TRW, INC. v. Fox Development Corp.

604 N.E.2d 626, 1992 Ind. App. LEXIS 1823, 1992 WL 358261
CourtIndiana Court of Appeals
DecidedDecember 8, 1992
Docket11A04-9010-CV-00468
StatusPublished
Cited by12 cases

This text of 604 N.E.2d 626 (TRW, INC. v. Fox Development Corp.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
TRW, INC. v. Fox Development Corp., 604 N.E.2d 626, 1992 Ind. App. LEXIS 1823, 1992 WL 358261 (Ind. Ct. App. 1992).

Opinion

MILLER, Judge.

Fox Development Corp. (Fox) entered into an agreement to manage the construction of TRW, Inc.'s (TRW) building expansion project. The Construction Management Agreement (Agreement) provided that the building would be constructed for a "guaranteed maximum price" of $861,-950-$783,590.91 for materials and labor, and $78,859.09 for Fox's construction management fee. A dispute arose over how much TRW owed Fox. Fox sued TRW for breach of contract. A jury awarded Fox $50,082.11 in compensatory damages-$6,535.30 for wall costs, $13,986.89 for construction management fees, interest, and attorneys fees-plus $750,000 in punitive damages. TRW claims that the written Agreement is unambiguous; therefore, interpretation of the contract was a question of law for the court and should not have gone to the jury.

We agree and reverse.

FACTS

In 1981, TRW sought bids for the expansion of its manufacturing facility located in Marshall, Illinois. Fox, a newly formed construction company located in Terre Haute, Indiana, submitted a building proposal based on some preliminary discussions with TRW. According to Fox's building proposal, "the construction process [would] integrate the Solarerete Wall System." R. 304. Solarerete walls are constructed by blowing high density concrete under high pressure into a polystyrene wall form. The result is a strong, energy efficient wall. Fox was certified by Solarcrete as a Solarcrete area developer and was authorized to use Solarcrete's patented construction methods.

After negotiating the cost of the expansion project, the parties entered into an *628 agreement whereby Fox would act as the project's construction manager. The pertinent provisions of the nine-page Agreement are:

[Fox] will perform those services which, more specifically hereinafter described, shall include consultation with [TRW] and [TRW's] designated representative, on construction related matters during development of the design and shall consist of the actual management, direction and responsibility for the construction of the Work, [Fox] being an Agent of [TRW] for the purposes of construction and completion of the Work.
* # # # L #
1.2 This Agreement represents the entire Agreement between [TRW] and [Fox] and supersedes all prior representations, negotiations or agreements. When plans and specifications are complete, they shall be identified by amendment to this Agreement. This Agreement shall not be superseded by any provisions of the documents for construction and may be amended only by written by both [TRW] and [Fox]. instrument
# * # * * *
4.1 All portions of the Work that the Construction Manager does not perform with his own forces shall be performed under Trade Contracts. The Construetion Manager shall request and receive proposals from Trade Contractors and Materials Vendors. Trade contracts and Purchase Orders will be awarded and administered in the name of the Owner by the Construction Manager as the Owner's agent. When the Agreement between the Construction Manager as Owner's Agent and the Trade Contractor and/or Materials Vendors involves an amount in excess of $100.00, the Construction Manager shall secure the approval of the Owner before contracting in the Owner's behalf.
* * # # a *
6.1 The Guaranteed Maximum Price shall be the sum of Eight Hundred Sixty One Thousand Nine Hundred Fifty Dollars ($861,950.00). The Guaranteed Maximum Price shall include only the actual cost of labor and materials furnished to perform and complete the Work and shall include the Construction Manager's Fee.
* * L # # *
7.1 In consideration of the performance of this Agreement, [TRW] agrees to pay [Fox] in current funds as compensation for his services a Construction Manager's Fee fixed in an amount equal to ten percent (10%) of the actual cost of labor and materials furnished to perform and complete the work.
# #k # * # *
8.1 [TRW], without invalidating <the Contract, may order Changes in the work within the general scope of the Contract consisting of additions, deletions or other revisions, the Guaranteed Maximum Price, and the Contract Time Schedule being adjusted accordingly. All such changes in the Work shall be authorized by Change Order.
8.2 A Change Order is a written order to [Fox] signed by [TRW] or this authorized agent issued after the execution of the Contract, authorizing a Change in the Work and/or an adjustment in the Guaranteed Maximum Price or the Contract Time Schedule."

