Hein v. Fox

254 P.2d 1076, 126 Mont. 514, 1953 Mont. LEXIS 15
CourtMontana Supreme Court
DecidedMarch 23, 1953
Docket9109
StatusPublished
Cited by24 cases

This text of 254 P.2d 1076 (Hein v. Fox) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hein v. Fox, 254 P.2d 1076, 126 Mont. 514, 1953 Mont. LEXIS 15 (Mo. 1953).

Opinion

MR. JUSTICE FREEBOURN:

Clarence J. Hein sued John R. Fox for Fox’ failure to finish drilling a well for water as agreed under the terms of a written contract. Trial by jury resulted in a verdict for Hein for $1,000. A new trial was ordered in the district court and from such order Hein appeals.

The complaint alleges and the answer admits: That “on or about the 6th day of February, 1950, the plaintiff and defendant entered into an agreement, ’ ’ which was in writing and signed by plaintiff and defendant, “whereby the defendant agreed to drill and develop a well six (6) inches in diameter * * * on the plaintiff’s farm * * * That the defendant further agreed that he would * * * prosecute said drilling diligently and in workmanlike manner until final completion of said well. That the plaintiff * * * would pay the sum of Six Dollars and Fifty Cents ($6.50) per foot for the first 260 feet drilling, when easing was necessary as consideration for said defendant’s work.”

Defendant’s answer admits that Hein paid Fox “the sum of Sixteen Hundred Fifty and no/100 Dollars ($1650.00) to apply on said contract and the drilling of said well.” Fox’ answer shows that he drilled one well to a depth of 250 feet, “but it became necessary to abandon said hole and seal the same off, by reason of the fact that the casing became broke.” A second well was then commenced. Hein said Fox ‘ ‘ just moved the rig ahead three or four feet and started another one.” The second well was down 350 feet when the casing, according to the answer, “hit and struck a boulder” which ended all further drilling on Fox’ part.

According to the provisions of the written agreement and contract, Fox, the contractor, had to “perform all the work required for the drilling, developing and testing of a six inch diameter well.” The work had to be “prosecuted diligently * * * until final completion in full conformity with the provisions hereof,” such provisions requiring “the contractor shall *517 not test the well upon its completion. The test to be used will be the equivalent to pumping a constant flow of water by operation of the pump intended for the well for a period of one (1) week. ’ ’

From the evidence it is plain that Fox never completed a well as agreed upon in the written contract.

Under the evidence the jury could have found that he was prevented from completing the well by hard luck while drilling and inability to secure needed six-inch easing and that he intended sometime in the future to complete the well. On the other hand, the jury could find and apparently did find that Fox had abandoned the drilling of and never intended to complete such well. The verdict for Hein bears out this conclusion.

The lower court gave as its reason for granting a new trial that: “Clearly the complaint does not state facts sufficient to constitute a cause of action. In particular the contract sued on was not valid or binding for want of approval by the named agency. * * * The amount of $1000.00 awarded by the jury is not supported by a preponderance of the evidence.”

The words, “want of approval by the named agency,” have reference to that part of the contract providing that it “shall not be valid or binding on the parties hereto unless approved by the duly authorized representative of the State Director of the Farmers Home Administration, United States Department of Agriculture, unless otherwise determined by the State Director the person who will countersign checks of the owner payable under this agreement will be such authorized representative.” The two checks, covering the $1,650.00 paid by Hein to Fox were both countersigned by “R M. Sherick.”

The record shows that defendant by demurrer filed November 21, 1950, challenged the complaint upon the ground “that said complaint and the whole thereof does not state facts sufficient to constitute a cause of action.” This demurrer was overruled by the court on December 5, 1950.

Defendant again challenged the complaint by motion for non-suit, when plaintiff rested, one of the grounds of such motion *518 being “that the complaint and the whole of it fails to state facts sufficient to constitute a cause 'of action against the defendant * * * ” The motion for a non-suit was denied by the court.

