Burras v. Canal Construction & Design Co.

470 N.E.2d 1362, 1984 Ind. App. LEXIS 3043
CourtIndiana Court of Appeals
DecidedNovember 20, 1984
Docket1-483 A 103
StatusPublished
Cited by36 cases

This text of 470 N.E.2d 1362 (Burras v. Canal Construction & Design Co.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Burras v. Canal Construction & Design Co., 470 N.E.2d 1362, 1984 Ind. App. LEXIS 3043 (Ind. Ct. App. 1984).

Opinion

RATLIFF, Judge.

STATEMENT OF THE CASE

This is an action for the breach of a construction contract. At trial, Canal Construction and Design (Canal) was awarded $9,864.07 in damages and $12,000 in fees based on the Burras' breach of the contract. - The Burrases were awarded $7,970.00 on their counterclaim against Canal for defective performance and breach of Warranty but denied relief on certain other theories in their counterclaim. This denial together with the trial court's award of compensatory damages and its refusal to award the Burrases punitive damages form the basis of their appeal. The Bur-rases also challenge the propriety of the $12,000 attorney fee award. We affirm in part and reverse in part.

EACTS

On August 25, 1980, the parties to the present action entered into a construction contract. Canal agreed to act as general contractor supervising the construction of a home for the Burrases in Noblesville, Indiana. The Burrases had previously received bids from other general contractors but became interested in hiring Canal after its second bid was approximately $80,000 less than the first bid. As further inducement, Canal presented a home in Eagle Creek as a model of work they had done in the past. Steve Miller, one of the principals of Canal, took the Burrases on a tour of the inside of the home, representing that Canal had managed its construction and done the trim carpentry and finishing work. Shortly thereafter, the contract for the construction of the Burras home was executed and Canal began work on the project about September 1, 1980.

A few months after construction began, differences arose between the parties. The house was to be substantially completed in 180 days. However, delays occurred and each side blamed the other for the delays. The contract price was set at $152,785, but by May of 1981, the Burrases had spent more than this amount and were dissatisfied with Canal's work. The dissatisfaction involved Canal's performance under the general contract and also trim carpentry which Canal was doing pursuant to a separate agreement executed with the Burrases in March, 1981.

On April 25, 1981, Canal received a letter from the Burrases stating that they felt compelled to alter the payment scheme originally set out in the general contract. Instead of submitting bills for material and labor to the Burrases for immediate payment on a weekly basis, payment would be made only after the Burrases were satisfied the work had been completed. On May 7, the Burrases received a letter in reply stating that such a modification was unacceptable to Canal and unless payments were made as originally provided in the contract, they would consider the Burrases *1365 in default. After receiving this letter, Mrs. Burras went to the construction site and told Steve Miller that Canal would receive no more payments until the house was completely finished. At this point, Canal walked off the job and soon afterward sued the Burrases for breach of contract. The Burrases filed a counterclaim alleging that Canal had breached both the general and trim contracts by walking off the job and breached its express warranty regarding labor. The counterclaim alleged violation of Indiana Code section 32-8-1-2, slander of title, fraud, and conversion and requested punitive damages. The trial court entered a general verdict finding Canal liable for breach of warranty and defective performance. The trial judge dismissed the claims based on Indiana Code section 82-8-1-2, slander of title, fraud, and conversion.

ISSUES

Due to our decision the issues presented for review are as follows:

1. Was there sufficient evidence to support the trial court's finding that the Bur-rases breached the construction contract?

2. Was the trial court's finding that the Burrases should receive damages for defective performance and breach of warranty inconsistent with the finding that the Bur-rases breached the construction contract?

8. Did the trial court err by involuntarily dismissing the Burrases counterclaims for:

(a) Conversion

(b) Fraud

(c) Slander of title

(d) Relief under Indiana Code section 82-8-1-2? >

4. Was the damage award to the Bur-rases for Canal's defective performance and breach of warranty inadequate?

5. Was the trial judge's award of $12,-000 in attorney fees to Canal excessive?

6. Was it proper for the trial court to award attorney fees incurred by Canal on appeal?

DISCUSSION AND DECISION

Issue One

The Burrases argue that the trial court erred in finding that they breached the contract. The general verdict by the trial judge states:

"Comes now the Court and being duly advised now enters judgment for Plaintiff and against defendants on Paragraph 1 of plaintiff's complaint for breach of contract in the principal sum of $9864.07 with prejudgment interest in the sum of $1188.69 and attorney fees in the sum of $12,000.00 and the Court being duly advised now enters judgment for defendants and against plaintiff on defendant's counterclaims for defective performance and breach of warranty in the sum of $7970.90."

