City of Kennett v. Katz Construction Co.

202 S.W. 558, 273 Mo. 279, 1918 Mo. LEXIS 153
CourtSupreme Court of Missouri
DecidedFebruary 16, 1918
StatusPublished
Cited by44 cases

This text of 202 S.W. 558 (City of Kennett v. Katz Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Kennett v. Katz Construction Co., 202 S.W. 558, 273 Mo. 279, 1918 Mo. LEXIS 153 (Mo. 1918).

Opinion

WALKER, P. J.

This is an appeal from an order granting a new trial. The appellant, the city of Kennett, to be designated herein as the city, brought suit in the circuit court of Dunklin County against the Katz Construction Company and the American Surety Company, to be designated herein respectively as the contractor and the surety company, each a corporation, upon a bond for $18,000 of the former as principal and the latter as surety, given to the city to insure the faithful performance of a contract for furnishing the necessary materials and labor to construct certain lines of sewers in the streets and alleys of the city and for the performance of other work incident thereto and necessary to facilitate the disposal of sewage, for which the contractor was to' be paid a total sum of $35,204.06, in the amounts and at the times stated in the contract; and which contract it was alleged had been breached by the contractor. The surety company filed its separate answer. The city dismissed as to the contractor. A [285]*285change of venue was granted on the application of the surety company to Bollinger County where, upon a trial, a verdict was rendered for the city in the sum of eighteen thousand dollars. A motion for a new trial was sustained, unless the city would enter a remittitur. This it refused to do, and perfected its appeal to this court.

The contract and bond on which this action is based contains among other provisions, the following:

“And it is hereby expressly agreed by and between all parties thereto that no extension of time, or alteration in, addition to, or omissions from the work provided for under said contract, plans and specifications, although without consent of said surety, shall violate this bond or discharge said surety. . . .
“Upon request of the contractor, the engineer will, upon or about the first of each month, make an estimate of work done and material delivered for the previous month, and payment will then he made by the council for ninety per cent of said estimate.”

The contract also provided that the work should be completed within nine months after its execution, which was in April, 1913, and for each day’s delay the contractor should pay $5 per day as liquidated damages. Thereupon the contractor commenced work under the contract. Subsequently certain changes were made in the plans and specifications at the request of the contractor. According to the testimony of expert engineers these changes did not increase the cost of construction or entail a delay in the work.

The work progressed under the contract until September 1, 1914. During this time thirteen estimates were rendered by the contractor to the city, aggregating $32,436.86. Of this amount ten per cent was withheld in accordance with the contract to be paid upon the completion and acceptance of the work, and the contractor was paid the difference, to-wit, $29,193.17, less $645 held by the city for delays in the work, which constituted the aggregate up to that time of the penalty therefor of $5 per day as prescribed in the contract. [286]*286Thereafter estimate number 14 was rendered for work performed during the month of September, 1914, and the contractor was informed that the city was temporarily out of funds necessary to pay that estimate. The contractor then agreed that if the city would pay six per cent interest on the amount due, it would carry, the warrant and proceed with the work, whereupon the warrant was issued for estimate number 14 and delivered to it, and same was later paid with interest thereon. Thereafter estimate number 15 for work performed during the month of October, 1914, was rendered by the contractor to the city, and was settled in the same manner as estimate number 14.

After the delivery by the city of its warrant to the contractor in payment of estimate number 15 and the acceptance of same by it, owing to the amount of water in the ground where the sewers were being constructed, it was mutually agreed that work on the system should be suspended until such time as it was practicable to resume operations. At the time this agreement was entered into the contractor had been paid for all work then performed.

The total estimate to this date for work performed amounted to the sum of $34,400.15. The amount paid to the contractor was $30,960.14. The difference between the total estimates for work performed and the amount paid the contractor was $4,390.01, $950 of same being the aggregate penalty for delays occasioned by the contractor, and the balance, $3,440.01, being the amount, ten per cent, authorized to be withheld until the completion of the work.

