Hansen v. Covell

24 P.2d 772, 218 Cal. 622, 89 A.L.R. 670, 1933 Cal. LEXIS 553
CourtCalifornia Supreme Court
DecidedJuly 31, 1933
DocketDocket No. Sac. 4428.
StatusPublished
Cited by91 cases

This text of 24 P.2d 772 (Hansen v. Covell) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hansen v. Covell, 24 P.2d 772, 218 Cal. 622, 89 A.L.R. 670, 1933 Cal. LEXIS 553 (Cal. 1933).

Opinion

SHENK, J.

The cross-appeals involved herein are from a judgment establishing a balance due from the defendant, George F. Covell, to the plaintiffs, C. H. Hansen and Joseph C. Buchen, contractors under a building construction contract. The contractors sought to recover unpaid balances under the contract plus certain items of extras and damages alleged to be due from said defendant, who is the owner of the property involved. A cross-complaint was filed by Covell against the contractors alleging abandonment on the part of the contractors and the cost of completion by said defendant for which he sought recovery against the contractors and their surety. These two actions and three other actions to foreclose mechanics’ liens were consolidated for trial. The word “plaintiffs” used herein refers unless otherwdse noted, to the plaintiffs, the contractors Hansen and Buchen, and the word “defendant” refers to the defendant Covell, the owner.

On May 25, 1923, the plaintiffs and the defendant entered into a contract whereby the former agreed to construct, exclusive of the steel work on the real property of the latter situated in the city of Modesto, a four-story and basement hotel building, in accordance with certain plans and specifications, for the contract price of $125,500. The building was to be completed on or before the first day of October, 1923, plus such additional time as the contractors might become entitled to under the contract. The Globe Indemnity Company was the surety on the contractors’ bond. The contract and the bond were duly filed for record.

Work was commenced on May 26, 1923, and possession of the structure was taken by the defendant on February 21, 1924. Progress payments were to be made as the construction proceeded, and final payment was due thirty-five days after completion. On February 21, 1924, a progress payment in the sum of $11,295 remained unpaid. The final payment in the sum of $12,550 also remained unpaid. In *625 the meantime mechanics’ liens of subcontractors were filed against the property. By their action the plaintiffs sought to recover the two sums of $11,295 and $12,550 with interest; also the sum of $3,303.65 alleged to be due for extras, and the further sum of $33,737, comprising twenty-one items of damages alleged to have been caused to the plaintiffs by the acts, neglect and delay of the owner.

By his answer and cross-complaint the defendant resisted the claims of the plaintiffs and sought to recover from the plaintiffs the sum of $7,284.80 alleged to be the amount expended by the defendant in completing the building, and further sums totaling $29,592.05 as damages.

During the course of the trial the owner paid the claims of mechanics who had filed liens to the extent of $9,183.32, and the surety company paid off a similar amount. There remained for determination in the consolidated actions also the claims of Stockton Plumbing Supply Company for $7,719.50, J. B. Biekel for $6,334.30, and J. M. Adams for $345.76.

After a protracted trial on the numerous issues raised the court found that the plaintiffs had substantially performed their contract so as to become entitled to a judgment for the sums of $11,295 and $12,550 remaining unpaid; but that the defendant was entitled to an offset for certain imperfections and defective workmanship, including the sum of $2,824.02 for the cost of removal and re-installation of bathtubs; $512.50 for imperfect columns and plastering; and $50 for concrete sidewalks, making a total to be deducted for offsets of $3,386.52. The defendant was adjudged entitled to a further credit on account of the sum of $9,183.32 paid by him to lien claimants. The court found various items of damages caused to the plaintiffs by the delay of the defendant, including also damages for withholding portions of certain progress payments beyond the times when the same became payable, in sums aggregating $2,827.99. Extras to which the plaintiffs were found to be entitled aggregated the sum of $495.65. Interest was also awarded to the plaintiffs on the two unpaid installments on the contract price from the dates they respectively were payable to the time of entry of judgment in the total sum of $8,195.35. The balance of $22,794.15 computed on the basis of the *626 above counter-awards, was decreed to be due from the defendant to the plaintiffs with costs.

