Mercantile National Bank of Indiana v. First Builders of Indiana, Inc.

774 N.E.2d 488, 2002 Ind. LEXIS 674, 2002 WL 1978820
CourtIndiana Supreme Court
DecidedAugust 27, 2002
Docket45S03-0102-CV-100
StatusPublished
Cited by10 cases

This text of 774 N.E.2d 488 (Mercantile National Bank of Indiana v. First Builders of Indiana, Inc.) is published on Counsel Stack Legal Research, covering Indiana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mercantile National Bank of Indiana v. First Builders of Indiana, Inc., 774 N.E.2d 488, 2002 Ind. LEXIS 674, 2002 WL 1978820 (Ind. 2002).

Opinion

ON PETITION TO TRANSFER

SULLIVAN, Justice.

When the general contractor on a construction project fails to pay its subcontractor, the subcontractor may seek payment from the project owner under Indiana’s “personal liability” statute. A personal liability claim is limited by the “amount due” the contractor and we hold that limit is calculated by placing the subcontractor in the same position that the general contractor would occupy in a lawsuit with the owner. In this case, the owner has no personal liability because the subcontractor failed to plead a personal liability claim and the owner did not consent to the issue being litigated at trial.

Background

Horst and Marianne Thompson (“Owner”) entered into a construction contract with First Builders of Indiana, Inc. (“Contractor”), under which Contractor was to build a house for Owner. Contractor opened an account with Schilling Brothers Lumber and Hardware, Inc. (“Subcontractor”), from which Contractor obtained construction materials for the project. After construction had proceeded for a period of time without incident, Owner discovered that Contractor was not following the blueprints and also discovered certain construction defects. Owner refused to pay Contractor any further amounts under the contract and subsequently finished the construction of the house without Contractor. Not surprisingly, Contractor sued Owner and Owner filed a counter-claim against Contractor.

Caught up in this dispute was Subcontractor who had not been paid amounts due from Contractor for materials supplied for use on the project. Subcontractor joined the lawsuit, filing two claims for payment against Contractor. Subcontractor also filed a claim against Owner, seeking to enforce a “mechanics’ lien.”

Enforcement of a “mechanics’ lien” is one of two statutory mechanisms that Indiana law provides for subcontractors that have not been paid by their contractors to seek payment from construction project owners. Ind.Code § 32-8-3-1 through 8 (the “Mechanics’ Lien Statute”). The second mechanism, although located in the Indiana Code chapter dealing with mechanics’ liens, is completely separate. It imposes “personal liability” on project owners in favor of subcontractors that have not been paid by their contractors, subject to certain limitations that are crucial in this case. Ind.Code § 32-8-3-9 (the “Personal Liability Statute”).

As noted, Subcontractor filed a claim against Owner to enforce a “mechanics’ hen” under the Mechanics’ Lien Statute. Subcontractor also sent a notice to Owner informing it that Subcontractor would seek to hold it personally liable for the amounts owed to it by Contractor. However, Subcontractor did not amend its complaint to assert a claim of “personal liability” under the Personal Liability Statute.

The Mechanics’ Lien Statute contains a number of strict notice requirements with which Subcontractor had not complied. As a consequence, the trial court granted summary judgment in favor of Owner pri- or to trial, finding that Subcontractor had not followed the requirements of the Mechanics’ Lien Statute. 1 The balance of the lawsuit continued, involving (at least) the claims between Owner and Contractor and between Contractor and Subcontractor.

After a bench trial, the trial court found that Owner was not hable to Contractor because of Contractor’s breach of contract. However, the trial court found that Owner *490 was liable to Subcontractor because Subcontractor held a valid and enforceable mechanic’s lien on Owner’s house. As should be apparent, this was the very-same issue on which the trial court had previously granted summary judgment in favor of Owner.

The Owner appealed but the Court of Appeals affirmed. While acknowledging that the trial court was “incorrect” in finding that Subcontractor was entitled to enforce a “mechanic’s lien,” the Court of Appeals held that the trial court’s judgment in favor of Subcontractor could “properly be affirmed on at [the] alternative legal theory” that Subcontractor was entitle to collect from Owner under the Personal Liability Statute. Mercantile Nat’l Bank of Indiana v. First Builders of Indiana, Inc., 732 N.E.2d 1287, 1290 (Ind.Ct.App.2000).

Discussion

I

Under Background, supra, we -briefly discussed the two statutory mechanisms Indiana law provides to permit a subcontractor that has not been paid by its general contractor to seek recovery from the owner of the construction project. It is worth spending a little more time distinguishing those mechanisms.

The Mechanics’ Lien Statute provides a procedure for persons who perform labor or furnish materials or machinery for construction projects to establish and enforce a lien on the structure on which they have worked or for which they have furnished materials or machinery and on the interest of the owner of the land on which the structure stands or with which it is connected to the extent of the value of the work performed and material furnished.

The Personal Liability Statute provides a procedure for subcontractors, workers employed by others, and persons who lease materials or machinery for construction projects to establish liability on the part of the owner of the project for the amount owed to such subcontractors, workers, and persons by their respective contractors, employers, and lessees.

A key difference between the Mechanics’ Lien Statute and the Personal Liability Statute is that under the Personal Liability Statute,- the amount of the owner’s liability shall not “exceed the amount which may be due, and may thereafter become due, from [the owner] to [such contractor,] employer or lessee.” Ind.Code § 32-8-3-9. The Indiana Personal Liability Statute, as Judge Posner has pointed out, “thus differs from a mechanics’ lien law, which by creating a secured interest gives a subcontractor priority over the owner’s unsecured creditors. Indiana mechanics’ lien law, moreover, does not, at least in so many words, limit the subcontractor’s lien to the amount that the owner owes the contractor.” See Coplay Cement Co., Inc. v. Willis & Paul Group, 983 F.2d 1435, 1437 (7th Cir.1993) (citations and subsequent discussion on possible limitation on amount recoverable under mechanics’ lien law omitted).

When the Court of Appeals found that the trial court’s judgment in favor of Subcontractor could be affirmed under the Personal Liability Statute, it was required to confront this limitation on recovery. That is, unless there were amounts still owed by Owner to Contractor, this limitation would preclude recovery by Subcontractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
774 N.E.2d 488, 2002 Ind. LEXIS 674, 2002 WL 1978820, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mercantile-national-bank-of-indiana-v-first-builders-of-indiana-inc-ind-2002.