R. 880-88. Fox's attorney prepared the Agreement and submitted it to TRW before the building plans were completed. In addition to the construction management fee, TRW paid Fox $10,000 to design the project.

When Fox solicited bids for the Solar-crete walls, the bids came in higher than Fox had estimated. In an effort to limit costs, Fox decided to build the Solarcrete walls itself and organized a subsidiary corporation, Crete Construction, for this purpose. James Libke (Libke), a Fox official, testified he had a "handshake agreement" with TRW that Fox (through Crete Construction) would build the walls "with the understanding that whatever it cost, [Fox] would be reimbursed on a periodic basis as the expenses and costs were incurred." R. 868-64.

*629 Crete Construction encountered difficulties in constructing the Solarerete walls, so Fox hired another subcontractor, Tri-State Solarerete, to complete the walls. Liens were filed against the TRW project, principally for equipment and subcontract work needed to complete the Solarerete walls. TRW discharged the liens, and with Fox's consent, deducted the lien payments from Fox's construction management fee.

At trial, Fox claimed TRW owed them $6,585.30 over and above the guaranteed maximum price for materials and labor costs incurred in constructing the Solar-crete walls and that TRW wrongfully withheld $18,986.89 in Construction Management Fees. TRW maintained that the contract was clear and unambiguous and that it had paid Fox all that it was obligated to pay under the guaranteed maximum price provision.

TRW moved for summary judgment before trial, a directed verdict after Fox presented its evidence, and again after presenting its own evidence. 1 However, the judge permitted Fox's breach of contract claim to go to the jury. TRW's Motion to Correct Errors, challenging both the compensatory and punitive damage awards, was overruled.

DECISION

TRW claims that the trial court erred in denying its motion for judgment on the evidence on Fox's breach of contract claim because TRW's financial obligations to Fox were limited to the guaranteed maximum price set forth in the Agreement. When reviewing the trial court's denial of a motion for judgment on the evidence, we will consider only the evidence most favorable to the nonmovant along with all reasonable inferences therefrom. Northern Indiana Public Service, Co. v. Stokes (1986), Ind.App., 493 N.E.2d 175

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Facilities Cost Mgmt. Group v. Otoe Cty. Sch. Dist.
291 Neb. 642 (Nebraska Supreme Court, 2015)
Trustees of Indiana University v. Cohen
910 N.E.2d 251 (Indiana Court of Appeals, 2009)
Zusy v. International Medical Group, Inc.
500 F. Supp. 2d 1087 (S.D. Indiana, 2007)
F.E. Gates Co. v. Hydro-Technologies, Inc.
722 N.E.2d 898 (Indiana Court of Appeals, 2000)
Fellows v. Board of Trustees of Welborn Clinic
63 F. Supp. 2d 942 (S.D. Indiana, 1998)
Zemco Manufacturing, Inc. v. Pecoraro
703 N.E.2d 1064 (Indiana Court of Appeals, 1998)
CSX Transportation, Inc. v. Kirby
687 N.E.2d 611 (Indiana Court of Appeals, 1997)
Kirchoff v. Selby
686 N.E.2d 121 (Indiana Court of Appeals, 1997)
Kovatch Mobile Equipment Corp. v. Warren Township
831 F. Supp. 665 (S.D. Indiana, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
604 N.E.2d 626, 1992 Ind. App. LEXIS 1823, 1992 WL 358261, Counsel Stack Legal Research, https://law.counselstack.com/opinion/trw-inc-v-fox-development-corp-indctapp-1992.