Southern Building Services, Inc. v. City of Fort Smith

2014 Ark. App. 437, 440 S.W.3d 346, 2014 Ark. App. LEXIS 586
CourtCourt of Appeals of Arkansas
DecidedSeptember 3, 2014
DocketCV-13-1132
StatusPublished
Cited by1 cases

This text of 2014 Ark. App. 437 (Southern Building Services, Inc. v. City of Fort Smith) is published on Counsel Stack Legal Research, covering Court of Appeals of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern Building Services, Inc. v. City of Fort Smith, 2014 Ark. App. 437, 440 S.W.3d 346, 2014 Ark. App. LEXIS 586 (Ark. Ct. App. 2014).

Opinion

BILL H. WALMSLEY, Judge.

| ¶ This dispute between appellant Southern Building Services, Inc., and the City of Fort Smith (the “City”) returns to our court. See S. Bldg. Servs., Inc. v. City of Fort Smith, 2018 Ark. App. 306, 427 S.W.3d 763 (Southern I). The issues in this appeal are (1) determining the “prevailing party” for purposes of an award of attorney’s fees and (2) entitlement to prejudgment interest. Southern argues that the circuit court erred in finding that the City was the prevailing party and awarding attorney’s fees to the City. Southern also asserts that it is entitled to prejudgment interest on the funds owed to it by the City. We agree that Southern is the prevailing party and that it is entitled to prejudgment interest. Accordingly, we reverse and remand for further proceedings consistent with this opinion.

The facts of this case are set out in detail in Southern I. Briefly, this case involves a dispute between Southern and the City over Southern’s failure to complete a construction ^project for the City. After the City terminated the contract for not timely completing the work, Southern filed suit for the remaining $183,701.22 that it claimed it was owed under the contract and for its attorney’s fees. The City counterclaimed for liquidated damages and prejudgment interest it claimed under the contract.

After a bench trial, the circuit court awarded the City $134,250 in liquidated damages for Southern’s failure to timely achieve substantial completion of the contract and 6% prejudgment interest. It also awarded the City $30,999, representing the City’s costs to complete the project, and $51,262 in attorney’s fees. The court denied the City’s claim for liquidated damages based on Southern’s failure to achieve final completion of the contract. There was no mention of Southern’s claim for the $183,701. Southern appealed, and the City cross-appealed.

We affirmed the liquidated-damages award to the City because Southern did not achieve substantial completion; however, we found that the circuit court erred in awarding prejudgment interest from June 18, 2008. Southern I, at 8, 427 S.W.3d at 767-68. We also remanded to the circuit court to apply a set-off of $183,701, representing the sum due Southern against the $134,250 awarded to the City because the City admitted that it had possession of the funds that were due Southern since 2008. Id. We affirmed the cost-of-completion-damages award to the City. Southern /, at 9, 427 S.W.3d at 768. However, we vacated the award of attorney’s fees, stating that the circuit court could redetermine who the prevailing party was on remand. Southern I, at 10, 427 S.W.3d at 768. On the City’s cross-appeal, we held that the circuit court did not err in denying the City’s claim for | ^liquidated damages for Southern’s failure to achieve final completion of the contract work because the City failed to mitigate its damages. Southern I, at 10-11, 427 S.W.3d at 769. The City filed a petition for review in the supreme court, which was denied on September 12, 2013.

On remand, Southern filed a motion seeking attorney’s fees and prejudgment interest. In its supporting brief, Southern asserted that it was the prevailing party on the basis that, after applying the set-off, it was still owed money. Southern cited Marcum v. Wengert, 344 Ark. 153, 40 S.W.3d 230 (2001), as its primary authority. Southern also sought prejudgment interest accrued on the $183,701.22 since 2008.

The City renewed its motion for attorney’s fees and responded to Southern’s motion for fees and prejudgment interest. In its motion and supporting brief, the City acknowledged that, after applying the set-off, Southern was entitled to $18,451.26. The City also sought its original attorney’s fees of $51,262. The City argued that it had successfully reduced Southern’s claim by 90%, from $188,701.22 to $18,451.26. Ultimately, the City claimed that it was the prevailing party and sought a judgment in the amount of $82,810.74, representing the City’s recovery of liquidated damages, completion damages, and attorney’s fees less Southern’s set-off. The City’s primary authority for its position was CJ Building Corp. v. TRAC-10, 368 Ark. 654, 249 S.W.3d 793 (2007).

The circuit court found that, after applying the set-off, Southern was due $18,451.26. The court then turned to the issue of identifying the prevailing party. The court found CJ Building directly on point and that, because the City had successfully reduced Southern’s claim |4by 90%, it was the prevailing party. The City was awarded $51,262 in attorney’s fees. This appeal followed.

On appeal, Southern argues two points: (1) the circuit court erred in finding that the City was the prevailing party and in awarding it attorney’s fees; and (2) the court erred in failing to award prejudgment interest on the amounts owed by the City to Southern under the contract.

Arkansas Code Annotated section 16-22-308 (Repl.1999), which allows a prevailing party to recover reasonable attorney’s fees in a breach-of-contract action, provides in pertinent part as follows:

In any civil action to recover [for] ... breach of contract, unless otherwise provided by law or the contract which is the subject matter of the action, the prevailing party may be allowed a reasonable attorney’s fee to be assessed by the court and collected as costs.

Our supreme court has said that a circuit court is not required to award attorney’s fees and, because of the judge’s intimate acquaintance with the trial proceedings and the quality of the service rendered by the prevailing party’s counsel, the circuit judge has a superior perspective to determine whether to award fees. Harrill & Sutter, P.L.L.C. v. Kosin, 2012 Ark. 385, 424 S.W.3d 272. The decision to award attorney’s fees and the amount to award is discretionary and will be reversed only if the appellant can demonstrate that the circuit court abused its considerable discretion. Id.

The first issue for us to determine is whether the circuit' court abused its discretion in awarding attorney’s fees to the City. As part of this determination, we must consider whether the circuit court erred in deciding that the City was the “prevailing party” in- this lawsuit. In |fiboth CJ Building, supra, and Marcum, supra, the supreme court held that to be the prevailing párty under section 16-22-308, the litigant must be granted some relief on the merits of its claim. In CJ Building, the general contractor successfully argued that it was contractually entitled to deduct its expenses in completing the contract from the retainage, even though the end result was that the subcontractor received a judgment for the difference. In Marcum, both parties were somewhat successful because they each were awarded a money judgment on part of their claims, albeit not the full amount sought. We recently held that a circuit court erred' in limiting its analysis to the outcome of the jury trial on damages instead of looking at the case as a whole. Brackelsberg v. Heflin, 2011 Ark. App. 678, 386 S.W.3d 636.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Williams v. Shackelford
2017 Ark. App. 149 (Court of Appeals of Arkansas, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
2014 Ark. App. 437, 440 S.W.3d 346, 2014 Ark. App. LEXIS 586, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-building-services-inc-v-city-of-fort-smith-arkctapp-2014.