Gray v. Bekins

199 P. 767, 186 Cal. 389, 1921 Cal. LEXIS 458
CourtCalifornia Supreme Court
DecidedJune 29, 1921
DocketS. F. No. 7637.
StatusPublished
Cited by50 cases

This text of 199 P. 767 (Gray v. Bekins) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gray v. Bekins, 199 P. 767, 186 Cal. 389, 1921 Cal. LEXIS 458 (Cal. 1921).

Opinion

LENNON, J.

The partial destruction of an unfinished building by an earthquake on April 18, 1906, engendered the controversy which culminated in the present action. Plaintiffs had constructed the first and second stories of a six-story brick and concrete warehouse, which they had contracted to build for defendants, when the portions erected were damaged by earthquake on the date above mentioned. When plaintiff H. N. Gray, defendant Martin Bekins, the architect, and brick contractor met at the building a few; weeks after the earthquake and examined the structure to ascertain the damages, it was decided that some repairing was necessary. .The exact amount of repairing was not determined, but there is testimony that it was decided that, before any further work was performed by plaintiffs, the building inspector of the board of public works of San Francisco should pass upon the extent of repairing to be done so that any subsequent controversy with the board might be avoided.

Plaintiff H. N. Gray testified that it was agreed that, before plaintiffs proceeded with the work, the examination by the building inspector should be procured by defendants and that the latter should inform plaintiffs of the result. The next information plaintiffs received after the meeting of the parties at the building above referred to was in the following month of June, when plaintiff - H. N. Gray drove to the *393 building and for the first time discovered men taking down the brick work and cleaning the brick, although plaintiffs liad not authorized anyone to tear down or demolish any portion of the building. Plaintiffs thereupon wrote a letter to the architect, dated June 29, 1906, containing a notification that, by tearing down portions of the brick work without plaintiffs’ consent, defendants had broken and terminated the contract with plaintiffs. The architect delivered this letter to defendants. The next word received by plaintiffs was a communication from defendants, dated August 14, 1906, notifying plaintiffs that, unless they immediately repaired the damages caused by the earthquake, defendants would make the repairs and charge plaintiffs with a proportionate share thereof. After the receipt of this letter, plaintiff H. N. Gray again went to the building and, finding that a considerable amount of repairing had already been performed by defendants, declined to proceed under the contract. It also appears from the testimony that, continuously after the earthquake, the first floor of the building was occupied by the “Bekins Van & Storage Company”; an office for the company had been established in the building, a sign bearing the name of the company was on the front of the building and several van loads of furniture were stored in the building. Neither plaintiffs nor the brick contractor gave permission to anyone to occupy any portion of the structure.

In August, 1906, plaintiffs instituted the present action for the recovery of $6,242.03, the difference between $13,742.03, the value of the work performed on the building by plaintiffs up to April 18, 1906, and seven thousand five hundred dollars, the sum alleged by plaintiffs to have been paid by defendants. The complaint contains three causes of action. In the first cause of action it is alleged that defendants prevented the performance of the contract by the acts above set forth. The second and third counts omit all reference to the contract and are respectively in indebitatus assumpsit and quantum meruit. Defendants’ answer denies that performance of the contract was prevented by defendants, admits the value of the work performed by plaintiffs was $13,742.03, and alleges that $10,485.00 of this sum has been paid, alleging, by way of a special defense and counterclaim, that the contract provides that the sum paid should at no *394 time during the progress of the work exceed three-fourths of the value of the work done and, therefore, the sum paid by defendants to plaintiffs was in excess of the amount due, and that, by the terms of the contract, plaintiffs are liable to defendants for a proportionate share of the sum expended by defendants in repairs. Defendants seek to recover a judgment against plaintiffs for $654.75.

The trial court found, among other things, that defendants rendered it impracticable and impossible for plaintiffs to proceed with the construction of the building by taking possession of and occupying the unfinished building as a warehouse and by tearing down and demolishing large portions of the unfinished warehouse, all without authority or consent from plaintiffs. The court further found that $13,742.03 was the value of labor and material furnished by plaintiffs in the construction of the warehouse, of which sum $10,485.00 had been paid plaintiffs by defendants, and rendered judgment in favor of plaintiffs for the sum of $3,257.03. Defendants appeal from the whole of the judgment and plaintiffs appeal from that portion which allows plaintiffs interest on the amount of the judgment only from the date of the entry of the judgment.

