Fairway Builders, Inc. v. Malouf Towers Rental Co.

603 P.2d 513, 124 Ariz. 242, 1979 Ariz. App. LEXIS 602
CourtCourt of Appeals of Arizona
DecidedJuly 3, 1979
Docket1 CA-CIV 3318
StatusPublished
Cited by63 cases

This text of 603 P.2d 513 (Fairway Builders, Inc. v. Malouf Towers Rental Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fairway Builders, Inc. v. Malouf Towers Rental Co., 603 P.2d 513, 124 Ariz. 242, 1979 Ariz. App. LEXIS 602 (Ark. Ct. App. 1979).

Opinion

OPINION

EUBANK, Judge.

The issues raised by the appeal and cross appeal in this complex case all involve an office building and garage constructed by appellant/cross appellee, Fairway Builders, Inc. (Fairway) for appellee/cross appellant, Malouf Towers Rental Co., Inc. (Malouf). The case was tried to the court without a jury, and no findings of fact or conclusions of law were requested or given. In this situation, we must affirm if possible “on any theory within the issues and supported by the evidence.” Gabitzch v. Cole, 95 Ariz. 15, 18, 386 P.2d 23, 25 (1963); Harmon v. Hanson’s Pump & Machine Works, Inc., 4 Ariz.App. 1must' assume that the court found every fact necessary to support its judgment. Estate of Brashear, 54 Ariz. 430, 96 P.2d 747 (1939). All inferences supported by the evidence must be taken in favor of affirming the judgment. Odom v. First National Bank of Arizona, 85 Ariz. 238, 336 P.2d 141 (1959); Logan v. O. S. Stapley Company, 14 Ariz.App. 65, 480 P.2d 680 (1971).

In light of these standards, the essential facts of this case are as follows. Malouf, a corporation formed by three members of the Malouf family, obtained a 99-year ground lease on a parcel of property located on Central Avenue in Phoenix. On November 4, 1964, Malouf contracted with Fairway for Fairway to construct a high-rise office building on the site for $1,279,000.00. The basic contract was on a four-page form entitled “The Standard Form of Agreement Between Owner and Contractor,” and was supplied by the American Institute of Architects. On page four of this Agreement, other documents are incorporated by reference into the contract. These other documents include the building plans and specifications, an “Agreement Dated November 4, 1964,” and the “General Conditions.” The General Conditions is another document supplied by the American Institute of Architects, the full title of which is “The General Conditions Of The Contract For The Construction Of Buildings.”

The parties again contracted on April 20, 1965 for Fairway to build the garage which was to accompany the office building. The contract sum was $181,200 and the parties again utilized “The Standard Form Of Agreement Between Owner and Contractor.” Like the office building contract, the garage contract incorporated the plans and specifications, and the General Conditions.

The two contracts were executed by W. B. Malouf, President of Malouf, and by Alfred Tibshraeny, President of Fairway. Mr. Tibshraeny and the Maloufs are related. Together, the two contracts constituted the Malouf Towers Project. While Fairway did some of the actual construction work itself, much of the work was performed by numerous subcontractors.

In 1968, Fairway brought this action against Malouf seeking recoveries for various alleged breaches of contract and on the basis of other theories. In its amended complaint, Fairway prayed for sums allegedly owed to it by Malouf under the office building and garage contracts. Further, it sought payment for extra work it had allegedly performed at Malouf’s oral request and for fees paid out of money owing to it, and requested foreclosure of its mechanics’ lien. Malouf counterclaimed and alleged that some of the construction work was negligently done and was defectively and incompletely performed in breach of contract. The case was exhaustively tried to the court over a period of weeks. As already noted, no findings of facts or conclusions of law were requested or given. The court’s judgment of August 5, 1975 reflects its acceptance of most of the allegations in the complaint and counterclaim. *247 The court awarded Fairway substantial amounts as due under the contracts (offset by allowances for work not done), and large sums for extra work. However, the court also awarded Malouf a sizeable amount as compensation for defective and incomplete work. Many of the sums awarded to Fairway were, by the terms of the judgment, to bear prejudgment interest from various dates. In paragraph 11 of . the judgment, the court offset the awards in favor of the parties, and the net result was a judgment in favor of Fairway of $90,188.76, “which money judgment shall bear interest at the rate of six (6%) percent per annum from and after dates due until paid as set forth herein.” This provision has caused considerable confusion in view of the court’s original decree that various amounts awarded to Fairway were to bear prejudgment interest from various dates. How is the prejudgment interest to be calculated in light of the offset? The court also awarded Fairway a mechanics’ lien on the Malouf Towers Project property in the net amount after offsets, $90,188.76.

