Kern v. City of Lawrenceburg

625 N.E.2d 1326, 1993 Ind. App. LEXIS 1557, 1993 WL 526719
CourtIndiana Court of Appeals
DecidedDecember 22, 1993
Docket15A01-9205-CV-144
StatusPublished
Cited by5 cases

This text of 625 N.E.2d 1326 (Kern v. City of Lawrenceburg) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kern v. City of Lawrenceburg, 625 N.E.2d 1326, 1993 Ind. App. LEXIS 1557, 1993 WL 526719 (Ind. Ct. App. 1993).

Opinion

ROBERTSON, Judge.

Robert F. Kern, doing business as Empire Masonry, appeals an adverse judgment on his cross-claim for foreclosure of a mechanic's lien against the City of Lawrence-burg, Robes & Kingman Securities Co., First Federal Savings & Loan Assn. of Columbus, Ohio, Plaza Properties Co., Donald L. Leathery and Charles R. Snyder, interest-holders in a property known as Dearborn Plaza. Although Kern did not seek a personal judgment against the City of Lawrenceburg, the owner of the real estate, Kern received a monetary judgment in the amount of $6,900.00, based upon a quantum meruit theory for water hauling services performed at the site, against Charles R. Snyder, Inc., the general contractor on the project, who was not a party to the action or made one by Kern. 1

The City of Lawrenceburg and the other defendants on the cross-claim, cross-appeal *1328 and ask that the judgment against Charles R. Snyder, Inc. be vacated as Charles R. Snyder, Inc. was never a party to the action. We order the monetary judgment in favor of Kern vacated for other reasons; 2 in all other respects, the judgment denying foreclosure is affirmed.

At the request of one of the parties, the trial court entered special findings of fact and conclusions of law, of which the following are relevant to this appeal:

18. ... Empire claimed at trial, that Empire performed the work shown on Exhibit J-S as a consequence of oral change orders that Snyder, Inc. authorized during the progress of the job. The provisions of the original contract and the statements on the partial waivers and releases (""the signed agreement to perform now and in the future, each and every covenant and provision of his written contract or suppliers agreement (as the case may be and as modified and changed in writing) provided that change orders, and the like, must be made in writing. If there were any oral change orders, the failure to put them in writing precludes recovery under the lien....
17. Empire seeks to charge Snyder, Inc. Six Thousand Nine Hundred Forty-five ($6,945.00) Dollars for hauling water to the construction site. There was no specific agreement that Snyder, Inc. would pay for hauling water, and Empire agreed to "hold its bid" after learning where water access was located. However, the Court finds that Empire did, in fact, haul water for Snyder and that it was at the request of Snyder's manager, and that Empire should be reimbursed for these efforts on a quantum meruit basis. The only evidence of the value of these services, is Empire's estimate of Six Thousand Nine Hundred ($6,900.00) Dollars; No evidence is presented that that price is unreasonable.
* * * # * #
28. The Contract between Empire and Snyder, Inc. was a fixed-price contract
for One Hundred Fifty Thousand Three Hundred ($150,800.00) Dollars.
24. Snyder, Inc. paid Empire all sums that Snyder, Inc. owed to Empire under the fixed-price contract. In so doing, Snyder, Inc. has paid Empire in full for Empire's work on the Dearborn Plaza project.
25. No money properly is due Empire as a consequence of its having performed labor and/or furnished materials and equipment in connection with the Dear-born Plaza project, with the exception of water hauling ... Defendant, Kern, can assert recompense for water hauling on a quantum meruit.
Empire may not properly assert a Me-chanie's Lien against the property, but is entitled to judgment in the amount of Six Thousand Nine Hundred ($6,900.00) Dollars.
26. Empire's execution of the Partial Waiver dated September 28, 1977, waived any claim for allegedly unpaid money for labor performed or materials and equipment furnished on the Dearborn Plaza project through September 28, 1977, except for the remaining balance shown on the Partial Waiver, Five Hundred Eight Dollars and five ($508.05) Cents. Snyder, Inc. paid Empire more than Five Hundred Eight Dollars and five ($508.05) Cents after September 28, 1977.
* # # # # *
29. Certain waivers were signed by the defendant, Kern's wife, as secretary for Empire, an authorized corporate officer thereof, knowingly and with full knowledge that she was receiving payments in exchange for the waiver. These were lien waivers and there is no evidence to indicate that this corporate officer did not know what she was signing or was under economic duress or for any other reason would be excused from her binding the corporation thereof with her signature on these waivers.... Empire and its officers are charged with the knowledge of the contents of the contract, specifications, and line waivers.

*1329 In reviewing the trial court's findings of fact, we neither weigh the evidence nor determine the credibility of witnesses. Gibson-Lewis Corp. v. Northern Indiana Public Service Co. (1988), Ind.App., 524 N.E.2d 1316, 1318, trams. denied. Findings of fact will be disturbed only if the record discloses that there were neither facts nor inferences on which to base the findings. Id. In other words, this Court will disturb the trial court's findings of fact and judgment only when such are clearly erroncous. See id.; Ind.Trial Rule 52(A). Pursuant to this standard of review, we will determine whether the law was correctly applied to the facts. Gibson-Lewis Corp., 524 N.E.2d at 1318.

The quoted findings indicate that the trial court considered two possible grounds for denying Kern a judgment in rem for foreclosure: first, that Kern was required by the terms of his contract with Charles R. Snyder, Inc. to obtain a written change order to modify his contract and second, that Kern had waived his right to a mechanic's lien for the water hauling expense in exchange for valuable consideration. Kern does not challenge the sufficiency of the evidence to sustain the findings; in any event, the transcript of evidence supports the findings.

Kern's own exhibits show that his water hauling claim is for work done from November 16, 1976 to June 20, 1977 ($6,000.00) and from September 2, 1977 to October 25, 1977 ($945.00). Kern's wife executed a series of waivers, the last one dated, September 28, 1977. After that date, Charles R. Snyder, Inc. paid out more than the $508.05 remaining on the contract to Kern's suppliers. Kern never submitted any claim for extras or additional compensation during the period when he was receiving draws, and made no claim for water hauling at any time before he filed his lien.

The testimony reflects that the standard in the industry and the specifications for the project placed upon Charles R. Snyder, Inc., the general contractor, the responsibility to supply water to the site. The specifications have not been made a part of the record on appeal. At a meeting in July, 1976, when the final fixed contract price was agreed upon, Charles Snyder, Sr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
625 N.E.2d 1326, 1993 Ind. App. LEXIS 1557, 1993 WL 526719, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kern-v-city-of-lawrenceburg-indctapp-1993.