Allen v. Gardner

272 P.2d 99, 126 Cal. App. 2d 335, 1954 Cal. App. LEXIS 2022
CourtCalifornia Court of Appeal
DecidedJune 30, 1954
DocketCiv. 15941
StatusPublished
Cited by30 cases

This text of 272 P.2d 99 (Allen v. Gardner) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Allen v. Gardner, 272 P.2d 99, 126 Cal. App. 2d 335, 1954 Cal. App. LEXIS 2022 (Cal. Ct. App. 1954).

Opinion

PETERS, P. J.

Mervin L. Gardner was awarded the principal contract to construct a school. The contract, among other things, required Gardner to furnish a specified quantity of specially designed concrete. This portion of the contract was subcontracted to the Fergusons, who agreed with Gardner to furnish the required concrete at $15.50 per cubic yard. After supplying a small quantity of the concrete, for which they were not fully paid, the Fergusons wrongfully breached *338 their contract, and refused to continue performance. Gardner was required to and did furnish the balance of the concrete required on the job. The trial court found that this concrete cost Gardner $43.02 a cubic yard. Damages were awarded to Gardner based on the difference between $15.50 per cubic yard, the price at which the Fergusons had agreed to furnish the concrete, and $43.02 per cubic yard, the cost to Gardner of the balance of the concrete. The Fergusons were adjudged entitled to an offset for the amount still owing them. So reduced, Gardner’s net damage was fixed at $54,237.87, and judgment entered in his favor for that amount. The Fergusons appeal from that judgment and from the order denying their motion for a new trial. * Appellants do not challenge the findings that they wrongfully breached the contract causing damage to Gardner, but direct their attack solely against the sufficiency of the evidence to sustain the findings as to the precise amount of damage.

The facts, more in detail, follow: Gardner, the cross-complainant, is a licensed contractor. He had a contract to construct a school for the Tahoe-Truekee Joint Unified School District. This contract required him to furnish 2,450 cubic yards of specially designed concrete. In May of 1950 the cross-defendants, collectively referred to herein as the Fergusons, contracted with Gardner to mix, prepare, furnish and deliver at the job site, all of the concrete called for by the main contract. The subcontract provided for a price of $15.50 per cubic yard, based on an estimate of six sacks of cement per cubic yard, with adjustments upward or downward dependent upon whether more or less cement was in fact required.

The Fergusons started performance under the contract, and supplied 374.75 cubic yards of concrete, but in October of 1950 they wrongfully breached the contract, and refused further performance. Gardner, thereupon, furnished the balance of the concrete. The court has found that he furnished 2,075.25 cubic yards of concrete, of which 1,147.65 cubic yards were poured under his direct supervision, and 927.6 cubic yards were poured by Lee H. Rovzar, a civil engineer, hired by Gardner for this purpose. Gardner kept no detailed records of the cost of the concrete poured by him, but Rovzar kept detailed records, which showed a total cost of $43.02 *339 per cubic yard for the concrete poured by him. Gardner testified that his costs were the same as Rovzar’s. The trial court accepted this figure as the cost to Gardner of the 2,075.25 cubic yards furnished by him, either directly or through Rovzar.

Gardner had not fully paid the Fergusons for the 374.75 cubic yards of concrete furnished by them, and refused to do so. Thereupon, the Fergusons, through an assignee, brought this action against Gardner for the balance owed to them. Gardner answered and cross-complained against the Fergusons to recover the damages incurred by the Fergusons’ breach of contract.

The causes were tried before the court without a jury. The court held that Gardner was entitled to damages against the Fergusons for the difference between the contract price of $15.50 per cubic yard, and the cost to Gardner of furnishing the concrete, fixed by the trial court at $43.02 per cubic yard, on 2,075.25 cubic yards. Thus, Gardner’s total damages were fixed at $57,110.88. The trial court also held that Gardner owed the Fergusons $2,873.01 for part of the concrete furnished by the Fergusons, which sum was offset against the claims of Gardner. So computed, the net damages to Gardner were fixed at $54,237.87. Judgment was entered against the Fergusons in this amount. It is from this judgment that the Fergusons appeal.

Appellants attack only the findings relating to the amount of damages found, contending that these findings are unsupported. As pointed out above, Rovzar’s cost computations were used to compute Gardner’s damages. Appellants' attack practically every major and some minor items contained in those computations. Their basic contention is that Gardner failed to prove the amount of his damages with the certainty required by law. They also contend that, even if Rovzar’s computations be accepted as to the 927.6 cubic yards of concrete poured by him, it was error to use those figures as the cost of the 1,147.65 cubic yards of concrete poured by Gardner. They also attack the finding that Gardner poured 1,147.65 cubic yards of concrete.

