CJ Building Corp. v. TRAC-10

249 S.W.3d 793, 368 Ark. 654, 2007 Ark. LEXIS 101
CourtSupreme Court of Arkansas
DecidedFebruary 8, 2007
Docket06-483
StatusPublished
Cited by12 cases

This text of 249 S.W.3d 793 (CJ Building Corp. v. TRAC-10) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CJ Building Corp. v. TRAC-10, 249 S.W.3d 793, 368 Ark. 654, 2007 Ark. LEXIS 101 (Ark. 2007).

Opinion

Jim Gunter, Justice.

This appeal arises from an order of the Hot Spring County Circuit Court entering judgment in favor of appellee, TRAC-10, against appellant, CJ Building Corporation (CJ), in the amount of $9,676.25 in attorneys’ fees and costs. On appeal, CJ argues that the circuit court erred in finding that TRAC-10 was the prevailing party under Ark. Code Ann. § 16-22-308 (Repl. 1999), and in awarding attorneys’ fees and costs to TRAC-10. We affirm.

CJ entered into a $1.4 million subcontract, dated October 29, 2002, with TRAC-10 to design, engineer, and construct four metal buildings for the Hot Spring County Power Plant (“project”). The scope of CJ’s work included design and installation of the heating, ventilation, and air conditioning (“HVAC”) systems for the buildings. After CJ completed its work and demobilized from the job site in September 2003, problems developed. TRAC-10 learned that CJ had not paid various suppliers or subcontractors, and the HVAC system in one building did not work properly. On February 3, 2004, CJ demanded a $56,126.77 retainage being held by TRAC-10, but TRAC-10 refused to pay because of the alleged deficiencies in CJ’s work.

On June 18, 2004, CJ filed a complaint against TRAC-10 for foreclosure of a materialman’s lien, asserting entitlement to the money owed on the subcontract. In its complaint, CJ named TRAC-10, Hot Spring Power Company, LLC, Hot Spring Power Company, LP, and Tractebel Project Development, Inc. as separate defendants. Specifically, CJ alleged that the Hot Spring Power Company was indebted to CJ in the sum of $63,287 for money owed for labor and materials. CJ commenced the action, claiming a first lien on the project. On July 8, 2004, TRAC-10 filed an answer, praying that CJ’s complaint be dismissed and requesting costs and expenses, including attorneys’ fees. Pursuant to Ark. Code Ann. § 18-44-118 (Repl. 2003), TRAC-10 filed a mechanic’s and materialman’s lien bond with the Hot Spring County Circuit Clerk on July 19, 2004, for double the amount of the lien claimed by CJ. In an agreed order entered on July 30, 2004, the circuit court found that, due to the filing of TRAC-10’s bond, CJ’s materialman’s lien claims were discharged. The circuit court further ruled that separate defendants Hot Spring Power Company, LLC, Hot Spring Power Company, LP, and Tractebel Project Development, Inc. were dismissed with prejudice because of the filing of TRAC-10’s bond.

A bench trial was held on November 21, 2005. At the close of the evidence, the circuit court made the following ruling from the bench:

Well, obviously the dispute begins with the retainage amount of $56,126.77. Both sides have folly explained all the various joint exhibits. The court finds and agrees with the defendant’s position that the items on the board up there, the cleanup punch list, the National HVAC, the S&S Plumbing and the bond were expenses they incurred in getting the contract to par.
Therefore, those are deducted from the retainage leaving a balance of $13,927.21 that is owed to the plaintiff for which judgment is granted, plus interest and the maximum rate from today’s date.
All right, that’s the court’s judgment.

On December 8, 2005, the circuit court entered an order and ruled that TRAC-10 was contractually entitled to withhold $42,199.56 from the payment due to CJ. The circuit court entered judgment in favor of CJ in the amount of $13,927.21 plus interest.

