Kingsbury v. Arcadia Unified School District

271 P.2d 40, 43 Cal. 2d 33, 1954 Cal. LEXIS 227
CourtCalifornia Supreme Court
DecidedJune 11, 1954
DocketL. A. 23074
StatusPublished
Cited by7 cases

This text of 271 P.2d 40 (Kingsbury v. Arcadia Unified School District) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kingsbury v. Arcadia Unified School District, 271 P.2d 40, 43 Cal. 2d 33, 1954 Cal. LEXIS 227 (Cal. 1954).

Opinion

SCHAUER, J.

Prom a judgment rendered by the court, sitting without a jury, awarding additional architect's fees for services rendered by plaintiff’s decedent, both parties appeal. Defendant attacks the judgment in its entirety, while plaintiff’s appeal is “based solely on that part of the judgment wherein” recovery of interest is denied. Por clarity, we shall hereinafter refer to the decedent as the architect. *36 We have concluded that the judgment should be sustained in all its aspects.

The issue presented is the interpretation of two contracts under which the architect rendered services. Under the first contract, made on December 1, 1943, and hereinafter called the 1943 contract, defendant school district employed the architect in connection with the proposed construction of an intermediate school building. For reasons not reflected in the record, the building was never constructed. Under the terms of the contract, as amended on February 6, 1946, the district paid to the architect a total of $33,000 for his services. Judgment was recovered for an additional $39,000.

Under the second contract, made on August 24, 1948, and hereinafter called the 1948 contract, the district paid to the architect $1,400 for services rendered' in connection with the proposed construction of classroom additions which project was also abandoned. Judgment was recovered for an additional $875.

1943 Contract

The chief controversy concerns the payment provisions of the 1943 contract. So far as here material that contract reads as follows:

“The District agrees to pay the Architect an amount equal to eight per cent (8%) 1 of the construction cost or costs of the ‘Building’ . . . when services as hereinafter stipulated have been rendered . . .
“Article 3. Payments. Payments to the Architect on account of [italics added] his fee shall be made as follows:
“a) Upon completion of the preliminary drawings and specifications ... an amount of Four Thousand Dollars ($4,000.00).
“b) Upon completion of a formal application to the proper governmental authorities in such form as may be required, on the basis of preliminary sketches and specifications, an additional amount of One Thousand Dollars . . .
“c) Upon completion of the working drawings and specifications, and their acceptance by the District ... an amount sufficient to increase the payments to a total of Nineteen Thousand Six Hundred Dollars ($19,600.00).
“d) Upon the completion of a formal application to the proper governmental authorities in such form as may be re *37 quired, an amount sufficient to increase the payments to a total of Twenty One Thousand Dollars . . .
“e) Upon the acceptance of the working drawings and specifications by the State Division of Architecture, an amount sufficient to increase the payments to a total of Twenty Two Thousand Four Hundred Dollars ($22,400.00).
“f) Upon completion of fifty percent (50%) of the construction work, an amount sufficient to increase the payments to ninety percent (90%) of the fee based upon the contract cost of the work.
“g) Upon completion of the construction work and its acceptance by the District ... an amount sufficient to increase the payments to one hundred percent (100%) of the fee based upon the total completed construction cost of the work.
“h) Should the work, as agreed upon, terminate with the services as stipulated under paragraph ‘a’ of Article 1 [preparation of preliminary drawings and specifications], then the payments as provided for under paragraph ‘a’ of Article 3 shall constitute the complete reimbursement to the Architect . . .
“If, at any future time, the District desires to resume the work [beyond preparation of preliminary drawings and specifications] . . . , then the amount of the payments made under paragraph ‘a’ of Article 3 shall be applied against the payments becoming due for the above services as stipulated in paragraphs ‘b’, ‘c’, ‘d’, ‘e’, ‘f’, and ‘g’ of Article 3. . . .
‘ ‘ Article 9. Abandonment of Project and Cancellation of Agreement. If the District determines at any time, not to proceed with the construction of the ‘Building’, or after the beginning of the construction work; to suspend indefinitely and/or abandon the construction work and shall require the Architect to suspend the performance of his services, or for reasons stipulated in Article 8 [inefficiency of Architect] decides to cancel or terminate this Agreement, there shall be due and payable within thirty (30) days after notice has been given in writing to the Architect of said suspension and/or abandonment or decision upon the part of the District to terminate or cancel this Agreement, a sum of money sufficient to increase [italics added] the total amount paid to the said Architect on the fee to an amount which shall bear the same proportion to the fee as the amount of services performed and/or provided by the Architect prior to the time of such suspension and/or abandonment or termination of this *38 Agreement shall bear to the entire services the Architect is required to perform and/or provide . . . Upon payment to the Architect of the amount or amounts provided under this Article the District may terminate and cancel this Agreement.
“Article 10. Supervision and Superintendence of the Work. . . . The Architect and the Engineers engaged by him shall supervise the work of construction covered by the working drawings and specifications prepared . . . within the scope of this Agreement ...”

In the contract the architect also agreed “to hire the services of a qualified Structional Engineer, and of a Mechanical and Electrical Engineer to collaborate jointly with him in the execution of his professional services.”

In February, 1944, defendant accepted the preliminary drawings and specifications prepared by the architect and paid him $4,000 as specified in paragraph (a) of article 3. On February 6, 1946, pursuant to a request by the architect for an amendment to the contract “to allow for an increase of payment since the original contract was estimated on a very low building cost basis, ’ ’ a written amendment to the contract was entered into, under which the payment provided in paragraph (c) of article 3 was increased from $19,600 to $33,000, that provided in paragraph (d) was increased from $21,000 to $34,000, and that provided in paragraph (e) from $22,400 to $35,750.

On June 5, 1946, defendant district accepted the final plans and specifications, prepared by the architect in collaboration with the structural engineer 2 employed by him, and on June 19, 1946, the district paid the architect $29,000, thus bringing the total payments to $33,000 as provided in amended paragraph (c) of article 3.

Nothing further was done by the architect under the contract, and on January 14, 1949, he died.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Meistrell v. McPhail
1989 OK CIV APP 67 (Court of Civil Appeals of Oklahoma, 1989)
City of Salinas v. Souza & McCue Construction Co.
424 P.2d 921 (California Supreme Court, 1967)
General Electric Co. v. Central Surety & Insurance
232 Cal. App. 2d 590 (California Court of Appeal, 1965)
Caplan v. Schroeder
364 P.2d 321 (California Supreme Court, 1961)
Coronet Constr. Co., Inc. v. Palmer
194 Cal. App. 2d 603 (California Court of Appeal, 1961)
Parker v. Maier Brewing Co.
180 Cal. App. 2d 630 (California Court of Appeal, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
271 P.2d 40, 43 Cal. 2d 33, 1954 Cal. LEXIS 227, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kingsbury-v-arcadia-unified-school-district-cal-1954.