In addition to the above the court adjudged the amounts due to the three lien claimants, and decreed the amounts found to be due to be a lien against the property of the owner to the following extent: Stockton Plumbing Company, $4,855.48, with interest from the commencement of foreclosure proceedings in the sum of $1608.16; J. E. Bickel, $5,818.50, with interest in the sum of $1900.68; and J. M. Adams, $298.26, with interest in the sum of $97.08; a total as against the owner of $14,578.16. As against the contractors and the surety company, the court added to the above amounts respectively the sums allowed as a deduction to the owner for defective workmanship; or, in other words, as against the contractors and the surety company, the court allowed the claims of the subcontractors without deduction for the respective items of offset involved in their claims and allowed to the owner for defective workmanship, thus making the total principal due from the contractors or the surety company to the lien claimants the sum of $14,278.06, with interest in the sum of $4,697.75.

The plaintiffs and the defendants Coveil and Globe Indemnity Company have appealed from the foregoing judgments, the plaintiffs and the Globe Indemnity Company from that portion of the judgment awarding damages to the defendant in the sum of $3,386.52 for defective workmanship, and the defendant Coveil from the whole of the judgment. A question is raised by the plaintiffs whether the notice of appeal filed by the defendant Co veil has the effect of an appeal by him from the whole of the judgment. However, the notice of intention to appeal and to prepare transcript, also filed by the defendant Coveil, contained ■ such a notice and as such has the effect of a notice of appeal from the whole judgment. (Purity Springs W. Co. v. Redwood Ice Delivery, 203 Cal. 286 [263 Pac. 810].)

A consideration of the record leads us to the conclusion that the contentions relating to the sufficiency of the evidence to support the awards to the plaintiffs for extras and damages, and to the defendant on account of imperfections and defective workmanship, are unfounded and that such awards may not be disturbed on the ground that the *627 evidence is insufficient to support them. The defendant, however, contends that the plaintiffs have by the contract waived any damages which might otherwise accrue by delay caused by the acts or neglect of the owner. The contract provides that “the time during which the contractors may be delayed by the acts or neglect of the owner or his employees ... or by the act of God . . . which are not caused by, or the continuance of which is not due to any reasonable" acts or conduct on the part of the contractors, shall be added to the time of completion”. Throughout the record it is shown that the contractors applied for extensions by virtue of the very acts of delay for which the court awarded damages.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

NICO Alloys v. American Metal Group CA2/2
California Court of Appeal, 2015
United States v. Travelers Casualty & Surety Co. of America
55 F. Supp. 3d 852 (N.D. West Virginia, 2014)
Southern Building Services, Inc. v. City of Fort Smith
2014 Ark. App. 437 (Court of Appeals of Arkansas, 2014)
Goodman v. Lozano
72 Cal. Rptr. 3d 275 (California Court of Appeal, 2008)
Radman v. Flanders Corp.
2007 UT App 351 (Court of Appeals of Utah, 2007)
Wakefield v. Bohlin
52 Cal. Rptr. 3d 400 (California Court of Appeal, 2006)
Wisper Corp. v. California Commerce Bank
49 Cal. App. 4th 948 (California Court of Appeal, 1996)
First National Bank of Minneapolis v. Kehn Ranch, Inc.
394 N.W.2d 709 (South Dakota Supreme Court, 1986)
Law v. Blue Lagoon-Pompano, Inc.
470 So. 2d 33 (District Court of Appeal of Florida, 1985)
Cox v. Summa Corp.
751 F.2d 1507 (Ninth Circuit, 1985)
Price Building Service, Inc. v. Holms
693 P.2d 553 (Montana Supreme Court, 1985)
Chesapeake Industries, Inc. v. Togova Entreprises, Inc.
149 Cal. App. 3d 901 (California Court of Appeal, 1983)
E. L. White, Inc. v. City of Huntington Beach
138 Cal. App. 3d 366 (California Court of Appeal, 1982)
Bentz Plumbing & Heating v. Favaloro
128 Cal. App. 3d 145 (California Court of Appeal, 1982)
Hughes Tool Co. v. Max Hinrichs Seed Co.
112 Cal. App. 3d 194 (California Court of Appeal, 1980)
Fairway Builders, Inc. v. Malouf Towers Rental Co.
603 P.2d 513 (Court of Appeals of Arizona, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
24 P.2d 772, 218 Cal. 622, 89 A.L.R. 670, 1933 Cal. LEXIS 553, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hansen-v-covell-cal-1933.