Perry v. Magneson

279 P. 650, 207 Cal. 617, 1929 Cal. LEXIS 542
CourtCalifornia Supreme Court
DecidedJuly 18, 1929
DocketDocket No. S.F. 13062.
StatusPublished
Cited by39 cases

This text of 279 P. 650 (Perry v. Magneson) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Perry v. Magneson, 279 P. 650, 207 Cal. 617, 1929 Cal. LEXIS 542 (Cal. 1929).

Opinion

WASTE, C. J.

The defendant United States Fidelity and Guaranty Company, a corporation, appeals from a judgment entered against it and in favor of the plaintiff, R. A. Perry, on a bond executed by it, conditioned upon the performance of a building contract by the defendant O. M. Magneson.

On June 10, 1910, plaintiff and defendant Magneson entered into a contract whereby the defendant agreed to construct a residence and garage for the plaintiff in accordance with certain plans and specifications, and to furnish all labor and materials necessary for such construction, at the agreed price of $23,567, the building to be completed within a designated period of time. Concurrently with the execution of the contract, the defendant Surety Company executed and delivered to plaintiff its bond in the penal sum of $6,000, agreeing to indemnify plaintiff for any pecuniary loss resulting from the breach of any of the terms and conditions of the contract by the defendant contractor. Magneson breached the contract by abandoning the work on February 11, 1911. On notification of the abandonment the Surety Company declined to take any steps in connection with the contract, and the work was completed by the plaintiff-owner, who thereafter instituted this action to recover on the bond. The prayer of the amended complaint was for the sum of $6,000, and costs. Judgment was given in favor of the plaintiff and against the Surety Company in the full penal amount of the bond, with interest at the rate of seven per cent from October 16, 1911, the date of the commencement of the suit, aggregating $12,834.32, together with interest thereon from the date of judgment until paid, and costs. No judgment was rendered against defendant Magneson, he having been previously adjudged a bankrupt.

It appears that after the completion of the building by the owner many lien suits were filed. As the determination of the action to recover on the bond was somewhat dependent upon the outcome of the lien cases, it was agreed between counsel for the respective parties hereto that the trial of this action should be postponed until the lien suits were finally determined. They therefore entered into a stipulation on *620 November 30, 1915, that this ease should be dropped from the calendar, to be .restored on five days’ notice by either party. The judgment in the lien cases, after two appeals, became final in June, 1919. Shortly thereafter the present cause was set for trial, and was continued from time to time until November, 1922, when the trial actually commenced. Judgment was ordered for the plaintiff, The Surety Company’s motion for a new trial was granted, and on April 30, 1926, the second trial commenced, at which time the Surety Company objected to proceeding with the ease, and moved to dismiss the action for want of prosecution, the same objection and motion having been made prior to the commencement of the first trial. The motion to dismiss was denied, and judgment in favor of the plaintiff was entered on January 28, 1928.

Appellant contends that, more than five years having elapsed between the time of the filing of the answers to plaintiff’s amended complaint and the date when the trial of the action commenced, and the parties not having entered into a written stipulation extending the time, its motion to dismiss should have been granted under the provisions of section 583 of the Code of Civil Procedure. (Miller & Lux, Inc., v. Superior Court, 192 Cal. 333 [219 Pac. 1006].) The mere lapse of five years between the filing of the answer and the date of the trial does not deprive the court of jurisdiction to thereafter try the case. The only relief granted under section 583, supra, by our decisions has been to require, on proper showing, that an order of dismissal be entered. (Rio Vista Min. Co. v. Superior Court, 187 Cal. 1, 5, 6 [200 Pac. 616].) If the court fails to grant that relief, two remedies are available to the injured party. He may, by mandamus directed against the trial court, compel the dismissal (Andersen v. Superior Court, 187 Cal. 95, 97 [200 Pac. 963]), or, by noting an exception to the ruling of the court and properly presenting the same by means of a bill of exceptions, he may have the order reviewed upon an appeal from the judgment. The appellant took neither of these steps. The order refusing to dismiss the action is not itself an appealable order, and is not one deemed excepted to under section 647 of the Code of Civil Procedure. No exception having been taken at the time the decision was made, it will be presumed that the *621 appellant acquiesced in the ruling of the court, and the objection cannot now be urged on appeal. (Davies v. Ramsdell, 40 Cal. App. 424, 427 [181 Pac. 94].)