Both parties filed timely motions for attorneys’ fees pursuant to Ark. Code Ann. § 16-22-308 (Repl. 1999), with each claiming to be the prevailing party in the contract action. On December 12, 2005, TRAC-10 submitted a motion for fees and costs on the basis that it was a prevailing party in the litigation. In its motion, TRAC-10 argued that, as a result of the circuit court’s rulings, TRAC-10 was the “prevailing party” under Ark. Code Ann. § 16-22-308 and Ark. R. Civ. P. 54 or the “successful party” in Ark. Code Ann. § 18-44-128 (Repl. 2003). TRAC-10, claimingit was the prevailing and successful party at trial, requested $76.25, pursuant to Ark. R. Civ. P. 54, for recoverable costs, and $19,357.50, pursuant to Ark. Code Ann. § 16-22-308 and Ark. Code Ann. § 18-44-128, for attorneys’ fees. On December 28, 2005, CJ filed a response, claiming that it was the prevailing party and prayed that the circuit court deny TRAC-10’s motion for fees and costs. Also, on December 21, 2005, CJ filed a motion for attorneys’ fees, asserting that, pursuant to the circuit court’s order on December 8, 2004, it was the prevailing party and requested $10,000 in attorneys’ fees.

On February 22, 2006, the circuit court entered an order ruling that TRAC-10 was the prevailing party, denying CJ’s motion for attorneys’ fees, and granting TRAC-10’s motion for fees in part. The circuit court awarded TRAC-10 judgment against CJ for attorneys’ fees and costs in the amount of $9,676.25. On March 8, 2006, CJ filed a timely amended notice of appeal. From the February 22, 2006, order, CJ brings its appeal.

For its sole point on appeal, CJ argues that the circuit court abused its discretion by finding that TRAC-10 was the prevailing party. Specifically, CJ contends that, although it did not receive the $63,287 that it requested in its complaint, it nevertheless received $13,927.21 of the retainage. TRAC-10 responds, arguing that the case in controversy presented a breach of contract for which attorneys’ fees might be claimed pursuant to Ark. Code Ann. § 16-22-308.

We have said that attorneys’ fees are not allowed except where expressly provided for by statute. Harris v. City of Fort Smith, 366 Ark. 277, 234 S.W.3d 875 (2006). An award of attorneys’ fees will not be set aside absent an abuse of discretion by the trial court. Id. While the decision to award attorneys’ fees and the amount awarded are reviewed under an abuse-of-discretion standard, we review factual findings by a circuit court on the existence of the Chrisco factors under a clearly-erroneous standard of review. Id.

Arkansas Code Annotated § 16-22-308, which allows a prevailing party to recover reasonable attorneys’ fees and costs in a breach-of-contract action, provides:

In any civil action to recover on an open account, statement of account, account stated, promissory note, bill, negotiable instrument, or contract relating to the purchase or sale of goods, wares, or merchandise, or for labor or services, or breach of contract, unless otherwise provided by law or the contract which is the subject matter of the action, the prevailing party may be allowed a reasonable attorney’s fee to be assessed by the court and collected as costs.

Id. 1

To be the prevailing party under section 16-22-308, the litigant must be granted some relief on the merits of its claim. BKD, LLP v. Yates, 367 Ark. 391, 240 S.W.3d 588 (2006) (citing Marcum v. Wengert, 344 Ark. 153, 40 S.W.3d 230 (2001)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mountain Pine Timber, Inc. v. Smith
2016 Ark. App. 197 (Court of Appeals of Arkansas, 2016)
Southern Building Services, Inc. v. City of Fort Smith
2014 Ark. App. 437 (Court of Appeals of Arkansas, 2014)
Sluyter v. Toney
2014 Ark. App. 247 (Court of Appeals of Arkansas, 2014)
Union Pacific Railroad Co. v. Gunderson Rail Services
712 F.3d 1214 (Eighth Circuit, 2013)
Harrill & Sutter, P.L.L.C. v. Kosin
2012 Ark. 385 (Supreme Court of Arkansas, 2012)
Payne v. Donaldson
385 S.W.3d 296 (Court of Appeals of Arkansas, 2011)
River Valley Land, Inc. v. Hudson
347 S.W.3d 40 (Court of Appeals of Arkansas, 2009)
Baptist Health v. Smith
536 F.3d 869 (Eighth Circuit, 2008)
Todd Smith v. Robert Casali
Eighth Circuit, 2008
City of Fort Smith v. Carter
270 S.W.3d 822 (Supreme Court of Arkansas, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
249 S.W.3d 793, 368 Ark. 654, 2007 Ark. LEXIS 101, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cj-building-corp-v-trac-10-ark-2007.