Record at 290.

The Burrases' argument is that the evidence is insufficient to support a finding that they breached the contract. Our standard on review of claims that the evidence is insufficient to support the trial court's judgment is clear.

"In reviewing the sufficiency of evidence in a civil cage, we will decide whether there is substantial evidence of probative value supporting the trial court's judgment. We neither weigh the evidence nor judge the credibility of witnesses but consider only the evidence most favorable to the judgment along with all reasonable inferences to be drawn therefrom. Only if there is a lack of evidence or evidence from which a reasonable inference can be drawn on an essential element of plaintiff's claim will we reverse a trial court."

Martin v. Roberts, (1984) Ind., 464 N.E.2d 896, 904.

In viewing the evidence most favorable to the judgment it appears that Burrases attempt to alter the payment scheme clearly constituted a breach of the construction contract. The provision in the contract regarding payment indicates unambiguously that the Burrases agreed to *1366 pay for material and labor when these bills were presented to them by Canal.

"5. Payments to Contractor. On a weekly basis, Contractor shall submit to Owner and Owner's lender, all bills, invoices, schedules for payment, and other records submitted to Contractor for work done hereunder or materials delivered pursuant hereto. - Upon delivery of such, Owner, or Owner's lender shall pay said amount, plus ten percent of such amount to Contractor. (Emphasis supplied.)"

Record at 851-68. The Burrases' letter to Canal dated April 25, 1981, attempting to alter the contractual provision stated in pertinent part as follows:

"[Wle feel compelled to alter our past payment routine. [The new payment process we feel would be fair to all concerned.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Planning Partners International, LLC v. QED, Inc.
2013 CO 43 (Supreme Court of Colorado, 2013)
Rogers Group, Inc. v. Diamond Builders, LLC
816 N.E.2d 415 (Indiana Court of Appeals, 2004)
Greg Allen Const. Co., Inc. v. Estelle
762 N.E.2d 760 (Indiana Court of Appeals, 2002)
Abbey Villas Development Corp. v. Site Contractors, Inc.
716 N.E.2d 91 (Indiana Court of Appeals, 1999)
Poehlman v. Feferman
693 N.E.2d 1355 (Indiana Court of Appeals, 1998)
Nelson v. Marchand
691 N.E.2d 1264 (Indiana Court of Appeals, 1998)
Pepsi-Cola Co. v. Steak 'N Shake, Inc.
981 F. Supp. 1149 (S.D. Indiana, 1997)
DeChristofaro v. MacHala
685 A.2d 258 (Supreme Court of Rhode Island, 1996)
Yin v. Society National Bank Indiana
665 N.E.2d 58 (Indiana Court of Appeals, 1996)
Houston v. Booher
647 N.E.2d 16 (Indiana Court of Appeals, 1995)
Hamlin v. Steward
622 N.E.2d 535 (Indiana Court of Appeals, 1993)
TRW, INC. v. Fox Development Corp.
604 N.E.2d 626 (Indiana Court of Appeals, 1992)
Willie's Const. Co., Inc. v. Baker
596 N.E.2d 958 (Indiana Court of Appeals, 1992)
Fordeck-Kemerly Electric, Inc. v. Helmkamp
591 N.E.2d 1035 (Indiana Court of Appeals, 1992)
City of Indianapolis v. Twin Lakes Enterprises, Inc.
568 N.E.2d 1073 (Indiana Court of Appeals, 1991)
Gorbett v. Claycamp
543 N.E.2d 401 (Indiana Court of Appeals, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
470 N.E.2d 1362, 1984 Ind. App. LEXIS 3043, Counsel Stack Legal Research, https://law.counselstack.com/opinion/burras-v-canal-construction-design-co-indctapp-1984.