Prescott National Bank v. Head

90 P. 328, 11 Ariz. 213, 1907 Ariz. LEXIS 90
CourtArizona Supreme Court
DecidedMarch 25, 1907
DocketCivil No. 992
StatusPublished
Cited by8 cases

This text of 90 P. 328 (Prescott National Bank v. Head) is published on Counsel Stack Legal Research, covering Arizona Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Prescott National Bank v. Head, 90 P. 328, 11 Ariz. 213, 1907 Ariz. LEXIS 90 (Ark. 1907).

Opinion

NAVE, J.

— Prior to the hearing of this case upon its merits, a motion filed by appellee to strike from the record the transcript of the reporter’s notes was denied; as was also a motion by appellee to dismiss the appeal. These motions raised a question of practice which has not heretofore-been the subject of a formal expression of our opinion. The judgment of the district court in this cause was rendered during the May term of the year 1905. Within that. [217]*217term a motion for a new trial was filed by appellant. By formal order, action upon this motion was continued for the term. Again at the November term there was a formal continuance of the motion. It was denied at the May term, 1906; whereupon appellant gave notice of appeal, and during that term caused to be made and filed a transcript of the reporter’s notes of the oral testimony.

Paragraph I486 of the Civil Code permits the oral testimony given in a case to be made a part of the record by filing a transcript of the court reporter’s notes. The statute does not expressly prescribe the time within which such transcript shall be filed. By the rules of this court, it is provided that the transcript, in order to become a part of the record, must be filed during the term in which the judgment was rendered, or within such reasonable time thereafter as shall be allowed by the court or the judge thereof. No extension of time was allowed. It was contended by the appellee that the reporter’s transcript should be stricken from the record by reason of the fact that it was not filed within the term at which judgment in the cause was rendered. By paragraph 1496 of the Civil Code it is provided that an appeal may be taken “during the term of the court at which final judgment or order is rendered” by the giving of notice of appeal in open court. The notice of appeal, as above stated, was given after the overruling of the motion for new trial at a term subsequent to that at which judgment was rendered. Upon this the appellee based his motion to dismiss the appeal. Our construction of our rule in regard to filing the reporter’s transcript and of paragraph 1496 is that for these purposes the term at which the judgment is rendered is the term at which the judgment becomes final by the overruling of a motion for a new trial. A different construction would lead to a palpable absurdity.

Appellant has made thirty-five assignments of error. Of these assignments the second to sixth, inclusive, the twelfth, and the twenty-first to thirty-fifth, inclusive, are too general for consideration. They are of the same character as those which were refused consideration in Ward v. Sherman, 7 Ariz. 277, 64 Pac. 434; Charouleau v. Shields, 9 Ariz. 73, 76 Pac. 821, and Daniel v. Gallagher, ante, p. 151, 89 Pac. 412. By the remaining assignments of error several matters are raised which we may properly consider.

[218]*218The facts in the ease are as follows: One Grant contracted to construct a building for the Prescott National Bank, the appellant in this case. A. J. Head, the appellee, was one of two sureties upon a joint and several indemnity bond given by the contractor to the bank. Head sold material to the contractor for the construction of the building. The material not having been paid for in full, Head perfected a lien npon the property for the unpaid balance. This is a suit by Head against the bank to foreclose this lien, and also the lien of another materialman which had been assigned to him. The bank answered setting forth the indemnity bond given to it by the contractor, and pleaded that Head, by reason of his obligation as surety thereon, is estopped from maintaining the action to foreclose these liens. Furthermore, the bank filed a counterclaim, setting up the indemnity bond, and demanding from Plead the payment of the amounts of liens paid by the bank to other persons, and of an amount expended by the bank to complete the building after abandonment of the work by the contractor. The trial court made findings of fact, which need not here be set forth, except to note a finding that certain alterations had been made in the work shown by the specifications without written orders of the supervising architect; the contract providing that no alteration shall be made except upon the written “order of the architect.” Upon these findings the trial court predicated, among others, the following conclusions of law: “(1) That the written contract made between said Grant and the Prescott National Bank is sufficiently referred to in said bond, and that a breach of said contract by failure to pay lien claims is a breach of said bond, and is covered by the conditions of said bond. (2) That primarily the plaintiff, being a surety on said bond, was estopped from enforcing a lien on said property, and that by said written notice to bring suit and failure to do so, plaintiff was released from liability upon said bond for lien claims filed by third parties and for the cost of completing said building, but was not, for that reason, relieved from the effect of the estoppel against enforcing his liens. (3) That by the making of such changes and alterations, without the written order of the architect, and without the knowledge of the plaintiff that they had been so made, plaintiff was released from all liability on said bond, or upon the counterclaim filed herein, and is not estopped from maintaining and enforcing his said liens upon said prop[219]*219erty.” The proper determination of this appeal is to be reached by a consideration of the soundness of these conclusions.

1. The condition of the indemnity bond is as follows: “The condition of the above obligation is such that, whereas, the above A. Grant has this day contracted and agreed with the said Prescott National Bank to furnish all the. labor and material necessary to construct in good, substantial and workmanlike manner a two-story brick and stone building on the west half of lot 24, in block 9, in the city of Prescott, Arizona. Work to be done in strict accordance with the plans, specifications and a contract, executed between the above parties, bearing even date with this. Said contract is made a part of this bond, and to which reference is made for a more complete description of the terms and conditions of the same. The express condition of the above obligation is that said A. Grant shall finish .the above work on or before the first day of July, 1901, as per contract. Then this obligation to be void and of no effect; otherwise to remain in full force and virtue.” The contract requires that the contractor shall provide the material and perform all work mentioned in the specifications and as shown in the architect’s drawings for the proper erection and construction of the building. It provides, further, that, if at any time there should be evidence of any lien or lienable claims, the owner should have the right to retain out of any payments then due an amount sufficient to indemnify him against such lien or claims; and, should there be any such claim after the payments are made, the contractor should refund to the owner moneys that the latter may be compelled to pay in discharging them. The “express condition” of the bond is brief indeed — that the contractor shall finish his work by a certain date “as per contract.” To finish the work “as per contract,” the contractor must furnish the materials. If he has placed the materials in the building without paying for them, and thereby has brought about the charging of the materials upon the owner by means of the materialman’s lien, he has not furnished the material within the meaning of his contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tucson House Construction Co. v. Fulford
378 F.2d 734 (Ninth Circuit, 1967)
Tucson House Construction Company v. Fulford
378 F.2d 734 (Ninth Circuit, 1967)
Parmelee v. Chicago Eye Shield Co.
157 F.2d 582 (Eighth Circuit, 1946)
City of Kennett v. Katz Construction Co.
202 S.W. 558 (Supreme Court of Missouri, 1918)
Milavetz v. Oberg
164 N.W. 910 (Supreme Court of Minnesota, 1917)
Hardiker v. Rice
94 P. 1094 (Arizona Supreme Court, 1908)
Liberty Mining & Smelting Co. v. Geddes
90 P. 332 (Arizona Supreme Court, 1907)
Kinsley v. New Vulture Mining Co.
90 P. 438 (Arizona Supreme Court, 1907)

Cite This Page — Counsel Stack

Bluebook (online)
90 P. 328, 11 Ariz. 213, 1907 Ariz. LEXIS 90, Counsel Stack Legal Research, https://law.counselstack.com/opinion/prescott-national-bank-v-head-ariz-1907.