City of Salinas v. Souza & McCue Construction Co.

424 P.2d 921, 66 Cal. 2d 217, 57 Cal. Rptr. 337, 1967 Cal. LEXIS 297
CourtCalifornia Supreme Court
DecidedMarch 21, 1967
DocketS. F. 22394
StatusPublished
Cited by57 cases

This text of 424 P.2d 921 (City of Salinas v. Souza & McCue Construction Co.) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Salinas v. Souza & McCue Construction Co., 424 P.2d 921, 66 Cal. 2d 217, 57 Cal. Rptr. 337, 1967 Cal. LEXIS 297 (Cal. 1967).

Opinion

PEEK, J. *

On these appeals the City of Salinas disputes findings that it misrepresented soil conditions to the damage of Souza & McCue Construction Company, its general contractor under a 1958 contract for the construction of a sewer-line.

The action was commenced by the city for damages for Souza’s alleged breach of the contract. The city also sought to recover from Souza’s surety, the Aetna Casualty & Surety Company, and from Armco Drainage & Metal Products, Inc., a supplier of products to Souza. In a pleading denominated a cross-complaint, Souza set forth causes of action against the city for the recovery of the balance allegedly due under the contract, and a common count for goods and services. Souza also cross-complained against Armco, alleging that the latter guaranteed performance of piping it supplied and had promised to indemnify Souza for any losses. After the city answered the cross-complaint, the trial court refused to allow Souza to amend to include causes of action against the city for fraudulent misrepresentation and breach of implied warranty of site conditions. We granted a writ of mandate directing the trial court to allow the filing of such an amendment. (Souza & McCue Constr. Co. v. Superior Court (1962) 57 Cal.2d 508 [20 Cal.Rptr. 634, 370 P.2d 338].)

*222 At the conclusion of the trial the court found that the city materially misrepresented soil conditions by failing to inform Souza and other bidders of unstable conditions known to it, that the city intended that Souza prepare its bid based on such misrepresentations, that Souza reasonably reiied on the misrepresentations in bidding on the contract, and that Souza should recover damages in the amount of $124,106, as proximately caused by the city’s fraudulent breach of contract. All other claims for relief were denied. On this appeal, the city’s main contention is that the foregoing findings, and the judgment based thereon, are not supported by the evidence.

There was considerable testimony that the city’s chief engineer in charge of the project, and other officials involved therein, had knowledge, from their general knowledge of the city and from past project experience, of highly unstable conditions existing in the subsoils along the plotted line of the sewer. They knew that particularly difficult conditions were likely to be encountered in an extensive slough area which the route crossed. There was also evidence that the chief engineer directed an independent testing firm to take borings at preselected spaeings and locations which avoided the area of the greatest unsettled conditions; that the method of taking the tests was misleading; that the reports of these boring tests were sent to bidders only a few days before the opening of bids, and that while it would have been proper practice to warn bidders of anticipated difficult conditions, the city officials did not do so.

It is the general rule that by failing to impart its knowledge of difficulties to be encountered in a project, the owner will be liable for misrepresentation if the contractor is unable to perform according to the contract provisions. (See United States v. Spearin (1918) 248 U.S. 132 [63 L.Ed. 166, 39 S.Ct. 59]; United States v. Atlantic Dredging Co. (1920) 253 U.S. 1, 11-12 [64 L.Ed. 735, 40 S.Ct. 423]; Gogo v. Los Angeles Flood Control Dist. (1941) 45 Cal.App.2d 334, 338, 341-342 [114 P.2d 65] ; A. Teichert & Son, Inc. v. State of California (1965) 238 Cal.App.2d 736, 755 [48 Cal.Rptr. 225].)

In a factually similar case, the contractor encountered “unusual quantities of quicksand and extensive subsoil water conditions which had not been shown on the plans or specifications . . . information as to which, although known to it, had been withheld by the city.” (Valentini v. City of Adrian *223 (1956) 347 Mich. 530, 533 [79 N.W.2d 885].) An award of damages was affirmed because, as stated at page 534: “The withholding by the city of its knowledge . . . resulting in excessive cost of construction, forms actionable basis for plaintiff’s claim for damages.”

