Luse Thermal Technologies LLC v. Graycor Industrial Constructors Inc.

CourtIndiana Court of Appeals
DecidedOctober 16, 2023
Docket23A-PL-00633
StatusPublished

This text of Luse Thermal Technologies LLC v. Graycor Industrial Constructors Inc. (Luse Thermal Technologies LLC v. Graycor Industrial Constructors Inc.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Luse Thermal Technologies LLC v. Graycor Industrial Constructors Inc., (Ind. Ct. App. 2023).

Opinion

FILED Oct 16 2023, 8:45 am

CLERK Indiana Supreme Court Court of Appeals and Tax Court

ATTORNEYS FOR APPELLANT ATTORNEYS FOR APPELLEES Kevin E Steele Gregory S. Gistenson Burke Costanza & Carberry, LLP Eric D. Hewlett Valparaiso, Indiana Barnes & Thornburg, LLP Chicago, Illinois Ryan A. Hiss Marissa Downs Michael V. Knight Laurie & Brennan, LLP Barnes & Thornburg, LLP Chicago, Illinois South Bend, Indiana Larry G. Evans Andrew T. Shupp Hoeppner Wagner & Evans, LLP Valparaiso, Indiana Tina M. Bird Thompson Coburn, LLP Chicago, Illinois

IN THE COURT OF APPEALS OF INDIANA

Luse Thermal Technologies, October 16, 2023 LLC, Court of Appeals Case No. Appellant-Plaintiff, 23A-PL-633 Appeal from the Lake Superior v. Court The Honorable John M. Sedia, Graycor Industrial Constructors, Judge Inc. and BP Products North Trial Court Cause No. America, Inc., 45D01-2012-PL-849 Appellees-Defendants.

Court of Appeals of Indiana | Opinion 23A-PL-633 | October 16, 2023 Page 1 of 43 Opinion by Judge Riley. Judges Crone and Mathias concur.

Riley, Judge.

STATEMENT OF THE CASE [1] Appellant-Plaintiff, Luse Thermal Technologies, Inc. (Luse), appeals the trial

court’s grant of partial summary judgment in favor of Appellee-Defendant,

Graycor Industrial Constructors, Inc. (Graycor), on Luse’s request for damages

and unjust enrichment claim, and the trial court’s grant of summary judgment

in favor of Appellee-Defendant, BP Products North America, Inc. (BP), on

Luse’s claims based on the Personal Liability Notice Statute and unjust

enrichment. In addition, Luse appeals the trial court’s grant of BP’s motion to

strike certain evidentiary materials. Lastly, Luse appeals the trial court’s denial

of its motion for partial summary judgment with respect to Graycor’s

counterclaim relating to the recovery of certain contractual costs.

[2] We affirm.

ISSUES [3] Luse presents this court with several issues on appeal, which we consolidate

and restate as the following seven issues:

(1) Whether the trial court abused its discretion by striking several of Luse’s

designated evidentiary materials;

Court of Appeals of Indiana | Opinion 23A-PL-633 | October 16, 2023 Page 2 of 43 (2) Whether the trial court erred in concluding, as a matter of law, that

Luse’s damages constituted damages for delay, as defined under Article

8.8. of the subcontract between Luse and Graycor, and are not

recoverable under the provisions of the subcontract;

(3) Whether the trial court erred in concluding, as a matter of law, that Luse

cannot assert a claim against Graycor based on unjust enrichment;

(4) Whether the trial court erred in concluding, as a matter of law, that Luse

failed to comply with the Personal Liability Notice (PLN) Statute,

Indiana Code section 32-28-3-9(b);

(5) Whether the trial court erred in concluding, as a matter of law, that

Luse’s claim based on unjust enrichment against BP was precluded;

(6) Whether the trial court erred by denying Luse’s motion for partial

summary judgment on Graycor’s claim for reimbursement of additional

costs because a genuine issue of material fact was created with respect to

Graycor’s contractual entitlement to these costs; and

(7) Whether Graycor is entitled to an award of appellate attorney fees.

FACTS AND PROCEDURAL HISTORY [4] This dispute centers around the construction of a Naptha Hydrotreater system

(NHT) at BP’s plant in Whiting, Indiana (Project). The NHT is a processing

unit that removes sulfur from gasoline to reduce environmental impact. The

construction project spanned several years, involved multiple subcontractors,

and cost BP $385 million to complete. On November 16, 2017, BP issued a

Request for Proposal (RFP), seeking a general contractor to guide the Project.

Court of Appeals of Indiana | Opinion 23A-PL-633 | October 16, 2023 Page 3 of 43 On May 17, 2018, BP entered into a Master Services Agreement with Graycor

for the construction of the NHT. That same day, Graycor entered into a

subcontract with Luse for the insulation and lagging work of the Project

(Subcontract).

