Willie's Const. Co., Inc. v. Baker

596 N.E.2d 958, 1992 Ind. App. LEXIS 1186, 1992 WL 177358
CourtIndiana Court of Appeals
DecidedJuly 29, 1992
Docket71A05-9111-CV-364
StatusPublished
Cited by25 cases

This text of 596 N.E.2d 958 (Willie's Const. Co., Inc. v. Baker) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Willie's Const. Co., Inc. v. Baker, 596 N.E.2d 958, 1992 Ind. App. LEXIS 1186, 1992 WL 177358 (Ind. Ct. App. 1992).

Opinion

BARTEAU, Judge.

Willie's Construction - Company, Inc. ("Willie's") appeals the award of damages to Martin and Vickie Baker for Willie's breach of contract in constructing the Baker's house. The Bakers cross appeal the trial court's award of attorney's fees and interest to Willie's. We affirm the award of damages to the Bakers and reverse the award of attorney's fees and interest to Willie's.

FACTS

In April, 1989, Willie's contracted to construct a new home for the Bakers on their lot in South Bend, Indiana. The contract specifically required that the basement walls be one hundred inches tall-twelve inches higher than the standard height of eighty-eight inches. The Bakers agreed to pay an additional $414.00 for this modification. The total purchase price of the house, including agreed upon modifications, was $54,401.95 to be paid in four installments.

Construction started on August 22, 1989, and the house was expected to be completed within 120 days. During construction, Willie's mistakenly poured eighty-eight inch basement walls instead of the one hundred inch walls as required by the contract. In late October, Mr. Baker discovered the mistake. When he brought the problem to Willie's attention, Willie's admitted that they "goofed up." (R. 269).

Willie's agreed to allow the Bakers to withhold a portion of the second install ment that was due until the problem could be resolved and the house completed. However, Willie's was hesitant to continue work because they feared the Bakers would refuse to pay for the house. Willie's slowed down construction and the house was not completed until April, 1990, eight months after it was started. The Bakers paid only $41,500.00, but were allowed to move in the house after agreeing to keep $10,000.00 in an escrow account until the dispute could be settled.

The Baker's expert, Tim Lykowski, estimated that the cost of increasing the height of the basement walls in the completed home by one foot would be $24,-000.00. This would involve lifting the house off its foundation and then adding to the top of the basement walls. There was also evidence that had Willie's corrected the mistake when it was first discovered the cost to repair would have been substantially less. Willie's experts, Dennis Dill-man and Robert Hawley, each testified that increasing the height of the walls would have no effect on the fair market value of the home.

The trial court found Willie's had breached the contract and awarded the Bakers a judgment for repairs and other damages in the amount of $25,258.32. The court further found that Willie's was entitled to the $12,587.95 balance due under the contract, attorney's fees of $8,147.00 and prejudgment interest in the amount of $5,276.59. Thus, the Bakers' net award was $4,241.78.

Willie's raises one issue on review:

Whether the trial court erred in basing its award of damages for breach of contract on the cost of remedying the breach rather than using the diminution in fair market value caused by the breach.

On cross appeal the Bakers also raise one issue:

Whether the trial court erred in awarding Willie's attorney's fees and prejudgment interest on its claim.

MEASURE OF DAMAGES

There was no dispute that the cost to restore the property was $24,000. The only issue Willie's raises is whether cost to repair is the correct measure of damages.

This court may not reverse a damage award unless it is based on insufficient evidence or is contrary to law. Salem Community School Corp. v. Richman (1980), Ind.App., 406 N.E.2d 269, 275. In *961 determining whether there is sufficient evidence, we may not weigh the evidence nor judge the credibility of the witnesses. If the award of damages is supported by the record, the determination of damages is within the sound discretion of the trial court. Indiana Univ. v. Indiana Bonding & Sur. (1981), Ind.App., 416 N.E.2d 1275, 1288.

Neither party requested special findings of fact, and none were made. In the absence of such, the ruling of the trial court is presumed to be based on findings supported by the evidence and if the judgment is sustainable on any legal theory, it must be affirmed. Complete Elec. Co. v. Liberty Nat'l. Bank (1988), Ind.App., 530 N.E.2d 1216, 1218.

