Kennedy v. Reece

225 Cal. App. 2d 717, 37 Cal. Rptr. 708, 1964 Cal. App. LEXIS 1423
California Court of Appeal·Decided March 19, 1964·No. Civ. 314·Published·Cited by 8 cases

Opinion

CONLEY, P. J.

This is an appeal by the plaintiff from a judgment adverse to him on his complaint and favorable to the defendants on their counterclaim. The plaintiff, Fred Kennedy, made a contract with Reece and Thomas, mining partners, to drill a water well for them; the agreement, on the letterhead of the Fred Kennedy Company, reads as follows:

“We propose to furnish all materials and perform all labor necessary to complete the following:
“drill 12” hole to estimated depth of 400’ 3.50 per ft. ease with new 6” well casing with bottom half perforated gravel pack, wash well and bail. 1.50 per ft.
“All of the above work to be completed in a substantial and workmanlike manner according to standard practices for the sum of two thousand Dollars ($2,000.00)
“Payments to be made $1,000.00 on signing this agreement bal when eased_$_as the work progresses to the value of_ per cent (_%) of all work completed. The entire amount of contract to be paid within_days after completion.
“Any alteration or deviation from the above specifications involving extra cost of materials or labor will only be executed upon written orders for same, and will become an extra charge over the sum mentioned in this contract. All agreements must be made in writing.
“ Resp ectfully submitted, Feed Kennedy Co.
Drilling and Sewer Contractors By: /s/ Fred Kennedy”

An acceptance is endorsed by Lewis H. Reece and Steven Thomas.

The complaint alleges with respect to the contract: “That on or about the 31st day of March, 1961, plaintiff and defendants entered into a written contract wherein plaintiff agreed to drill for defendants certain water well at an estimated *721 cost of Two Thousand Dollars; that after commencing drilling operations it was determined that it was not possible to obtain water in the area selected by defendants, hence, by mutual agreements the parties discontinued drilling operations, at which time there was due to plaintiff the sum of Four Hundred Dollars, demand for which has been made and no part of which has been paid.”

The answer and counterclaim avers, on the contrary, that the agreement was to drill a 12-inch hole for a water well to an estimated depth of 400 feet, case it with new 6-inch well casing with the bottom half perforated, and further to gravel pack, wash and bail the well for a fixed price of $2,000, payable $1,000 upon execution of the contract and the balance when the casing was installed; that the sum of $1,000 was paid upon the execution of the contract and that plaintiff “failed and refused to perform the contract and breached the same and after abandoning one hole at a depth of 130 feet, commenced a second hole, which he abandoned at 270 feet, and failed and refused and continues to fail and refuse to drill a hole to the depth of 400 feet and ease the same.” The pleading further alleges that the two holes in question were placed at points selected by the plaintiff as most likely to yield water; that plaintiff breached the contract by failing and refusing to complete the well; that the two holes in the ground have no value; that at the time the contract was entered into the plaintiff knew that the defendants required the well for the purpose of supplying water for their gold mining and milling operations. The counterclaim sets forth items constituting the alleged damages as follows:

“That as a direct and proximate result of plaintiff’s breach of contract, defendants sustained the following damages:
1. Cost of installing pump, motor and pipe line in the well on the property of a third person ... $1380.64
2. Additional cost of heavier pump.............$ 900.00
3. Cost of recapping abandoned holes ...........$ 200.00
4. Down payment.............................$1000.00
5. Loss of four months profit from gold mill operation ............................$12,000.00
all to defendants’ damage in the sum of $15,480.64.”

The cause was tried by the court sitting without a jury, and resulted in a judgment for the defendants on their counterclaim in the sum of $1,307.15, besides interest and costs.

The findings generally support the theory pleaded by the *722 defendants. The court expressly found that the allegations in the complaint as to the contract were not true, and that the averments in the answer relative to the agreement are true except with respect to damages, as to which it is held:

“That as a direct and proximate result of plaintiff’s breach of contract, defendants sustained the following damages:
1. Increased cost of Pump..........$1062.80
2. Electrical Work................ 290.15
3. Plastic & fittings........... 877.01
As set forth in defendants ’ Exhibit F:
1. Pumping plant panel & labor..... 208.62
2. One new #43 Hi Lift Stator only. 83.57
3. One Penn Control Switch........ 25.00
Total ...................................$2547.15
Less
1. Labor saved by using plastic pipe...........................$ 240.00
2. Balance on contract with plaintiff .......................$1000.00
Total..........................$1240.00 _
Defendants’ damages are the difference........$1307.15”

Free access — add to your briefcase to read the full text and ask questions with AI

Kennedy v. Reece, 225 Cal. App. 2d 717, 37 Cal. Rptr. 708, 1964 Cal. App. LEXIS 1423 (Cal. Ct. App. 1964).

225 Cal. App. 2d 717 (Kennedy v. Reece) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Fitness International v. KB Salt Lake III
California Court of Appeal, 2023
G. W. Andersen Construction Co. v. Mars Sales
164 Cal. App. 3d 326 (California Court of Appeal, 1985)
Kirkpatrick v. Temme
654 P.2d 1011 (Nevada Supreme Court, 1982)
Ellison v. City of San Buenaventura
48 Cal. App. 3d 952 (California Court of Appeal, 1975)
Avon Sheet Metal Co. v. HERITAGE HOUSE ASSOC.
259 A.2d 241 (New Jersey Superior Court App Division, 1969)
Kennedy v. Reece
240 Cal. App. 2d 769 (California Court of Appeal, 1966)
Bumby & Stimpson, Inc. v. Peninsula Utilities Corp.
169 So. 2d 499 (District Court of Appeal of Florida, 1964)