Brandeis MacH. & Supply Co., LLC v. Capitol Crane Rental, Inc.

765 N.E.2d 173, 47 U.C.C. Rep. Serv. 2d (West) 200, 2002 Ind. App. LEXIS 456, 2002 WL 437370
CourtIndiana Court of Appeals
DecidedMarch 21, 2002
Docket49A05-0107-CV-314
StatusPublished
Cited by5 cases

This text of 765 N.E.2d 173 (Brandeis MacH. & Supply Co., LLC v. Capitol Crane Rental, Inc.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brandeis MacH. & Supply Co., LLC v. Capitol Crane Rental, Inc., 765 N.E.2d 173, 47 U.C.C. Rep. Serv. 2d (West) 200, 2002 Ind. App. LEXIS 456, 2002 WL 437370 (Ind. Ct. App. 2002).

Opinion

OPINION

VAIDIK, Judge.

Case Summary

Brandeis Machinery & Supply Company (Brandeis) appeals the damage award granted by the trial court. In particular, Brandeis maintains that the trial court erred by failing to award the contract price and by failing to include service charges for late payment according to the terms of its contract with Capitol Crane Rental, Inc. (Capitol). Because we find that the evidence supports the trial court's damage calculation, we affirm.

Facts and Procedural History

Brandeis and Capitol entered into a Lease Agreement on June 16, 1998. Under the lease, Capitol rented a 85-ton Grove Model RT635C Rough Terrain Crane (Crane) from Brandeis for six months. The lease included an option for Capitol to buy the Crane. When the first six months of the lease expired, Capitol continued to rent the Crane for another six-month period on a month-to-month basis.

Brandeis' lead salesman, Greg Henry, and Capitol's owner, Steve Dotlich, executed a Cash Sales Contract (Contract) on June 16, 1999. Under the Contract, Capitol agreed to buy the Crane "as is-where is" for $291,778.46. The Contract included the following provision:

TERMS OF PAYMENT: Net 10 days from invoice date .... If not paid on due date, 2% per month service charge will be applied.

Appellant's App. p. 39. Brandeis CEO signed the Contract to acknowledge approval of the deal on June 22, 1999. Brandeis sent Capitol the invoice for the Crane on June 29, 1999.

In late June of 1999, Maxim Crane Works (Maxim), a national crane rental company, approached Dotlich about buying Capitol. After Maxim asked to buy Capitol, Dotlich returned the Crane to the Brandeis lot. About one week after Dotlich had returned the Crane, Henry, who had dealt with Dotlich regarding the lease and the Contract, called Dotlich to inquire about the returned Crane. During their telephone conversation, Dotlich informed Henry that he "did not want to buy [the Crane] any more." Appellant's App. p. 121. Dotlich also told Henry that he was selling his business.

When Brandeis discovered that Dotlich had returned the Crane, the Brandeis managers told Henry and the sales staff not to sell the Crane because it belonged to Capitol and not to Brandeis. Additionally, Brandeis marked the Crane with chalk to indicate that the Crane was the property of Capitol and had already been sold to Capitol.

Before returning the Crane, Capitol repaired damage to the Crane. Dotlich testified that the Crane's boom had been damaged around the time that he signed the Contract, but he could not recall if the damage occurred before or after he signed the Contract. Capitol bought parts from Brandeis and repaired the Crane.

After Capitol returned the Crane to Brandeis, Brandeis expended $9,794.86 to inspect the repairs made to the boom. Walter Ross, Brandeis' Indianapolis Branch Manager, testified that the Crane was inspected because he understood that *176 Brandeis had reached "some kind of resolution" with Capitol that Brandeis would prepare to resell the Crane. Tr. p. 22. He testified that the inspection of the Crane was performed for the express purpose of selling the Crane to someone else.

At trial, Henry testified regarding Brandeis' customary business practices. Henry stated that he was aware of more than one instance when a customer had signed a contract with Brandeis, but decided to cancel the contract before any money had changed hands. In these cases, Brandeis cancelled the contracts and did not try to enforce the sales. Henry explained that the reason for this practice was to avoid upsetting and losing customers. Additionally, Henry testified that when dealing with Capitol and generally with all of Brandeis' customers, a transaction was only considered final when payment was made.

Following the trial, each side submitted post-trial briefs. In its brief, Brandeis contended that the appropriate damage award would include the purchase price of the Crane, which was $291,773.46 plus interest at the rate of 2% per month for late payment as provided for in the Contract. As of May 31, 2001, $159,302.38 had accumulated in late payment interest. Furthermore, Brandeis calculated the damage award to include the inspection fee of the Crane due to the damage sustained and repairs performed while in Capitol's care as an incidental cost. The costs for the inspection of the repairs were $9,794.86. Based on these numbers, Brandeis prayed for a damage award totalling $460,870.70.

In its brief, Capitol maintained that no damages should have been awarded. In the alternative, Capitol submitted that damages should be caleulated by subtracting the fair market value of the Crane from the Contract price of $291,778.46. Regarding the fair market value of the Crane, Henry testified that based on rates of depreciation the Crane's fair market value in June/July 1999 was between $270,000 and $275,000. Due to the difference, Capitol suggested using the median value of $272,500. The difference between the median fair market value of $272,500 and the Contract price of $291,778.46 is a damage award of $19,273.46.

The trial court entered judgment in favor of Brandeis on June 21, 2001. The trial court ordered that "Brandeis Machinery & Supply Co., LLC, recover of and from the defendant, Capitol Crane Rentals, Inc., the sum of $29,067.00 with interest thereon from the date of judgment, as provided by law, plus costs of this action." Appellant's App. p. 5. This appeal ensued.

Discussion and Decision

Brandeis asserts that the trial court erred in calculating the damage award. First, Brandeis contends that the trial court erred by failing to award the full Contract price when calculating the damages. Second, Brandeis argues that the trial court erred by failing to include service charges for the late payment as dictated by the terms of the Contract in the damage calculation. We address each contention in turn.

In this case, neither party requested special findings of fact and the trial court did not enter any. When the trial court enters a general judgment without special findings and conclusions, we may not reweigh evidence or consider witness credibility but must affirm if sustainable on any legal theory. Perdue Farms, Inc. v. Pryor, 688 N.E.2d 289, 240 (Ind.1997) Willie's Constr. Co., Inc. v. Baker, 596 N.E.2d 958, 961 (Ind.Ct.App.1992), trans. denied. In reviewing a general Judgment, we must presume that the trial court correctly followed the law. Perdue, 683 N.E.2d at 240. Additionally, due re *177 gard must be given the trial court's opportunity to judge the credibility of witnesses, and the judgment should not be set aside unless clearly erroneous. Id. at 241. Moreover, generally the computation of damages is a matter within the sound discretion of the trial court. Marathon Oil Co. v. Collins, 744 N.E.2d 474, 481 (Ind.Ct.App.2001). A damage award will not be reversed upon appeal unless it is based on insufficient evidence or is contrary to law. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Conrad v. Atkins
868 N.E.2d 878 (Indiana Court of Appeals, 2007)
Bruno v. Wells Fargo Bank, N.A.
850 N.E.2d 940 (Indiana Court of Appeals, 2006)
General Motors Corp. v. Sheets
818 N.E.2d 49 (Indiana Court of Appeals, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
765 N.E.2d 173, 47 U.C.C. Rep. Serv. 2d (West) 200, 2002 Ind. App. LEXIS 456, 2002 WL 437370, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brandeis-mach-supply-co-llc-v-capitol-crane-rental-inc-indctapp-2002.