Kennedy v. Reece

225 Cal. App. 2d 717, 37 Cal. Rptr. 708, 1964 Cal. App. LEXIS 1423
CourtCalifornia Court of Appeal
DecidedMarch 19, 1964
DocketCiv. 314
StatusPublished
Cited by8 cases

This text of 225 Cal. App. 2d 717 (Kennedy v. Reece) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kennedy v. Reece, 225 Cal. App. 2d 717, 37 Cal. Rptr. 708, 1964 Cal. App. LEXIS 1423 (Cal. Ct. App. 1964).

Opinion

CONLEY, P. J.

This is an appeal by the plaintiff from a judgment adverse to him on his complaint and favorable to the defendants on their counterclaim. The plaintiff, Fred Kennedy, made a contract with Reece and Thomas, mining partners, to drill a water well for them; the agreement, on the letterhead of the Fred Kennedy Company, reads as follows:

“We propose to furnish all materials and perform all labor necessary to complete the following:
“drill 12” hole to estimated depth of 400’ 3.50 per ft. ease with new 6” well casing with bottom half perforated gravel pack, wash well and bail. 1.50 per ft.
“All of the above work to be completed in a substantial and workmanlike manner according to standard practices for the sum of two thousand Dollars ($2,000.00)
“Payments to be made $1,000.00 on signing this agreement bal when eased_$_as the work progresses to the value of_ per cent (_%) of all work completed. The entire amount of contract to be paid within_days after completion.
“Any alteration or deviation from the above specifications involving extra cost of materials or labor will only be executed upon written orders for same, and will become an extra charge over the sum mentioned in this contract. All agreements must be made in writing.
“ Resp ectfully submitted, Feed Kennedy Co.
Drilling and Sewer Contractors By: /s/ Fred Kennedy”

An acceptance is endorsed by Lewis H. Reece and Steven Thomas.

The complaint alleges with respect to the contract: “That on or about the 31st day of March, 1961, plaintiff and defendants entered into a written contract wherein plaintiff agreed to drill for defendants certain water well at an estimated *721 cost of Two Thousand Dollars; that after commencing drilling operations it was determined that it was not possible to obtain water in the area selected by defendants, hence, by mutual agreements the parties discontinued drilling operations, at which time there was due to plaintiff the sum of Four Hundred Dollars, demand for which has been made and no part of which has been paid.”

The answer and counterclaim avers, on the contrary, that the agreement was to drill a 12-inch hole for a water well to an estimated depth of 400 feet, case it with new 6-inch well casing with the bottom half perforated, and further to gravel pack, wash and bail the well for a fixed price of $2,000, payable $1,000 upon execution of the contract and the balance when the casing was installed; that the sum of $1,000 was paid upon the execution of the contract and that plaintiff “failed and refused to perform the contract and breached the same and after abandoning one hole at a depth of 130 feet, commenced a second hole, which he abandoned at 270 feet, and failed and refused and continues to fail and refuse to drill a hole to the depth of 400 feet and ease the same.” The pleading further alleges that the two holes in question were placed at points selected by the plaintiff as most likely to yield water; that plaintiff breached the contract by failing and refusing to complete the well; that the two holes in the ground have no value; that at the time the contract was entered into the plaintiff knew that the defendants required the well for the purpose of supplying water for their gold mining and milling operations. The counterclaim sets forth items constituting the alleged damages as follows:

“That as a direct and proximate result of plaintiff’s breach of contract, defendants sustained the following damages:
1. Cost of installing pump, motor and pipe line in the well on the property of a third person ... $1380.64
2. Additional cost of heavier pump.............$ 900.00
3. Cost of recapping abandoned holes ...........$ 200.00
4. Down payment.............................$1000.00
5. Loss of four months profit from gold mill operation ............................$12,000.00
all to defendants’ damage in the sum of $15,480.64.”

The cause was tried by the court sitting without a jury, and resulted in a judgment for the defendants on their counterclaim in the sum of $1,307.15, besides interest and costs.

The findings generally support the theory pleaded by the *722 defendants. The court expressly found that the allegations in the complaint as to the contract were not true, and that the averments in the answer relative to the agreement are true except with respect to damages, as to which it is held:

“That as a direct and proximate result of plaintiff’s breach of contract, defendants sustained the following damages:
1. Increased cost of Pump..........$1062.80
2. Electrical Work................ 290.15
3. Plastic & fittings........... 877.01
As set forth in defendants ’ Exhibit F:
1. Pumping plant panel & labor..... 208.62
2. One new #43 Hi Lift Stator only. 83.57
3. One Penn Control Switch........ 25.00
Total ...................................$2547.15
Less
1. Labor saved by using plastic pipe...........................$ 240.00
2. Balance on contract with plaintiff .......................$1000.00
Total..........................$1240.00 _
Defendants’ damages are the difference........$1307.15”

The evidence shows that Mr. Kennedy was an experienced water well driller carrying on his trade in the area; that he assured Mr. Reece that he was certain of getting an acceptable well and that there would be no trouble in reaching the 400-foot level contemplated by the written contract. However, the first hole drilled by the plaintiff, after being carried to a depth of 130 feet, was abandoned at the instance of the appellant because he claimed that he had struck hard rock. The plaintiff told Mr. Reece that he would move, without charging him any additional sum, to a new point on the land of a neighbor, if Mr. Reece would dig a sump hole at the proposed location and construct a passable roadway to the place where the well was to be drilled. The defendants accordingly secured permission to drill the well on the neighbor’s property, and the second hole was carried down to a depth of 270 feet; Mr. Kennedy claimed that he there struck the same hard formation, which he said was granite but which the evidence on behalf of the defendants showed was a relatively brittle rock that could be drilled through. Mr. Kennedy removed his equipment without any preliminary notice to defendants and left the area; he did not complete the well, and he did not insert any casing or cap either of the holes. No consent was given by Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fitness International v. KB Salt Lake III
California Court of Appeal, 2023
G. W. Andersen Construction Co. v. Mars Sales
164 Cal. App. 3d 326 (California Court of Appeal, 1985)
Kirkpatrick v. Temme
654 P.2d 1011 (Nevada Supreme Court, 1982)
Ellison v. City of San Buenaventura
48 Cal. App. 3d 952 (California Court of Appeal, 1975)
Avon Sheet Metal Co. v. HERITAGE HOUSE ASSOC.
259 A.2d 241 (New Jersey Superior Court App Division, 1969)
Kennedy v. Reece
240 Cal. App. 2d 769 (California Court of Appeal, 1966)
Bumby & Stimpson, Inc. v. Peninsula Utilities Corp.
169 So. 2d 499 (District Court of Appeal of Florida, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
225 Cal. App. 2d 717, 37 Cal. Rptr. 708, 1964 Cal. App. LEXIS 1423, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kennedy-v-reece-calctapp-1964.