Most of these attacks of appellants relate to the method of proof used by Gardner to establish his damages. He produced Rovzar as his witness, who testified that his cost for the concrete poured by him was $43.02 per cubic yard. Rovzar supported this figure with detailed records of his costs. These *340 records, of course, referred only to the 927.6 cubic yards of concrete that he poured. Gardner, who had kept no records of the cost of the 1,147.65 cubic yards poured by him, testified that his costs were the same as those of Rovzar, that there was no difference in his labor costs, the cost of cement or aggregates, the cost of pouring, etc., and those of Rovzar. Gardner also testified that the school architect, during the course of the construction, ordered additional concrete work, and that for this supplementary concrete the school district was charged and paid $43.02 per cubic yard. The Fergusons contend that this was not a proper or sufficient way to prove damages insofar as the concrete directly poured by Gardner is concerned. In the absence of direct evidence of costs incurred by Gardner it is urged that there was a failure of proof on the issue.

Appellants have misconceived the law applicable to this situation. They stand before the court as violators of their contract. Their acts caused damage, serious damage, to Gardner. Those facts were proved definitely and with certainty. The law requires, and properly so, that the fact of damage be proved with reasonable certainty. (Civ. Code, § 3301.) Uncertainty as to the fact of damage, that is, as to the nature, existence or cause of the damage, is fatal. But the same certainty as to the amount of the damage is not required. An innocent party damaged by the acts of a contract violator will not be denied recovery simply because precise proof of the amount of damage is not available. The law only requires that some reasonable basis of computation be used, and will allow damages so computed even if the result reached is only an approximation. (See annotation commenting on cases from many states, 78 A.L.R. 858.)

These rules have frequently been applied in California. In Speegle v. Board of Fire Underwriters, 29 Cal.2d 34, 46 [172 P.2d 867], the California Supreme Court quoted the following with approval from Bigelow v. RKO Radio Pictures, Inc.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Waverly Kaffaga v. Thomas Steinbeck
938 F.3d 1006 (Ninth Circuit, 2019)
JMR Construction Corp. v. Environmental Assessment & Remediation Management, Inc.
243 Cal. App. 4th 571 (California Court of Appeal, 2015)
Mitsui O.S.K. Lines, Ltd. v. Seamaster Logistics, Inc.
618 F. App'x 304 (Ninth Circuit, 2015)
Scheenstra v. California Dairies, Inc.
213 Cal. App. 4th 370 (California Court of Appeal, 2013)
Beasley v. Wells Fargo Bank
235 Cal. App. 3d 1383 (California Court of Appeal, 1991)
DuBarry International, Inc. v. Southwest Forest Industries, Inc.
231 Cal. App. 3d 552 (California Court of Appeal, 1991)
GHK Associates v. Mayer Group, Inc.
224 Cal. App. 3d 856 (California Court of Appeal, 1990)
Berg v. First State Insurance
915 F.2d 460 (Ninth Circuit, 1990)
R.P. Porter International, Inc. v. Pacific International Engineering, Ltd.
12 Am. Samoa 2d 48 (High Court of American Samoa, 1989)
Suburban Mobile Homes, Inc. v. AMFAC Communities, Inc.
101 Cal. App. 3d 532 (California Court of Appeal, 1980)
Guntert v. City of Stockton
55 Cal. App. 3d 131 (California Court of Appeal, 1976)
Davies v. Krasna
535 P.2d 1161 (California Supreme Court, 1975)
Distribu-Dor, Inc. v. Karadanis
11 Cal. App. 3d 463 (California Court of Appeal, 1970)
A. A. Baxter Corp. v. Colt Industries, Inc.
10 Cal. App. 3d 144 (California Court of Appeal, 1970)
Warner Construction Corp. v. City of Los Angeles
466 P.2d 996 (California Supreme Court, 1970)
Page v. Bakersfield Uniform & Towel Supply Co.
239 Cal. App. 2d 762 (California Court of Appeal, 1966)
Fairlane Estates, Inc. v. Carrico Construction Co.
228 Cal. App. 2d 65 (California Court of Appeal, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
272 P.2d 99, 126 Cal. App. 2d 335, 1954 Cal. App. LEXIS 2022, Counsel Stack Legal Research, https://law.counselstack.com/opinion/allen-v-gardner-calctapp-1954.