Lasky v. American Indemnity Co.

282 P. 974, 102 Cal. App. 192, 1929 Cal. App. LEXIS 91
CourtCalifornia Court of Appeal
DecidedNovember 27, 1929
DocketDocket No. 6775.
StatusPublished
Cited by3 cases

This text of 282 P. 974 (Lasky v. American Indemnity Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lasky v. American Indemnity Co., 282 P. 974, 102 Cal. App. 192, 1929 Cal. App. LEXIS 91 (Cal. Ct. App. 1929).

Opinion

*195 GRAY, J., pro tem.

Defendant, the surety on a bond given under the terms of section 1183 of the Code of Civil Procedure, appeals, under the alternative method, from a judgment ordering payment of the full penal sum to the clerk of the court, for distribution between the owners of the building and various lien claimants whose respective suits had been consolidated for trial on defendant’s motion. But a brief statement of fact is necessary for an adequate consideration of defendant’s contentions. Contemporaneously, the owners, hereinafter referred to as the plaintiffs, and a building contractor entered into two written contracts, the first, for the exchange of properties, and the second, for the construction of an apartment house. In the exchange contract plaintiffs agreed to convey to the contractor their equity in certain flats, at an agreed valuation of $10,000 and the contractor agreed to convey to plaintiffs a vacant lot and construct thereon, in accordance with the terms of the building contract, an apartment house at a total cost, for land and building of $22,300, payable by a credit thereon, of said sum of $10,000 and balance as specified in the building contract. It is undisputed that the parties, verbally, segregated the sum of $10,000 into two items: $3,500 for the price of the vacant lot and $6,500 as the first payment on the cost of the apartment house. The building contract, in the ordinary terms usually used in such contracts, provided that the contractor would construct, according to plans and specifications, an apartment house and that plaintiffs would pay therefor a total of $18,800, payable $6,500 forthwith and the balance in four installments as the work progressed. On the next day defendant executed and delivered to plaintiffs its bond in the penal sum of $10,000. The contractor abandoned the work after receiving the second and third installment payments, amounting to $5,100. After notice and demand, defendant refused to complete the building contract and the plaintiffs finished the building at a cost of $7,857.84 in excess of the contract price. The foregoing facts are undisputed.

By way of cross-complaint, defendant sought a cancellation of its bond, alleging, briefly stated, that plaintiffs, several days after the execution and delivery of the bond, falsely represented to it, that the exchange contract was no *196 longer in effect. The undisputed evidence discloses that, at such time, the plaintiff husband and a companion called at the office of defendant’s general agent, at the latter’s request, and there delivered to him copies of both contracts, that the agent retired to his private office for fifteen minutes, and, upon returning, conversed with the husband and his companion. What was said and done in this conversation is disputed by the parties. A stenographer of the agent, who died before trial, testified that, in response to the agent’s inquiry, the companion said the exchange was no longer in effect and that the husband concurred therein. Both these gentlemen denied that either made such statement and both testified that the agent said that the contracts were all right. Upon this conflict the court found that the alleged misrepresentation had not been -made. Urging, that as the stenographer’s testimony is the more probable, it is entitled to the greater weight, defendant requests that we hold, upon a review of the evidence, that this finding is unsupported. Since the weight of evidence is for the trial court’s determination, our review is limited to ascertaining whether there is any substantial evidence to support a finding, and, if there is, we cannot disturb it. (2 Cal. Jur. 935.) It is apparent that plaintiff’s testimony adequately supports this finding. Defendant further criticises the court’s additional finding that plaintiffs • informed it that the exchange contract was still effective, on the ground that there is no direct, evidence to that effect. While there is no such direct testimony, yet the trial court might well, &s it impliedly did, infer such statement from the acts and conduct of the parties. (Ryder V. Bamberger, 172 Cal. 791 [158 Pac. 753].)

In several different ways defendant argues that no recovery can be had on the bond because plaintiffs did not pay in cash the sum of $6,500 as the first payment or that, if any recovery is had, the amount thereof should be reduced by such sum. This argument entirely ignores the above finding that it knew of the existence of the exchange contract, and, inferentially, contracted on the basis of its continued existence. It also overlooks another finding, not questioned by it, that the contractor, a,s part of the same transaction in which the two contracts were executed, real *197 ized from encumbrances placed by Mm on the flats, money in excess of $6,500. Therefore, indirectly, the contractor did receive from plaintiffs the first payment and defendant was not injured by the existence of the exchange contract.

Eleven subcontractors sued to foreclose their liens. In six of these actions a cause of action upon the bond was stated and in four of the six defendant was named as a party. The court found that the claims of plaintiffs in these four actions amounted to $4,559.93, that plaintiffs in the instant case were entitled to recover $7,857.48, and that the aggregate of these two sums exceeded the penal sum of $10,000 namd in the bond. Upon defendant’s motion these eleven actions were consolidated for trial with the instant case. Pursuant to stipulation between plaintiffs and the eleven- subcontractors, the judgment ordered defendant to pay to the clerk of the court the sum of $10,000 and authorized the latter to distribute this sum as provided in the stipulation. Half-heartedly, defendant, ignoring their literal wording, attempts to misconstrue the findings as authorizing judgment against it and in favor of subcontractors who sought no recovery on the bond. By stipulation those entitled to judgment- under their pleadings permitted others not so entitled to participate in their judgments. This arrangement followed in the judgment did not increase the amount for which defendant was legally liable, but merely, by way of assignment, increased the number of persons participating in the distribution of the sums legally recoverable. As defendant was not injured thereby it has no cause of complaint. (Robinson v. Western States Gas etc. Co., 184 Cal. 401 [194 Pac. 39].)

Defendant requests a modification of that portion of the judgment awarding costs to all plaintiffs in the consolidated actions, in so far as it awards such costs to five of such plaintiffs, because four of such five did not sue defendant and the other sought no recovery on the bond. Plaintiffs Lasky, there being no briefs on behalf of any of the subcontractors, object to a consideration of this request on the ground that the record does not show that any of such five plaintiffs filed cost bills. Obviously, since such modification does not affect the objecting plaintiffs, they are not in a position to object. But, as the appeal has *198 been taken from the entire judgment, the portion as to costs is subject to review, even if there is no showing of such filing. (White v. Gaffney, 1 Cal. App. 715 [82 Pac.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Granite Construction v. Bond Safeguard Ins. CA3
California Court of Appeal, 2014
Application of Bertelson
617 P.2d 121 (Montana Supreme Court, 1980)
Kingsbury v. Arcadia Unified School District
271 P.2d 40 (California Supreme Court, 1954)

Cite This Page — Counsel Stack

Bluebook (online)
282 P. 974, 102 Cal. App. 192, 1929 Cal. App. LEXIS 91, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lasky-v-american-indemnity-co-calctapp-1929.