Conditions thereafter permitting that work be resumed, the city notified the contractor to proceed to complete the work and that funds were available for its payment. At that time the city had available the sum of $6100, for the payment of this work, or more than the balance due the contractor under its bid. The contractor refused to perform any more work under the contract. Whereupon the city gave notice to the surety company, as surety on the contractor’s bond, of the [287]*287abandonment by tbe latter of its contract and requested tbe surety company to complete the work. This it failed and refused to do. Whereupon the city entered into another contract with one A. O. Brown, in an endeavor to effect the completion of the sewer system in accordance with the original plans and specifications and the changes made at the request of the contractor, in which undertaking the city agreed to pay not exceeding $6100 for the completion of the work, and it expended this sum in that behalf, which was found not sufficient for the purpose. Thereupon this suit was brought to recover on the bond with the result stated. At the trial experts testified it would require an expenditure of $18,000 to $20,000, in addition to all former sums paid out by the city in that behalf, to complete the sewer system in accordance with the original specifications and the changes made. The jury returned a verdict in favor of the city and against the surety company in the sum of $18,000; the city having, as stated, theretofore dismissed the action against the contractor. A motion for a new trial was sustained on the ground, as stated in the order therefor, that the city had refused to enter a remittitur, but as disclosed by the record that the trial court had erred in not instructing the jury that the right of recovery should have been limited to $6,100, that being the amount the city had expended in attempting to complete the sewer system. Other conditions of the contract, facts in evidence, and actions of the trial court, will, if necessary for the proper understanding of the case and the determination of the issues, be set out in the opinion.

Review on nueriociitory order. I. The general rule as to the extent to which this court will review a record upon an appeal from an interlocutory order, as in the instant case, is as follows: When an order for' a new trial is granted for a specific reason, the appellant assumes no other burden of showing error than that which prompted the trial court’s action. If other grounds are relied on to sustain the order, which have been preserved in the record, the [288]*288respondent must call the appellate court’s attention to same or they will not be considered. [State ex rel. Bank v. Ellison, 266 Mo. l. c. 432; Benjamin v. Railroad, 245 Mo. l. c. 609; Emmons v. Quade, 176 Mo. l. c. 27; Millar v. Madison Car Co., 130 Mo. 523.]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Harvey v. Timber Resources, Inc.
37 S.W.3d 814 (Missouri Court of Appeals, 2001)
Murphy v. City of Springfield
794 S.W.2d 275 (Missouri Court of Appeals, 1990)
Ideker, Inc. v. Missouri State Highway Commission
654 S.W.2d 617 (Missouri Court of Appeals, 1983)
Richardson v. Volkswagenwerk, A.G.
552 F. Supp. 73 (W.D. Missouri, 1982)
Graeff Ex Rel. Graeff v. Baptist Temple of Springfield
576 S.W.2d 291 (Supreme Court of Missouri, 1978)
Hoehn v. Hampton
483 S.W.2d 403 (Missouri Court of Appeals, 1972)
Mills v. Murray
472 S.W.2d 6 (Missouri Court of Appeals, 1971)
Denton Construction Co. v. Missouri State Highway Commission
454 S.W.2d 44 (Supreme Court of Missouri, 1970)
State Ex Rel. State Highway Commission v. Thurman
428 S.W.2d 955 (Missouri Court of Appeals, 1968)
Bomson v. Electra Mfg. Co.
402 S.W.2d 7 (Missouri Court of Appeals, 1966)
Kirst v. Clarkson Construction Company
395 S.W.2d 487 (Missouri Court of Appeals, 1965)
Stephens v. Henningsen, Inc.
358 S.W.2d 450 (Missouri Court of Appeals, 1962)
Overton Ex Rel. Overton v. Tesson
355 S.W.2d 909 (Supreme Court of Missouri, 1962)
Shechter v. Brewer
344 S.W.2d 784 (Missouri Court of Appeals, 1961)
Brader v. Rehm
323 S.W.2d 392 (Missouri Court of Appeals, 1959)
Blackburn v. Carlson Seed Company
321 S.W.2d 520 (Missouri Court of Appeals, 1959)
Milton v. Hudson Sales Corp.
313 P.2d 936 (California Court of Appeal, 1957)
Moore v. St. Louis Southwestern Railway Company
301 S.W.2d 395 (Missouri Court of Appeals, 1957)
Allen v. Gardner
272 P.2d 99 (California Court of Appeal, 1954)
Johnson v. St. Louis Public Service Co.
256 S.W.2d 308 (Missouri Court of Appeals, 1953)

Cite This Page — Counsel Stack

Bluebook (online)
202 S.W. 558, 273 Mo. 279, 1918 Mo. LEXIS 153, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-kennett-v-katz-construction-co-mo-1918.