The main point advanced by defendants is that plaintiffs failed to allege or prove full performance or facts excusing performance by plaintiffs. [1] A party who has contracted to perform an act for an agreed consideration can maintain an action upon the contract even though he himself has failed to fully perform if performance on his part was prevented by operation of law, the act of the other party to the contract, the act of God or of the public enemy. (Civ. Code, sees. 1511, 1512, 1514.) [2] If the other party to the contract has not actually prevented performance, but has merely committed a breach of the contract, the party who has not fully performed the act agreed upon cannot maintain a suit upon the contract, but may treat the contract as terminated and sue for the reasonable value of that which he furnished under the contract. (Cox v. McLaughlin, 76 Cal. 70, [9 Am. St. Rep. 164, 18 Pac. 100]; Carlson v. Sheehan, 157 Cal. 692, 696, [109 Pac. 29]; Connell v. Higgins, 170 Cal. 541, [150 Pac. 769].) [3] In the instant case plaintiffs have treated the contract as rescinded and are suing for the reasonable value of labor performed and materials furnished, *395 and it was, therefore, unnecessary to allege or prove full performance on their part or acts which rendered performance impossible. If defendants violated the contract by the commission of the acts alleged, plaintiffs can recover the reasonable value of the work performed and materials furnished by them less any sums already paid by defendants.

[4] In every building contract which contains no express covenants on the subjects there are implied covenants to the effect that the contractor shall be permitted to proceed with the construction of the building in accordance with the other terms of the contract without interference by the owner and that he shall be given such possession of the premises as will enable him to adequately carry on the construction and complete the work agreed upon.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Silbermann v. Shangri-La Construction CA2/7
California Court of Appeal, 2020
Bullock v. Philip Morris USA, Inc.
198 Cal. App. 4th 543 (California Court of Appeal, 2011)
Uzyel v. Kadisha
188 Cal. App. 4th 866 (California Court of Appeal, 2010)
Gm Testani Construction Co. v. Delcegno, No. Cv-92-0291747s (Oct. 25, 1994)
1994 Conn. Super. Ct. 10872 (Connecticut Superior Court, 1994)
Chesapeake Industries, Inc. v. Togova Entreprises, Inc.
149 Cal. App. 3d 901 (California Court of Appeal, 1983)
Levy-Zentner Co. v. SOUTHERN PAC. TRANSPORTATION
74 Cal. App. 3d 762 (California Court of Appeal, 1977)
Coac, Inc. v. Kennedy Engineers
67 Cal. App. 3d 916 (California Court of Appeal, 1977)
Hartford Electric Applicators of Thermalux, Inc. v. Alden
363 A.2d 135 (Supreme Court of Connecticut, 1975)
San Diego Professional Ass'n v. Herrick
4 Cal. App. 3d 424 (California Court of Appeal, 1970)
Conderback, Inc. v. Standard Oil Co.
239 Cal. App. 2d 664 (California Court of Appeal, 1966)
Kenworthy v. State of California
236 Cal. App. 2d 378 (California Court of Appeal, 1965)
Kennedy v. Reece
225 Cal. App. 2d 717 (California Court of Appeal, 1964)
McConnell v. Pacific Mutual Life Insurance
205 Cal. App. 2d 469 (California Court of Appeal, 1962)
Caplan v. Schroeder
364 P.2d 321 (California Supreme Court, 1961)
Schmidt v. Waterford Winery, Ltd.
177 Cal. App. 2d 28 (California Court of Appeal, 1960)
Allen v. Miller
84 N.W.2d 571 (North Dakota Supreme Court, 1957)
Oliver v. Campbell
273 P.2d 15 (California Supreme Court, 1954)
Hensler v. City of Los Angeles
268 P.2d 12 (California Court of Appeal, 1954)
Magee v. Breckenridge
244 P.2d 103 (California Court of Appeal, 1952)
Bomberger v. McKelvey
220 P.2d 729 (California Supreme Court, 1950)

Cite This Page — Counsel Stack

Bluebook (online)
199 P. 767, 186 Cal. 389, 1921 Cal. LEXIS 458, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gray-v-bekins-cal-1921.