Southern Building Services, Inc. v. City of Fort Smith

427 S.W.3d 763, 2013 Ark. App. 306, 2013 WL 1904804, 2013 Ark. App. LEXIS 329
CourtCourt of Appeals of Arkansas
DecidedMay 8, 2013
DocketNo. CA 12-503
StatusPublished
Cited by4 cases

This text of 427 S.W.3d 763 (Southern Building Services, Inc. v. City of Fort Smith) is published on Counsel Stack Legal Research, covering Court of Appeals of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern Building Services, Inc. v. City of Fort Smith, 427 S.W.3d 763, 2013 Ark. App. 306, 2013 WL 1904804, 2013 Ark. App. LEXIS 329 (Ark. Ct. App. 2013).

Opinion

BILL H. WALMSEY, Judge.

| iThis casé involves a construction dispute between appellant Southern Building Services, Inc. (“SBS”), and appellee City of Fort Smith, Arkansas (“City”). Following a three-day bench trial, the circuit court awarded the City liquidated damages of $134,250, plus interest at the rate of 6% per annum from June 18, 2008, for SBS’s failure to timely achieve substantial completion of the project. It also awarded the City $30,999.96 for the cost of completing the project and $51,262 for attorney’s fees. On appeal, SBS argues that the circuit court erred in each of those awards. The City cross-appeals, arguing that the court erred in not awarding the City liquidated damages for SBS’s failure to achieve final completion of the contract within fifteen days after substantial completion. We affirm in part, reverse and 12remand in part, and vacate in part on direct appeal. We affirm on cross-appeal.

On April 17, 2007, SBS entered into a contract with the City to construct six structures at Lake Shepherd Springs Recreational Area (the project): the Pool House, Upper Bath House, Lower Bath House, Marina Office, Day-Use Pavilion, and Day-Use Restroom. The contract required substantial completion of the Day-Use Restroom within 120 calendar days of notice to proceed and of the other five structures within 210 calendar days from notice to proceed. Final completion was required within fifteen days of substantial completion. The contract provided specific, different liquidated damages for failure to meet the substantial-completion deadlines for the Day-Use Restroom ($250 per day) and for the other five structures ($750 per day). A third liquidated-damage amount of $200 per day was provided for failure to meet the final completion deadline. The engineering firm overseeing construction and acting as the City’s agent and representative was Mickle Wagner Coleman, Inc., with Bobby Aldridge as the lead engineer. The architectural firm overseeing the project was Tim A. Risley and Associates.

A notice to proceed was issued on May 11, 2007, and SBS commenced work on May 14, 2007. According to SBS, it encountered many delays beyond its control, such as weather, interference by other contractors, utility issues, layouts and elevations, and faulty design, among others. By March 2008, it had reached substantial completion of the Day-Use Restroom, and substantial completion of the other five structures occurred on May 5, 2008. Under the contract, the engineer acted for the City, and the City was to execute change orders recommended by the engineer. The contract price could be changed only by change border, and the engineer and the City directed that all changes of time and price would be approved in one final reconciliation.

In June 2008, inspection of the completed project was scheduled, and the City advised the bonding company that it would be authorizing final payment. In July 2008, SBS was given what it calls the final change order to indicate that work under the contract was complete. This final change order reflected an approved adjustment to the contract of $15,401, making the total contract price $1,698,401. It also showed that thirty-two additional days had been added to the contract time and that liquidated damages had not been assessed. Liquidated damages were later assessed at $134,250, although they did not appear in the final change order. SBS requested a waiver of the liquidated damages and additional contract time. In December 2008, SBS was informed that it had agreed to the final change order and was contractually bound by the order.

By resolution adopted on March 16, 2010, the City terminated the contract and assessed liquidated damages against SBS in the amount of $134,250 for failure to timely achieve the substantial-completion deadlines for the six buildings. The resolution also assessed liquidated damages in the amount of $156,600 for failure to achieve final completion of the contract work.

On March 11, 2010, SBS sued the City for an additional sum of $183,701.22 allegedly owed, together with reasonable attorney’s fees.1 The complaint asserted causes of action based |4on breach of contract, promissory estoppel, constructive fraud, and equitable estoppel. The City answered and counterclaimed for liquidated damages for delay in achieving both substantial completion and final completion and for the cost of completing'SBS’s work. In its answer and counterclaim, the City contended that work costing the sum of $20,000 to complete the contract remained undone. The City sought liquidated damages totaling $290,850 and, after applying a credit of $183,701.22 for “sums due for work accomplished under the contract,” asserted entitlement to the sum of $107,148.78, together with prejudgment interest and a reasonable attorney’s fee.

After both parties moved for and were denied summary judgment, the case proceeded to a three-day bench trial held in February 2012. The court filed its written judgment on February 22, 2012. In it, the court characterized “the issue [as] a simple one, whether [SBS] should be assessed liquidated damages and if so in what amount.” The court found that, when it came to a time-related change order, the City had told SBS to document the delays and they would be addressed at the end of the contract if they could not be resolved within fifteen days. However, the court also found that SBS failed to do that and “just chose not to make substantiated requests for additional time until November 26, 2008, and at trial.” Although SBS contended that the time frame for completion of the projects excluded weekends and holidays, the court noted that there was testimony that SBS did in fact work on some weekends. SBS’s contention that it was entitled to additional days because of various reasons, including weather, lack of supervision, other contractors, and dumpster and electrical-related problems, was rejected because SBS, by its own admission, failed to document the delays. 15Although the contract required the job being finally completed within fifteen days of substantial completion, the court found that SBS failed to do so. The court found it “amazing” that SBS either could not or would not complete the multiple punch lists. The court concluded that the City was entitled to liquidated damages in the sum of $134,250 plus interest at the rate of 6% per annum from June 18, 2008.

Turning to the City’s counterclaim, the court found that, despite the difficulty in getting SBS to complete the job, the City failed to avail itself of its right to terminate the contract until March 2010.2 The court noted that the law was clear that an injured party cannot sit idly by and allow liquidated damages to increase. According to the court, the breach occurred in May 2008, but the City sat idly by and allowed liquidated damages to escalate. The court concluded that the City was entitled to judgment for $30,999.66 for remedial work to complete the project and that $20,000 of this amount had been withheld by the City.3 SBS filed its notice of appeal on March 21, 2012. The City filed its notice of cross-appeal on March 30, 2012.

The City filed its motion for attorney’s fees on March 7, 2012, seeking $51,262 for fees. By order entered on April 13, 2012, the circuit court awarded the City $51,262 in attorney’s fees, to be paid within sixty days. SBS filed its notice of appeal from the fee order | (ion May 11, 2012.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McDermott Brandon Properties, LLC v. Wheeler
2023 Ark. App. 269 (Court of Appeals of Arkansas, 2023)
Riley v. Welcometotulum Inv. Props., LLC
544 S.W.3d 561 (Court of Appeals of Arkansas, 2018)
Thompson v. Broussard
2017 Ark. App. 423 (Court of Appeals of Arkansas, 2017)
Southern Building Services, Inc. v. City of Fort Smith