Walsh & Kelly, Inc. v. International Contractors, Inc.

943 N.E.2d 394, 2011 Ind. App. LEXIS 105, 2011 WL 303241
CourtIndiana Court of Appeals
DecidedFebruary 1, 2011
DocketNo. 64A03-1006-PL-284
StatusPublished
Cited by8 cases

This text of 943 N.E.2d 394 (Walsh & Kelly, Inc. v. International Contractors, Inc.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Walsh & Kelly, Inc. v. International Contractors, Inc., 943 N.E.2d 394, 2011 Ind. App. LEXIS 105, 2011 WL 303241 (Ind. Ct. App. 2011).

Opinion

OPINION

RILEY, Judge.

STATEMENT OF THE CASE

Appellant-Plaintiff, Walsh & Kelly, Inc. (Walsh), appeals the trial court’s judgment in favor of Appellee-Defendant, Signature Properties, Inc. (Signature), with respect to Signature’s claim that it was not fully indemnified for its damages by a collateral assignment agreement and with respect to Signature’s claim that Walsh slandered the title of Signature’s property.

We affirm.

ISSUES

Walsh raises two issues on appeal, which we restate as follows:

(1) Whether the trial court erred in holding that Signature’s collateral assignment agreement with International Contractors, Inc. (International) did not fully indemnify Signature; and
(2) Whether the trial court erred in holding that Walsh was liable to Signature for slander of title.

FACTS AND PROCEDURAL HISTORY

Signature is a real estate developer that owns property in the Crisman Cove subdivision of Portage, Indiana. The subdivision consists of 36.76 acres divided into 89 lots. In September of 2003, Portage approved the streets in the subdivision for public use, so Signature contracted with International to complete excavation work and install roads and curbs in the subdivision. International completed the excavation work itself but hired Walsh to install the new curbs and pave the roads. As it had agreed, Walsh completed this work on March 31, 2005. Walsh did not, however, do any work on the actual lots owned by Signature.

On May 4, 2005, Walsh billed International $97,588.50 for its work on the road paving and curb installation. Then, on May 9, 2005, International billed Signature $71,685.00. Signature paid International $71,685.00, but International only paid Walsh $78,718.50. After this payment, International still owed Walsh $18,870.00. Subsequently, on August 15, 2005, Walsh billed International for an additional $41,239.50. International billed Signature $41,239.50, and Signature paid International the full $41,239.50. International did not make any further payments to Walsh, which left a remaining balance of $60,109.50 due on the contract between International and Walsh. International [397]*397has not made any payments since that time.

When International failed to make payments to Walsh, the Treasurer of Walsh, Michael J. Schaum (Schaum), decided on behalf of Walsh to file a Sworn Statement of Intention to Hold a Lien (mechanic’s lien) on October 21, 2005, against 26 of the subdivision lots that Signature had not yet sold. According to Walsh, the lien was only intended to encumber the unimproved lots owned by Signature. Towards that end, Schaum attempted to determine which lots were undeveloped by driving around the subdivision before filing the lien. Walsh also released lots from the lien when it learned that Signature no longer owned the lots. When Schaum made the decision to file the hen, though, he did not seek the advice of Walsh’s counsel before doing so. He also admits that he was unaware that Indiana’s mechanic’s lien statute does not permit a lien to be filed against the property of an owner where the owner has paid the general contractor all sums due and to become due for the work.

In response to Walsh’s actions, Signature requested multiple times that Walsh release the lien from its lots. On January 11, 2006, Signature’s attorney, Steven W. Handlon (Handlon), wrote a letter to Walsh making this request and asserting that the lien was improper because Walsh had not done any work on those lots. In the same letter, Handlon informed Walsh that Signature had paid all sums due under its contract with International, so it could not legally be the subject of a lien arising out of a debt between International and Walsh. Walsh did not release the lien, though, and Handlon once again contacted Walsh on March 11, 2006, reiterating that the lien was improper and that Signature had fully paid International.

On February 20, 2006, Signature entered into a collateral assignment with Brett Waldo (Waldo), the principal of International. In this collateral assignment, Waldo assigned his right, title, and interest in and to a certain purchase installment agreement (purchase installment agreement) for the purchase of real estate in LaPorte County, Indiana, to Signature, in order to secure payment to Signature for any indebtedness owed by International to Signature as a result of International’s failure to pay Walsh. Then, on March 11, 2006, Signature demanded that Walsh commence suit to foreclose on its mechanic’s lien within thirty days.

On March 30, 2006, Walsh filed a breach of contract lawsuit against International and a complaint to foreclose mechanic’s lien against Signature. Subsequently, on April 24, 2006, Signature filed a counterclaim for slander of title and conversion against Walsh and a cross-claim for indemnity and damages against International. On January 24, 2007, Signature filed a motion for partial summary judgment, asserting that the mechanic’s lien was neither valid nor enforceable. In response, Walsh filed a cross-motion for partial summary judgment on February 22, 2007. On July 2, 2007, the trial court held a hearing on the motions for partial summary judgment. Then, on September 14, 2007, the trial court entered its order granting Signature’s motion for partial summary judgment, but denying Walsh’s motion. Walsh appealed this interlocutory order, and on July 31, 2008, this court affirmed the trial court’s partial summary judgment in favor of Signature. See Walsh & Kelly, Inc. v. International Contractors, Inc., et al., 64A03-0712-CV-618, 2008 WL 2930226 (Ind.Ct.App. July 31, 2008).

After the partial summary judgment, the only issues remaining for trial were Walsh’s breach of contract claim against [398]*398International, Signature’s slander of title counter-claim against Walsh, and Signature’s indemnity cross-claim against International. On April 7, 2010, the trial court conducted a bench trial. On May 3, 2010, the trial court found for Signature on its slander of title and damages claims. Additionally, the trial court found damages for International’s breach of contract with Walsh and refused to consider the collateral agreement between Signature and Waldo as fully indemnifying Signature for its damages from Walsh’s mechanic’s lien.

Walsh now appeals. Additional facts will be provided as necessary.

DISCUSSION AND DECISION

I. Standard of Review

In order to prevail on a slander of title claim, a plaintiff must prove that the defendant made false, malicious statements regarding the plaintiffs ownership of the land in question, and that those statements caused the plaintiff pecuniary loss. Davis v. Sponhauer, 574 N.E.2d 292, 300 (Ind.Ct.App.1991). Malicious statements are those made knowingly or with reckless disregard for their falsity. Id. Malice may be inferred by the trier of fact from the evidence. Lee and Mayfield, Inc. v. Lykowski House Moving Engineers, Inc., 489 N.E.2d 603, 608 (Ind.Ct.App.1986).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
943 N.E.2d 394, 2011 Ind. App. LEXIS 105, 2011 WL 303241, Counsel Stack Legal Research, https://law.counselstack.com/opinion/walsh-kelly-inc-v-international-contractors-inc-indctapp-2011.