America, Inc.
644 N.E.2d 124 (Indiana Supreme Court, 1994)
Provident Bank v. Tri-County Southside Asphalt, Inc.
804 N.E.2d 161 (Indiana Court of Appeals, 2004)
Provident Bank v. Tri-County Southside Asphalt, Inc.
806 N.E.2d 802 (Indiana Court of Appeals, 2004)
Robert Neises Construction Corp. v. Grand Innovations, Inc.
938 N.E.2d 1231 (Indiana Court of Appeals, 2010)
Kohl's Indiana, L.P. and Kohl's Dept. Store, Inc. v. Dennis Owens
979 N.E.2d 159 (Indiana Court of Appeals, 2012)