City of Indianapolis v. Twin Lakes Enterprises, Inc.

568 N.E.2d 1073, 1991 Ind. App. LEXIS 447, 1991 WL 44442
CourtIndiana Court of Appeals
DecidedMarch 28, 1991
Docket30A01-9005-CV-187
StatusPublished
Cited by69 cases

This text of 568 N.E.2d 1073 (City of Indianapolis v. Twin Lakes Enterprises, Inc.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Indianapolis v. Twin Lakes Enterprises, Inc., 568 N.E.2d 1073, 1991 Ind. App. LEXIS 447, 1991 WL 44442 (Ind. Ct. App. 1991).

Opinion

ROBERTSON, Judge.

The City of Indianapolis (the City) appeals from a jury verdict in favor of Twin Lakes Enterprises, Inc. (Twin Lakes) in Twin Lakes' suit for damages for breach of contract or, alternatively, for compensation for the City's unjust enrichment in quasi-contract. The City claims the evidence is insufficient to support a judgment based upon its breach of contract or, if the evidence is sufficient, Twin Lakes' waiver precludes a recovery for breach of contract. The City also alleges that the trial court erroneously submitted the issue of quasi-contract to the jury when a contract governed the relationship of the parties and that the trial court submitted an erroneous instruction to the jury on the issue of quasi-contract. The City further contends the trial court improperly instructed the jury on other matters and refused to submit a proper instruction. Finally, the City claims the trial court improperly awarded prejudgment interest to Twin Lakes. We affirm in *1076 part and remand for modification of the judgment.

The evidence most favorable to the judgment below reveals that the City sought bids for construction of a rowing course on the Eagle Creek Reservoir for the Pan Am Games and entered into a contract with Twin Lakes for that purpose. The contract stated that Twin Lakes was to provide all labor and materials and do all things necessary for the proper construction and completion of the project in accordance with the plans and specifications provided by the City's subcontracted engineers. The contract provided that Twin Lakes was to dredge the site of the rowing course of silt and sand by means of a suction hose to produce a flat, mud bottom in the bed of the reservoir. The evidence also reveals that the City, through its employees, knew of the existence of large obstructions on the floor of the reservoir inconsistent with the manner in which Twin Lakes was to dredge the reservoir bed.

I.

Is the evidence sufficient to support the judgment for breach of contract; and, if so, has Twin Lakes waived recovery on that issue?

The City claims the evidence presented does not establish a breach of contract. Twin Lakes counters with a contention that the City breached the contract when it failed to fully disclose the conditions at the proposed site of the rowing course, specifically the existence of the large obstructions. We conclude such evidence was sufficient to establish a breach of the contract by the City.

When we review the sufficiency of the evidence to support the judgment of the trial court, we neither weigh evidence nor judge witness credibility. Rather, we will affirm the judgment of the trial court if it is supported by sufficient evidence when viewed most favorably to the appellee, here Twin Lakes. Jos. Schlitz Brewing v. Central Bev. Co., Inc. (1977), 172 Ind.App. 81, 359 N.E.2d 566.

The City first alleges that the contract between the parties placed the burden upon Twin Lakes to discover any obstructions which subsequently hindered its progress of the project. The City cites the following pertinent part of the contract:

BIDDERS SHALL EXAMINE THE SITE AND THOROUGHLY FAMILIARIZE THEMSELVES WITH THE SITE AND ALL CONDITIONS IN CONNECTION THEREWITH. LACK OF FAMILIARITY WITH THE SITE AND PRESENT CONDITIONS WILL NOT BE CONSIDERED AS JUSTIFICATION FOR CHANGES OR EXTRA CHARGES OF ANY KIND, SINCE ANY CONTRACT, IN WHOLE OR IN PART WILL BE BASED ON THE ASSUMPTION THE BIDDER KNOWS, UNDERSTANDS AND ACCEPT THESE EXISTING CONDITIONS.

However, as Twin Lakes contends, the evidence also shows the City assumed at least some responsibility to inform Twin Lakes about the conditions of the dredge site. The contract stated that Twin Lakes was to provide all labor and materials and do all things necessary for the proper construction and completion of the project in accordance with the plans and specifications provided by the City. These plans and specifications contained no information about the obstructions at the site even though Twin Lakes was expected to rely upon them when it dredged the site. In addition, the contract provided that an on-site meeting would be scheduled by the City for the benefit of the bidders to acquaint them with the site conditions and to answer bidding questions. Twin Lakes attended this meeting, but the City provided no information about the existence of obstructions on the bed of the reservoir.

We will address one of the City's contentions at this point because to do so will facilitate our review. The City claims the evidence is insufficient to show it knew of the dumping of large obstructions at the site where dredging was to take place. The City maintains that it has consistently denied having had such knowledge and that any dumping about which it had knowledge occurred outside the dredge site in very *1077 small amounts. However, the evidence also shows that the City defined the job in the contract as a sand and silt dredging operation. Twin Lakes was supposed to accomplish the work with a suction hose, which an employee for the City had told one witness could not be done because of the existence of obstructions in the dredge site. Moreover, although much of the evidence addresses itself to mining, excavation, and dumping of materials on land adjacent to the reservoir, there is also evidence that the stream bed for the creek near the dredge site was moved after these activities had begun. The record therefore contains sufficient evidence from which the jury could have concluded that the large obstructions had been dumped in the reservoir with the City's knowledge at the location which eventually became the dredge site and that the City had known of the large obstructions both before and after it had entered into the contract.

We now proceed with our analysis and note that the question of whether a breach of contract has occurred is a question of fact to be determined by the jury. Strong v. Commercial Carpet Co., Inc. (1975), 163 Ind.App. 145, 822 N.E.2d 387, rehearing denied in port, 168 Ind.App. 145, 324 N.E.2d 884. The above recited evidence is sufficient for the jury to conclude that the City led Twin Lakes to believe, through the language of the contract, that it would disclose what it knew about the site conditions but then failed to inform Twin Lakes that it had previously permitted others to dump large obstructions at the dredge site. Moreover, the jury could have concluded that Twin Lakes went to the location of the project with City representatives, examined the site, and attempted to thoroughly familiarize itself with the site and its conditions, only to be thwarted by the City's silence about large obstructions, which lay underwater and out of sight, at a time when the City had assumed responsibility to acquaint Twin Lakes with the site. If all of these these facts are taken as true, as we must assume they were, then the City failed to perform the obligations it assented to undertake in the agreement and thereby breached the contract.

The City also claims the evidence is insufficient in several other respects to support a breach of contract on its part. Specifically, the City alleges it was not proved to have breached the contract when it flooded the dredge site, when it failed to pay on the contract, or when it expelled Twin Lakes from the project site in favor of another contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

James A Simon v. William R Simon Farms Inc.
Indiana Court of Appeals, 2024
Hess v. Biomet, Inc.
N.D. Indiana, 2022
John Barkers and Specialty Limos, LLC v. Jason Price
48 N.E.3d 367 (Indiana Court of Appeals, 2015)
AM General LLC v. James A. Armour
46 N.E.3d 436 (Indiana Supreme Court, 2015)
Gayle Fischer v. Michael and Noel Heymann
12 N.E.3d 867 (Indiana Supreme Court, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
568 N.E.2d 1073, 1991 Ind. App. LEXIS 447, 1991 WL 44442, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-indianapolis-v-twin-lakes-enterprises-inc-indctapp-1991.