"Ordinarily, in a breach of contract case the injured party's damages are measured by the loss in value to kim of the other party's failure to perform." Restatement (Second) of Contracts § 347(a) (emphasis added).

The fair market value of a home does not necessarily reflect the value to the homeowner. As many homeowners discover, it is not unusual to find that the cost of additions or improvements made in order to conform a home to the owner's personal tastes, often do not result in a corresponding increase in the home's market value. The provision in the contract requiring one hundred inch basement walls was an unusual one for which there was an extra $414.00 charge. Walls taller than eighty-eight inches are extremely rare according to Willie's experts. This was a feature that the Bakers wanted from the beginning and Willie's specifically agreed to provide it. -It is difficult to put a valuation on the difference in height because the Bakers wanted this modification as a matter of personal taste, not because it would increase the value of their home.

In breach of construction contract cases, the proper measure of damages is either 1) the difference between the value of the building as constructed and what its value would have been had it been constructed in accordance with the contract, or 2) the reasonable cost of curing the defects to make the building conform to the contract. - Clark's Pork Farms v. Sand Livestock Sys. (1990), Ind.App., 563 N.E.2d 1292, 1297.

The factor that determines which of the alternative measures of damages applies is whether the defects can be remedied without taking down and reconstructing a substantial portion of the building, or whether the defects could be repaired at a reasonable cost, or, as it is often stated, whether construction and completion in accordance with the contract would involve unreasonable economic waste.

Id. (quoting Sanborn Elec. v. Bloomington Athletic Club (1982), Ind.App., 433 N.E.2d 81, 89).

Willie's argues that if the Bakers are allowed to recover repair cost when it exceeds the difference in fair market value, then the Bakers will be placed in a position better than they would have been in had no breach occurred. Willie's argues that the Bakers could choose not to repair the home and sell it, profiting to the extent that the repair cost exceeds market value. The Restatement of Contracts specifically discusses this matter:

[If the performance [of a construction contract] is defective ... it may not be possible to prove the loss in value to the injured party with reasonable certainty.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thomas Ridgway v. Robert Stratton
Michigan Court of Appeals, 2024
Planning Partners International, LLC v. Qed, Inc.
310 P.3d 126 (Colorado Court of Appeals, 2011)
Ream v. YANKEE PARK HOMEOWNER'S ASS'N, INC.
915 N.E.2d 536 (Indiana Court of Appeals, 2009)
St. Louis, LLC v. FINAL TOUCH
899 A.2d 1018 (New Jersey Superior Court App Division, 2006)
Natare Corp. v. D.S.I., Duraplastec Systems, Inc.
833 N.E.2d 76 (Indiana Court of Appeals, 2005)
The Osler Institute, Inc. v. Lois Forde
386 F.3d 816 (Seventh Circuit, 2004)
Rogers Group, Inc. v. Diamond Builders, LLC
816 N.E.2d 415 (Indiana Court of Appeals, 2004)
Brandeis MacH. & Supply Co., LLC v. Capitol Crane Rental, Inc.
765 N.E.2d 173 (Indiana Court of Appeals, 2002)
Harrison v. Thomas
761 N.E.2d 816 (Indiana Supreme Court, 2002)
Greg Allen Const. Co., Inc. v. Estelle
762 N.E.2d 760 (Indiana Court of Appeals, 2002)
Harrison v. Thomas
744 N.E.2d 977 (Indiana Court of Appeals, 2001)
State ex rel. Allstate Insurance v. Gaughan
508 S.E.2d 75 (West Virginia Supreme Court, 1998)
STATE EX REL. ALLSTATE INS. v. Gaughan
508 S.E.2d 75 (West Virginia Supreme Court, 1998)
Salcedo v. Toepp
696 N.E.2d 426 (Indiana Court of Appeals, 1998)
Barrington Management Co. v. Paul E. Draper Family Ltd.
695 N.E.2d 135 (Indiana Court of Appeals, 1998)
Shumate v. Lycan
675 N.E.2d 749 (Indiana Court of Appeals, 1997)
Haas Carriage, Inc. v. Berna
651 N.E.2d 284 (Indiana Court of Appeals, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
596 N.E.2d 958, 1992 Ind. App. LEXIS 1186, 1992 WL 177358, Counsel Stack Legal Research, https://law.counselstack.com/opinion/willies-const-co-inc-v-baker-indctapp-1992.