Luse Thermal Technologies LLC v. Graycor Industrial Constructors Inc.

Indiana Court of Appeals·Decided October 16, 2023·No. 23A-PL-00633·Published

Opinion

FILED

Oct 16 2023, 8:45 am

CLERK

Indiana Supreme Court

Court of Appeals

and Tax Court

ATTORNEYS FOR APPELLANT ATTORNEYS FOR APPELLEES Kevin E Steele Gregory S. Gistenson Burke Costanza & Carberry, LLP Eric D. Hewlett Valparaiso, Indiana Barnes & Thornburg, LLP Chicago, Illinois

Ryan A. Hiss Marissa Downs Michael V. Knight Laurie & Brennan, LLP Barnes & Thornburg, LLP Chicago, Illinois South Bend, Indiana Larry G. Evans

Andrew T. Shupp

Hoeppner Wagner & Evans, LLP Valparaiso, Indiana

Tina M. Bird

Thompson Coburn, LLP

Chicago, Illinois

IN THE

COURT OF APPEALS OF INDIANA

Luse Thermal Technologies, October 16, 2023 LLC, Court of Appeals Case No. Appellant-Plaintiff, 23A-PL-633 Appeal from the Lake Superior v. Court The Honorable John M. Sedia, Graycor Industrial Constructors, Judge Inc. and BP Products North Trial Court Cause No. America, Inc., 45D01-2012-PL-849 Appellees-Defendants.

Court of Appeals of Indiana | Opinion 23A-PL-633 | October 16, 2023 Page 1 of 43

Opinion by Judge Riley.

Judges Crone and Mathias concur.

Riley, Judge.

STATEMENT OF THE CASE [1] Appellant-Plaintiff, Luse Thermal Technologies, Inc. (Luse), appeals the trial

court’s grant of partial summary judgment in favor of Appellee-Defendant, Graycor Industrial Constructors, Inc. (Graycor), on Luse’s request for damages and unjust enrichment claim, and the trial court’s grant of summary judgment in favor of Appellee-Defendant, BP Products North America, Inc. (BP), on Luse’s claims based on the Personal Liability Notice Statute and unjust enrichment. In addition, Luse appeals the trial court’s grant of BP’s motion to strike certain evidentiary materials. Lastly, Luse appeals the trial court’s denial of its motion for partial summary judgment with respect to Graycor’s counterclaim relating to the recovery of certain contractual costs.

[2] We affirm.

ISSUES [3] Luse presents this court with several issues on appeal, which we consolidate

and restate as the following seven issues:

(1) Whether the trial court abused its discretion by striking several of Luse’s designated evidentiary materials;

(2) Whether the trial court erred in concluding, as a matter of law, that Luse’s damages constituted damages for delay, as defined under Article 8.8. of the subcontract between Luse and Graycor, and are not recoverable under the provisions of the subcontract;

(3) Whether the trial court erred in concluding, as a matter of law, that Luse cannot assert a claim against Graycor based on unjust enrichment;

(4) Whether the trial court erred in concluding, as a matter of law, that Luse failed to comply with the Personal Liability Notice (PLN) Statute, Indiana Code section 32-28-3-9(b);

(5) Whether the trial court erred in concluding, as a matter of law, that Luse’s claim based on unjust enrichment against BP was precluded;

(6) Whether the trial court erred by denying Luse’s motion for partial summary judgment on Graycor’s claim for reimbursement of additional costs because a genuine issue of material fact was created with respect to Graycor’s contractual entitlement to these costs; and (7) Whether Graycor is entitled to an award of appellate attorney fees.

FACTS AND PROCEDURAL HISTORY [4] This dispute centers around the construction of a Naptha Hydrotreater system

(NHT) at BP’s plant in Whiting, Indiana (Project). The NHT is a processing unit that removes sulfur from gasoline to reduce environmental impact. The construction project spanned several years, involved multiple subcontractors, and cost BP $385 million to complete. On November 16, 2017, BP issued a Request for Proposal (RFP), seeking a general contractor to guide the Project.

On May 17, 2018, BP entered into a Master Services Agreement with Graycor for the construction of the NHT. That same day, Graycor entered into a subcontract with Luse for the insulation and lagging work of the Project (Subcontract).

[5] The Subcontract specified that Luse would be paid $6,497,987 for its work on the Project and detailed in Article 8.8 that:

8.8 Delay Claims. The Subcontractor understands and agrees that the potential for its Work being delayed by the conduct of others is inherent in any construction project, including the Project. Accordingly, and other than to the extent the Contractor receives compensation from the Owner or any other entity responsible for such delay, the Contractor shall not be liable to the Subcontractor for any damages whatsoever that may be suffered by the Subcontractor, or for which the Subcontractor may become liable, on account of any acts or omissions on the part of (a) the Contractor or those for whom it is responsible, (b)

the Owner, (c) the Design Professional, or (d) any other entity that may arise from or are in any way related to the Project or the Work. The Subcontractor further agrees: (i) any such delay, other than to the extent compensation is otherwise provided in this Subcontract, shall be fully compensated for by an extension of the time to complete performance of the Work and (ii) it shall make no claim due to delay in the performance of Work against those who might have a claim against the Contractor for such damages.