The contractor’s bond provided that in no event should the surety be subject to any suit, action or other proceeding thereon that was instituted later than the thirteenth day of June, 1911. It is the contention of the appellant, therefore, that this action is barred by the fact that suit was not instituted until October 16, 1911. In this connection, the trial court found that immediately upon the abandonment of the contract by Magneson, and within thirty days after knowledge of his default, the plaintiff, in writing, as provided in the bond, notified the United States Fidelity and Guaranty Company of the fact, showing the abandonment by Magneson; that the Guaranty Company declined to assume and complete or procure the completion of the contract, but accepted the notice and “thereupon agreed to and with plaintiff to waive the requirements of said bond that suit be commenced thereon on or before the 13th day of June, 1911, and agreed to and with plaintiff to pay to plaintiff the amount of the liability thereunder when the exact amount of plaintiff’s damage be ascertained, and further agreed to and with plaintiff that action might be commenced upon said bond at any time subsequent to said 13th day of June, 1911, when such amount of damage was ascertained.” Reasonable intendments and inferences to be drawn from the evidence support the finding. The provision for the limitation of time for the commencement of suit upon the bond was no doubt reasonable in point of time under ordinary circumstances, and, had the surety merely insisted upon a strict compliance with the provision, its position here would be tenable. (Fitzpatrick v. North American Acc. Ins. Co., 18 Cal. App. 264 [123 Pac. 209].) But the appellant here did not do that. While it declined to take any steps in connection with the contract with Magneson in relation to the completion of the building when the contractor abandoned the work, it notified the plaintiff in writing that it would “be ready to meet its liability, if there is any, upon the bond when the amount of that liability is finally determined.” We believe that agreement brings the case well within the rule that a surety cannot hold out a hope of amicable adjustment of claims and thus *622 delay action against it, and then plead the delay caused by its own conduct as a defense to the action when brought. (14 R. C. L. 1423; Thompson v. Phoenix Ins. Co., 136 U. S. 287, 34 L. Ed. 408, 413, 10 Sup. Ct. Rep. 1019].)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rhode v. National Medical Hospital of Monterey Park, Inc.
93 Cal. App. 3d 528 (California Court of Appeal, 1979)
Estate of Sharp
18 Cal. App. 3d 565 (California Court of Appeal, 1971)
Title Insurance & Trust Co. v. San Diego Hospital Ass'n
18 Cal. App. 3d 565 (California Court of Appeal, 1971)
Big Bear Mun. Water Dist. v. Superior Court of San Bernardino Cty.
269 Cal. App. 2d 919 (California Court of Appeal, 1969)
Flamer v. Superior Court
266 Cal. App. 2d 907 (California Court of Appeal, 1968)
Owens v. Pyeatt
248 Cal. App. 2d 840 (California Court of Appeal, 1967)
Conderback, Inc. v. Standard Oil Co.
239 Cal. App. 2d 664 (California Court of Appeal, 1966)
Vogelsang v. Wolpert
227 Cal. App. 2d 102 (California Court of Appeal, 1964)
Benson v. City of Los Angeles
384 P.2d 649 (California Supreme Court, 1963)
Coronet Constr. Co., Inc. v. Palmer
194 Cal. App. 2d 603 (California Court of Appeal, 1961)
Schmidt v. Waterford Winery, Ltd.
177 Cal. App. 2d 28 (California Court of Appeal, 1960)
Shell Chemical Corp. v. Owl Transfer Co.
344 P.2d 108 (California Court of Appeal, 1959)
Shell Chemical Corp. v. OWL Transfer Co.
173 Cal. App. 2d 796 (Appellate Division of the Superior Court of California, 1959)
Stamler v. Kissinger
315 P.2d 887 (California Court of Appeal, 1957)
Sears, Roebuck & Co. v. Blade
294 P.2d 140 (California Court of Appeal, 1956)
Chase v. National Indemnity Co.
278 P.2d 68 (California Court of Appeal, 1954)
Anderson v. Anderson
276 P.2d 862 (California Court of Appeal, 1954)
Guyman v. Anderson
271 P.2d 1020 (Idaho Supreme Court, 1954)
Industrial Indemnity Co. v. Industrial Accident Commission
252 P.2d 649 (California Court of Appeal, 1953)

Cite This Page — Counsel Stack

Bluebook (online)
279 P. 650, 207 Cal. 617, 1929 Cal. LEXIS 542, Counsel Stack Legal Research, https://law.counselstack.com/opinion/perry-v-magneson-cal-1929.