F.E. Gates Co. v. Hydro-Technologies, Inc.

722 N.E.2d 898, 2000 Ind. App. LEXIS 66, 2000 WL 92209
CourtIndiana Court of Appeals
DecidedJanuary 28, 2000
Docket02A03-9812-CV-505
StatusPublished
Cited by4 cases

This text of 722 N.E.2d 898 (F.E. Gates Co. v. Hydro-Technologies, Inc.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
F.E. Gates Co. v. Hydro-Technologies, Inc., 722 N.E.2d 898, 2000 Ind. App. LEXIS 66, 2000 WL 92209 (Ind. Ct. App. 2000).

Opinion

OPINION

BROOK, Judge.

Case Summary

F.E. Gates Company, a division of the Blakley Corporation (“Gates”), appeals from a jury verdict in favor of Hydro-Technologies, Inc. (“Hydro-Tech”) on Hydro-Tech’s claim for wrongful termination of a subcontract.

We affirm.

Facts and Procedural History

Gates raises three issues for our review, which we consolidate and restate as:

(1) whether the trial court erred when it denied Gates’ motions for judgment on the evidence; and
(2) whether the trial court properly instructed the jury.

Hydro-Tech is a specialty contractor in the field of hydrodemolition, a process by which concrete is removed using high pressure water. Hydrodemolition is accomplished through the use of a robot, a wheeled vehicle hydraulically driven and capable of delivering 13,000 to 14,000 pounds of water pressure per square inch. The robot must be calibrated with fixed pressure and flow rates such that the desired depth of sound concrete can be removed. Once the robot’s calibrations are set, however, all structurally unsound concrete will be removed automatically regardless of depth.

On July 16, 1996, Gates contacted Hydro-Tech concerning renovations at a parking garage located in Fort Wayne, Indiana and owned by NBD Bank, NA (“NBD”). At that time, Gates was in the process of negotiating a contract (“Prime Contract”) with NBD to act as general contractor to the renovation project, which *900 included removing approximately 40,000 square feet of concrete and resurfacing the badly deteriorated garage floor decks. The Prime Contract was signed on August 30,1996.'

On September 10, 1996, Gates and Hydro-Tech executed a subcontract (“Subcontract”) providing for the hydrodemolition of the garage floor decks. The Subcontract between Gates as general contractor and Hydro-Tech as subcontractor consists of three parts: (1) an American Institute of Architects Standard Form of Agreement Between Contractor and Subcontractor (“Agreement”); (2) a Special Agreement Between Contractor and Subcontractor entitled Exhibit A (“Exhibit A”); and (3) a Hydrode-molition Agreement and Operational Plan entitled Exhibit B (“Exhibit B”). The preamble to Exhibit B sets forth the following:

WHEREAS, Contractor requires surface removal utilizing hydro equipment. WHEREAS, the standard depth of removal required under this Agreement is not to exceed 3 inches.

Exhibit B further provides that the basic unit price for removal of up to three inches of concrete is $4.75 per square foot, and identifies an additional unit price of $1.58 to be paid “as applicable” for each inch or fraction of an inch of removal that exceeds three inches.

In addition, Article 1.1 of the Agreement reads as follows:

The Subcontract Documents consist of (1) this Agreement; (2) the Prime Contract, consisting of the Agreement between the Owner and Contractor and the other Contract Documents enumerated therein, including conditions of the Contract (General, Supplementary and other Conditions), Drawings, Specifications, Addenda issued prior to execution of the Agreement between the Owner and Contractor and Modifications issued subsequent to the execution of the Agreement between the Owner and Contractor, whether before or after the execution of this Agreement, and other Contract Documents, if any, listed in the Owner-Contractor Agreement; (3) other documents listed in Article 16 of this Agreement; and (4) Modifications to this Subcontract issued after execution of this Agreement. These form the Subcontract, and are as fully a part of the Subcontract as if attached in this Agreement or repeated herein. The Subcontract represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations or agreements, either written or oral. An enumeration of the Subcontract Documents, other than Modifications issued subsequent to the execution of this Agreement, appears in Article 16.

(Emphasis added). The Prime Contract, in turn, incorporates documents containing the technical specifications by which renovations are to be performed, including Document 02630 (“Hydrodemolition Surface Preparation”), which provides:

1.6 CALIBRATION AND TESTING OF HYDRODEMOLITION EQUIPMENT
A. Trial area will be designated by Engineer to demonstrate that equipment, personnel and methods of operation are capable of producing results satisfactory to Engineer. Trial area shall consist of 2 sections, approximately 200 sq. ft. each, one section deteriorated concrete and one section sound concrete.
B. In sound concrete area, adjust equipment to remove 2 in. to 3 in. of concrete. Two passes may be required.
C. After completion of the above test section, equipment shall be located over deteriorated concrete and using same parameters for sound concrete removal, used to remove all deteriorated concrete. If sufficient result is obtained, parame *901 ters shall be used for production removal.

1.7 OPERATION OF HYDRODE-MOLITION EQUIPMENT

A. Once operating parameters of hy-drodemolition equipment are defined and calibrated, they shall not be changed as machine progresses across parking deck, in order to prevent unnecessary removal of sound concrete below required minimum removal depth. Contractor shall exercise care to avoid removal of sound concrete below required depth....

1.8 CONCRETE REMOVAL

A. All concrete within marked boundaries shall be removed to minimum depth shown on Drawings using hydrodemolition techniques. Concrete shall be removed to depth of % in. below lowest top reinforcement. Removals shall be performed in a manner that avoids excessive concrete removals between reinforcement. ...
C. If floor delaminations exist beyond minimum removal depth, removals shall continue until all unsound and delaminated concrete has been removed from cavity.

Hydro-Tech commenced its first shift of operations the evening the Subcontract was executed. At no time did Hydro-Tech remove more than three inches of sound concrete; all removal depths greater than three inches occurred within corroded and deteriorated areas. Gates found the depths of removal unacceptable, however, and insisted that only three inches of concrete, whether sound or unsound, be removed. It advised Hydro-Tech that unless Hydro-Tech could obtain removals “not to exceed 8 inches,” the Subcontract would be terminated. Hydro-Tech responded that it was impossible for the hydrodemolition equipment to remove only three inches of deteriorated concrete and that to continually recalibrate the robot would be in violation of both the Subcontract and standard trade practices. As a result of this dispute, Hydro-Tech was prohibited from carrying out further demolition of the garage floor decks and removed its equipment from the job site on September 17,1996.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
722 N.E.2d 898, 2000 Ind. App. LEXIS 66, 2000 WL 92209, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fe-gates-co-v-hydro-technologies-inc-indctapp-2000.