(Appellant’s App. Vol. III, pp. 28-29). The Subcontract was not accompanied by a project schedule but, in line with what had been discussed during a prior meeting, Luse’s work would commence on May 21, 2018, and reach substantial completion by August 22, 2019. The insulation scope of the Project was divided into two different phases. First, Luse would mobilize immediately to insulate several large pieces of equipment which were to be delivered by barge to a staging area at the BP facility. Luse would then return in the spring of 2019 for a second phase, which entailed the insulation of the pipe portion of the Project. Insulation of the pipe portion would be one of the last activities to be completed on the NHT Project because Luse could not insulate the pipe until the other crafts had completed their part of the work.

[6] The Project experienced a number of delays which resulted in project deadlines being moved back. On February 6, 2019, Graycor and BP entered into what would be the first of three settlement agreements to resolve open change orders and claims that Graycor had submitted to BP. This First Settlement Agreement settled “all delay controversies that have arisen between May 1, 2018, and October 31, 2018” for a settlement payment of $2.7 million to be paid to Graycor by BP. (Appellant’s App. Vol. VIII, p. 50). By May 2019, Luse became concerned with the small sections of pipe which had been released for insulation activities and Luse’s resulting inability to progress its work toward its contractual completion deadline. As of August 22, 2019—Luse’s anticipated completion date—Graycor had only released a small fraction of the entire pipe portion of the Project for Luse to insulate.

[7] By the fall of 2019, the NHT Project was significantly behind schedule. Graycor and BP reached an amicable resolution with respect to the slow progress of the work, culminating, on November 6, 2019, in the second settlement agreement (Second Settlement Agreement). The Second Settlement

Agreement increased Graycor’s baseline contract price to $147 million, which represented an increase of approximately $27 million, and further contained an explicit commitment from Graycor that liquidated damages could be assessed against it at the rate of $250,000 per week up to a cap of $1 million in the event that Graycor would not finalize the work by the new deadline of January 31, 2020.

Free access — add to your briefcase to read the full text and ask questions with AI

Luse Thermal Technologies LLC v. Graycor Industrial Constructors Inc., (Ind. Ct. App. 2023).

Luse Thermal Technologies LLC v. Graycor Industrial Constructors Inc. (Luse Thermal Technologies LLC v. Graycor Industrial Constructors Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

R.L. Turner Corp. v. Town of Brownsburg
963 N.E.2d 453 (Indiana Supreme Court, 2012)
Williams v. Tharp
914 N.E.2d 756 (Indiana Supreme Court, 2009)
Zoeller v. East Chicago Second Century, Inc.
904 N.E.2d 213 (Indiana Supreme Court, 2009)
Reuille v. E.E. Brandenberger Construction, Inc.
888 N.E.2d 770 (Indiana Supreme Court, 2008)
First Federal Savings Bank of Indiana v. Key Markets, Inc.
559 N.E.2d 600 (Indiana Supreme Court, 1990)
Price v. Freeland
832 N.E.2d 1036 (Indiana Court of Appeals, 2005)
Indianapolis Raceway Park, Inc. v. Curtiss
386 N.E.2d 724 (Indiana Court of Appeals, 1979)
AKJ Industries, Inc. v. Mercantile National Bank
779 N.E.2d 543 (Indiana Court of Appeals, 2002)
Encore Hotels of Columbus, LLC v. Preferred Fire Protection
765 N.E.2d 658 (Indiana Court of Appeals, 2002)
Forty-One Associates, LLC v. Bluefield Associates, L.P.
809 N.E.2d 422 (Indiana Court of Appeals, 2004)
City of Indianapolis v. Twin Lakes Enterprises, Inc.
568 N.E.2d 1073 (Indiana Court of Appeals, 1991)
Edwards v. Bethlehem Steel Corp.
517 N.E.2d 430 (Indiana Court of Appeals, 1988)
Stafford v. Barnard Lumber Co., Inc.
531 N.E.2d 202 (Indiana Supreme Court, 1988)
Lee & Mayfield, Inc. v. Lykowski House Moving Engineers, Inc.
489 N.E.2d 603 (Indiana Court of Appeals, 1986)
Stelko Electric, Inc. v. Taylor Community Schools Building Corp.
826 N.E.2d 152 (Indiana Court of Appeals, 2005)
McCorry v. G. Cowser Construction, Inc.
644 N.E.2d 550 (Indiana Supreme Court, 1994)
Spudich v. Northern Indiana Public Service Co.
745 N.E.2d 281 (Indiana Court of Appeals, 2001)
Stout v. Kokomo Manor Apartments
677 N.E.2d 1060 (Indiana Court of Appeals, 1997)
Humphries v. Ables
789 N.E.2d 1025 (Indiana Court of Appeals, 2003)