Coronet Constr. Co., Inc. v. Palmer

194 Cal. App. 2d 603, 15 Cal. Rptr. 601, 1961 Cal. App. LEXIS 1857
CourtCalifornia Court of Appeal
DecidedAugust 9, 1961
DocketCiv. 24966; Civ. 24967
StatusPublished
Cited by4 cases

This text of 194 Cal. App. 2d 603 (Coronet Constr. Co., Inc. v. Palmer) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Coronet Constr. Co., Inc. v. Palmer, 194 Cal. App. 2d 603, 15 Cal. Rptr. 601, 1961 Cal. App. LEXIS 1857 (Cal. Ct. App. 1961).

Opinion

BISHOP, J. pro tem. * *

These two cases were tried together ; the plaintiff in the second, is one of the defendants *607 in the first; and the issues are intertwined. It therefore seems well to consider them together.

The first action is for damages caused by the breach of a contract of March 3, 1958, allegedly entered into between the plaintiffs and the defendants. The second one was an endeavor by one who was a defendant in the first cause to foreclose a mechanic’s lien. A judgment was entered, in the first case, awarding the plantiffs $37,504.20, and one decreeing that the plaintiff take nothing was entered in the second case. Defendants D. M. Patritti, Consumers Transportation Corporation, and Cee Tee Construction Company appealed from the first judgment and Consumers Transportation Corporation, the plaintiff in the second action, appealed from its judgment. We have concluded, in the first case, that the evidence fails to support the findings against defendant Consumers Transportation Corporation. As to the other two appealing defendants we are modifying the judgment by striking the provision for interest. We are affirming the judgment in the second ease.

We will relate the facts of interest in the first case somewhat sketchily, mainly for background purposes. The plaintiffs owned a newly plotted tract of land in Encino, hilly country, well away from the center of Los Angeles City. In order to get the area to acceptable grades, some parts had to be cut down, some parts filled in and compacted. The defendants, or some of them, entered into a contract, in writing, with the plaintiffs whereby they (the defendants) undertook to do the work just referred to. They entered upon the performance of the contract; worked more than six months; were paid by the plaintiffs, directly, nearly $70,000 and in addition plaintiffs paid for defendants’ benefit some $11,000. The defendants quit work before the job was completed and plaintiffs carried on, expending some $33,000 more to finish the work. It was to recover the damages that they suffered by reason of defendants’ failure to complete their contract for the agreed contract price that the plaintiffs brought the first action.

Probably the most difficult question to answer, of those that confronted the trial court, was this one: What persons were bound by the contract? Beginning with the instrument itself, plaintiffs’ Exhibit 1, we note that it was composed of a printed form which furnished the opening provisions and the conclusion of that agreed upon. To this printed form were attached two typewritten sheets, and, at one time, so the last *608 sentence on the typewritten sheets states, “said plans,” quite essential to give the contract substance, “are attached hereto and made a part of this contract. ’ ’

In its opening paragraph the contract declares that it is made and entered into “. . . by and between Coronet Construction Co., Inc. . . . hereinafter called Owner and E. M. Palmer & Associates . . . hereinafter called Sub-Contractor.” Thereafter, throughout the printed form, the references are to “Contractor” and “Sub-Contractor,” none to “Owner.” The typewritten pages, however, refer to “Owner” and “Contractor.” Without doubt the trial court was justified in interpreting “Sub-Contractor” wherever it appeared as “Contractor,” and understanding “Contractor” to mean “Owner,” except where, in the typewritten pages, it did mean “Contractor.”

The manner in which the contract was executed is of some guidance in answering the question: Whom did it obligate? Words can not as readily reveal the manner of execution so it is better seen:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Weiner v. Fleischman
816 P.2d 892 (California Supreme Court, 1991)
Day v. Rosenthal
170 Cal. App. 3d 1125 (California Court of Appeal, 1985)
A. A. Baxter Corp. v. Colt Industries, Inc.
10 Cal. App. 3d 144 (California Court of Appeal, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
194 Cal. App. 2d 603, 15 Cal. Rptr. 601, 1961 Cal. App. LEXIS 1857, Counsel Stack Legal Research, https://law.counselstack.com/opinion/coronet-constr-co-inc-v-palmer-calctapp-1961.