Here, the city argues that provisions in the contract specifications requiring that the bidders “examine carefully the site of the work,” and stating that it is “mutually agreed that the submission of a proposal shall be considered prima facie evidence that the bidder has made such examination,” prevents a holding that the city is liable for the consequences of its fraudulent representation. However, even if the language had specifically directed the bidders to examine subsoil conditions, which it did not, it is clear that such general provisions cannot excuse a governmental agency for its active concealment of conditions. (See, e.g., United States v. Atlantic Dredging Co., supra, 253 U.S. 1; United States v. Spearin, supra, 248 U.S. 132; Christie v. United States (1915) 237 U.S. 234 [59 L.Ed. 933, 35 S.Ct. 565] ; A. Teichert & Son, Inc. v. State of California, supra, 238 Cal.App.2d 736.)

The city further argues that because it entered into a modification of the contract after Souza encountered initial subsurface difficulties, Souza waived any claim going to fraudulent representations. The modification provided for the use of imported soils for side support and backing material, extended the time and adjusted the contract price. This came about when the parties became aware that the native soils would not support the sewer line. At that time Souza, however, was still not aware of the city’s knowledge, nor did it have knowledge of its own, of the unstable conditions that might be expected to become increasingly grave as the line was further extended.

The modification provided that “the parties . . . have finally decided to settle and compromise all of their differences and settle their dispute by this compromise agreement.” The only dispute that had arisen at that point did not involve the considerable quicksand problems that Souza was to face during the remainder of the project, and concerned chiefly the inability of native soils to meet the compaction requirements of the original contract. That agreement could hardly be deemed to have settled a dispute over problems of which the contractor was not yet aware, and which, perforce, the parties could not have intended to include in the *224 agreement. (See Lemm v. Stillwater Land & Cattle Co. (1933) 217 Cal. 474, 482 [19 P.2d 785]; Warfield

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kelly v. House
California Court of Appeal, 2020
Cohen v. Sterling CA2/5
California Court of Appeal, 2015
King v. Willmett
187 Cal. App. 4th 313 (California Court of Appeal, 2010)
Los Angeles Unified School District v. Great American Insurance
234 P.3d 490 (California Supreme Court, 2010)
Broberg v. Guardian Life Insurance Co. of America
171 Cal. App. 4th 912 (California Court of Appeal, 2009)
McClain v. Octagon Plaza, LLC
71 Cal. Rptr. 3d 885 (California Court of Appeal, 2008)
Rotolo Chevrolet v. Superior Court
129 Cal. Rptr. 2d 283 (California Court of Appeal, 2003)
Amelco Electric v. City of Thousand Oaks
38 P.3d 1120 (California Supreme Court, 2002)
Plut v. Fireman's Fund Insurance
102 Cal. Rptr. 2d 36 (California Court of Appeal, 2000)
Howard Contracting, Inc. v. G.A. MacDonald Construction Co.
83 Cal. Rptr. 2d 590 (California Court of Appeal, 1999)
General Motors Corp. v. Northrop Corp.
685 N.E.2d 127 (Indiana Court of Appeals, 1997)
Pacific Gas & Electric Co. v. Superior Court
28 Cal. App. 4th 174 (California Court of Appeal, 1994)
Maxon Industries, Inc. v. State Compensation Insurance Fund
16 Cal. App. 4th 1387 (California Court of Appeal, 1993)
Merenda v. Superior Court
3 Cal. App. 4th 1 (California Court of Appeal, 1992)
Ralph Andrews Productions, Inc. v. Paramount Pictures Corp.
222 Cal. App. 3d 676 (California Court of Appeal, 1990)
Hurd v. Nelson
714 P.2d 767 (Wyoming Supreme Court, 1986)
Danzig v. Jack Grynberg & Associates
161 Cal. App. 3d 1128 (California Court of Appeal, 1984)
Arthur L. Sachs, Inc. v. City of Oceanside
151 Cal. App. 3d 315 (California Court of Appeal, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
424 P.2d 921, 66 Cal. 2d 217, 57 Cal. Rptr. 337, 1967 Cal. LEXIS 297, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-salinas-v-souza-mccue-construction-co-cal-1967.