These rulings upon demurrer and motion for non-suit indicate that the trial court upon these occasions believed the complaint did state facts sufficient to constitute a cause of action, although the complaint did not allege that the written contract between Hein and Fox had been approved by the named agency, the Farmers Home Administration, as provided for in the contract pleaded. By alleging that Hein had paid Fox $1,650 for drilling and that “defendant began drilling a well six (6) inches in diameter and worked part time on said well until the month of June 1950,” the complaint, upon its face, showed that the parties had waived the provision of the contract requiring approval thereof by the named agency. Evidence of plaintiff in his case in chief showing that Hein had paid Fox $1,650 for drilling and that Fox had drilled the two dry holes and supporting the allegations of the complaint constituted a waiver of such approval by the named agency.

This court finds no good reason justifying the action of the trial court in changing its ruling on the sufficiency of the complaint between the time the demurrer and motion for non-suit were ruled upon and the ruling thereon made upon motion for a new trial.

We look with disfavor upon the practice followed by the trial court here and recommend that if a trial court believes a complaint is subject to demurrer, proper ruling thereon should be made at the earliest possible stage of proceedings, so that the pleading may be amended, where feasible, thereby avoiding-wasted time, effort and expense.

The approval by the agency was a condition precedent to the actual carrying out of the contract and ceased to be such by reason of the waiver.

A waiver may be by mere voluntary expression of waiver and nearly always by continuing to render performance or by receiving further performance from the other party, with *519 knowledge that the condition has not been performed. 3 Corbin on Contracts, see. 755, p. 918.

Then, too, where a party enters into a contract knowing that permission of government officers will be required during the course of performance, that such permission was not forthcoming when required does not constitute an excuse for nonperformance. See: 17 C. J. S., Contracts, sec. 463, page 953; Standard Oil Co. of New York v. Central Dredging Co. 252 N. Y. 545, 170 N. E. 137.

In addition to asking damages in the amount of $1,650 paid, Hein pleaded special damages in the amount of $1,000 for having been “without water for his stock, milking parlor and water for domestic purposes.” According to Hein he obtained a license “to sell Grade A milk, on the strength of this well.” Grade A milk “sells for very near double what cheese milk sells for.” This license “was given me on the strength” of the well promised by Fox “and the water produced by it.” Because of no well hein lost “the Grade A license.”

R. C. M. 1947, sec.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Davidson v. Barstad
2019 MT 48 (Montana Supreme Court, 2019)
Moore v. Goran, LLC
2017 MT 208 (Montana Supreme Court, 2017)
Fisher v. State Farm Mutual Automobile Insurance
2013 MT 208 (Montana Supreme Court, 2013)
Reisbeck v. Farmers Insurance Exchange
2007 MT 171 (Montana Supreme Court, 2007)
Henderson v. Estate of Henderson
2002 MT 56N (Montana Supreme Court, 2002)
Marco & Co. v. Deaconess/Billings Clinic Health System
1998 MT 26 (Montana Supreme Court, 1998)
Maxted v. Barrett
643 P.2d 1161 (Montana Supreme Court, 1982)
Steinke v. Boeing Co.
525 F. Supp. 234 (D. Montana, 1981)
Smith v. Zepp
567 P.2d 923 (Montana Supreme Court, 1977)
Veterans Rehabilitation Center, Inc. v. Birrer
551 P.2d 1001 (Montana Supreme Court, 1976)
Duffy v. BUTTE TEACHERS'UNION, NUMBER 332
541 P.2d 1199 (Montana Supreme Court, 1975)
Palmquist v. ALLARDYCE PETROLEUM CORPORATION
520 P.2d 783 (Montana Supreme Court, 1974)
Hawkins v. First Federal Savings and Loan Ass'n
280 So. 2d 93 (Supreme Court of Alabama, 1973)
Heckman and Shell v. Wilson
487 P.2d 1141 (Montana Supreme Court, 1971)
Security Sewage Equipment Co. v. McFerren
237 N.E.2d 898 (Ohio Supreme Court, 1968)
Security Sewage Equipment Co. v. McFerren
230 N.E.2d 130 (Ohio Court of Appeals, 1967)
Kennedy v. Reece
225 Cal. App. 2d 717 (California Court of Appeal, 1964)
Northwest Oil & Refining Co. v. Honolulu Oil Corp.
195 F. Supp. 281 (D. Montana, 1961)
Tiedman v. American Pigment Corp.
253 F.2d 803 (Fourth Circuit, 1958)

Cite This Page — Counsel Stack

Bluebook (online)
254 P.2d 1076, 126 Mont. 514, 1953 Mont. LEXIS 15, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hein-v-fox-mont-1953.