Both parties challenge the judgment on numerous bases, most of which involve the sufficiency of the evidence. Further facts will be stated as necessary in the discussions of the various issues.

I. THE VAULT DOOR

As already noted, the trial court awarded a large sum to Fairway as due under the office building contract. This sum was immediately partially reduced by offsets for work not performed, in breach of contract. One of these offsets was $1,000.00 for Fairway’s failure to install a vault door specified in the plans. Fairway raises numerous challenges to this offset, but we consider only the alleged failure of Malouf to prove its damages due to the lack of the door since this issue is dispositive.

At trial, Malouf attempted to prove its damages and the value of the door through the testimony of James F. Lindlan, an architect connected with the Malouf Towers Project. He stated that the vault door had an approximate value of $1,000.00 to $1,200.00. However, the court sustained an objection to this testimony, although it was not stricken from the record. Malouf attempts to avoid the fact that the objection was sustained by contending that it is the rule in Arizona that testimony which enters the record but is not stricken, even though an objection to its admissibility is sustained, nevertheless remains part of the record. Malouf cites Greene v. Hereford, 12 Ariz. 85, 95 P. 105 (1908) in support of its contention. The entire relevant portion of Greene consists of the following sentence:

The fifteenth assignment of error is idle, for the reason that, although the court sustained the objection to the question, the witness nevertheless answered the question after the objection was sustained, and the answer was neither withdrawn nor stricken out on motion, but remains in the record.

Id. at 97, 95 P. at 108. While this sentence does seem to support Malouf’s suggested rule, we think Greene is inapplicable since that case involved a jury trial. Of course, it is important in a jury trial to strike testimony to which an objection has been sustained, or to give a cautionary instruction. However, there is no general requirement in trials to the court to strike evidence to which an objection has been sustained. Once the objection is sustained in a non-jury trial, the evidence is excluded and must not be considered by the court. Consequently, Mr. Lindlan’s testimony as to the value of the vault door could not be considered and cannot provide a basis for the award of damages for the door.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ventures 7000 v. Acc
Court of Appeals of Arizona, 2022
McKnight v. McKnight
D. Arizona, 2021
Synergy v. Singh
Court of Appeals of Arizona, 2021
Mesa v. Davis
Court of Appeals of Arizona, 2021
Dishon v. Gorham
D. Arizona, 2020
Chula Vista Homeowners Ass'n v. Irwin
426 P.3d 1228 (Court of Appeals of Arizona, 2018)
Commerce v. Zinke
Court of Appeals of Arizona, 2017
Suenos v. Diane Goldman
633 F. App'x 874 (Ninth Circuit, 2015)
Eick v. Delta
Court of Appeals of Arizona, 2015
Perkins v. Hon. brain/barnett
Court of Appeals of Arizona, 2015
Southern Building Services, Inc. v. City of Fort Smith
2014 Ark. App. 437 (Court of Appeals of Arkansas, 2014)
Sullivan v. Homes
Court of Appeals of Arizona, 2014
Aprea II v. Hafter
Court of Appeals of Arizona, 2014
Southwest v. Burns
Court of Appeals of Arizona, 2014
Next Gen Capital, LLC v. Consumer Lending Associates LLC
316 P.3d 598 (Court of Appeals of Arizona, 2013)
ASARCO LLC v. Americas Mining Corp.
404 B.R. 150 (S.D. Texas, 2009)
Radman v. Flanders Corp.
2007 UT App 351 (Court of Appeals of Utah, 2007)
Chang v. Brethren Mutual Insurance
897 A.2d 854 (Court of Special Appeals of Maryland, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
603 P.2d 513, 124 Ariz. 242, 1979 Ariz. App. LEXIS 602, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fairway-builders-inc-v-malouf-towers-rental-co-arizctapp-1979.