[5] The Subcontract specified that Luse would be paid $6,497,987 for its work on

the Project and detailed in Article 8.8 that:

8.8 Delay Claims. The Subcontractor understands and agrees that the potential for its Work being delayed by the conduct of others is inherent in any construction project, including the Project. Accordingly, and other than to the extent the Contractor receives compensation from the Owner or any other entity responsible for such delay, the Contractor shall not be liable to the Subcontractor for any damages whatsoever that may be suffered by the Subcontractor, or for which the Subcontractor may become liable, on account of any acts or omissions on the part of (a) the Contractor or those for whom it is responsible, (b) the Owner, (c) the Design Professional, or (d) any other entity that may arise from or are in any way related to the Project or the Work. The Subcontractor further agrees: (i) any such delay, other than to the extent compensation is otherwise provided in this Subcontract, shall be fully compensated for by an extension of the time to complete performance of the Work and (ii) it shall make no claim due to delay in the performance of Work against those who might have a claim against the Contractor for such damages.

(Appellant’s App. Vol. III, pp. 28-29). The Subcontract was not accompanied

by a project schedule but, in line with what had been discussed during a prior

meeting, Luse’s work would commence on May 21, 2018, and reach substantial

completion by August 22, 2019. The insulation scope of the Project was

Court of Appeals of Indiana | Opinion 23A-PL-633 | October 16, 2023 Page 4 of 43 divided into two different phases. First, Luse would mobilize immediately to

insulate several large pieces of equipment which were to be delivered by barge

to a staging area at the BP facility. Luse would then return in the spring of 2019

for a second phase, which entailed the insulation of the pipe portion of the

Project. Insulation of the pipe portion would be one of the last activities to be

completed on the NHT Project because Luse could not insulate the pipe until

the other crafts had completed their part of the work.

[6] The Project experienced a number of delays which resulted in project deadlines

being moved back. On February 6, 2019, Graycor and BP entered into what

would be the first of three settlement agreements to resolve open change orders

and claims that Graycor had submitted to BP. This First Settlement Agreement

settled “all delay controversies that have arisen between May 1, 2018, and

October 31, 2018” for a settlement payment of $2.7 million to be paid to

Graycor by BP. (Appellant’s App. Vol. VIII, p. 50). By May 2019, Luse

became concerned with the small sections of pipe which had been released for

insulation activities and Luse’s resulting inability to progress its work toward its

contractual completion deadline. As of August 22, 2019—Luse’s anticipated

completion date—Graycor had only released a small fraction of the entire pipe

portion of the Project for Luse to insulate.

[7] By the fall of 2019, the NHT Project was significantly behind schedule.

Graycor and BP reached an amicable resolution with respect to the slow

progress of the work, culminating, on November 6, 2019, in the second

settlement agreement (Second Settlement Agreement). The Second Settlement

Free access — add to your briefcase to read the full text and ask questions with AI

Related

R.L. Turner Corp. v. Town of Brownsburg
963 N.E.2d 453 (Indiana Supreme Court, 2012)
Williams v. Tharp
914 N.E.2d 756 (Indiana Supreme Court, 2009)
Zoeller v. East Chicago Second Century, Inc.
904 N.E.2d 213 (Indiana Supreme Court, 2009)
Reuille v. E.E. Brandenberger Construction, Inc.
888 N.E.2d 770 (Indiana Supreme Court, 2008)
First Federal Savings Bank of Indiana v. Key Markets, Inc.
559 N.E.2d 600 (Indiana Supreme Court, 1990)
Price v. Freeland
832 N.E.2d 1036 (Indiana Court of Appeals, 2005)
Indianapolis Raceway Park, Inc. v. Curtiss
386 N.E.2d 724 (Indiana Court of Appeals, 1979)
AKJ Industries, Inc. v. Mercantile National Bank
779 N.E.2d 543 (Indiana Court of Appeals, 2002)
Encore Hotels of Columbus, LLC v. Preferred Fire Protection
765 N.E.2d 658 (Indiana Court of Appeals, 2002)
Forty-One Associates, LLC v. Bluefield Associates, L.P.
809 N.E.2d 422 (Indiana Court of Appeals, 2004)
City of Indianapolis v. Twin Lakes Enterprises, Inc.
568 N.E.2d 1073 (Indiana Court of Appeals, 1991)
Edwards v. Bethlehem Steel Corp.
517 N.E.2d 430 (Indiana Court of Appeals, 1988)
Stafford v. Barnard Lumber Co., Inc.
531 N.E.2d 202 (Indiana Supreme Court, 1988)
Lee & Mayfield, Inc. v. Lykowski House Moving Engineers, Inc.
489 N.E.2d 603 (Indiana Court of Appeals, 1986)
Stelko Electric, Inc. v. Taylor Community Schools Building Corp.
826 N.E.2d 152 (Indiana Court of Appeals, 2005)
McCorry v. G. Cowser Construction, Inc.
644 N.E.2d 550 (Indiana Supreme Court, 1994)
Spudich v. Northern Indiana Public Service Co.
745 N.E.2d 281 (Indiana Court of Appeals, 2001)
Stout v. Kokomo Manor Apartments
677 N.E.2d 1060 (Indiana Court of Appeals, 1997)
Humphries v. Ables
789 N.E.2d 1025 (Indiana Court of Appeals, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
Luse Thermal Technologies LLC v. Graycor Industrial Constructors Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/luse-thermal-technologies-llc-v-graycor-industrial-constructors-inc-indctapp-2023.