JMR Construction Corp. v. Environmental Assessment & Remediation Management, Inc.

243 Cal. App. 4th 571, 198 Cal. Rptr. 3d 47, 2015 Cal. App. LEXIS 1172
CourtCalifornia Court of Appeal
DecidedDecember 30, 2015
DocketH039055
StatusPublished
Cited by32 cases

This text of 243 Cal. App. 4th 571 (JMR Construction Corp. v. Environmental Assessment & Remediation Management, Inc.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
JMR Construction Corp. v. Environmental Assessment & Remediation Management, Inc., 243 Cal. App. 4th 571, 198 Cal. Rptr. 3d 47, 2015 Cal. App. LEXIS 1172 (Cal. Ct. App. 2015).

Opinion

Opinion

MÁRQUEZ, J.

— This dispute arose from a public works project involving the construction of a dental clinic at the Presidio of Monterey (the Project). The owner, the United States Army Corps of Engineers (the Corps), retained JMR Construction Corp. (JMR) as general contractor for the Project. JMR, in turn, entered into various subcontracts, including separate electrical and plumbing subcontracts, with Environmental Assessment and Remediation Management, Inc. (EAR). SureTec Insurance Company (SureTec) issued separate bonds guaranteeing EAR’S performance under the two subcontracts.

While the Project was ongoing, JMR (1) communicated with EAR about alleged delays, deficient and late submittals, and improper plumbing work, and (2) retained certain funds otherwise due to EAR under the subcontracts. After the Project was completed, JMR filed suit against EAR and SureTec (collectively, defendants) for breach of contract and for foreclosure of the performance bonds. JMR alleged it was damaged as a result of EAR’s failure to perform under the two subcontracts. EAR filed a cross-complaint for recovery of retention funds withheld under the subcontracts.

After a court trial, JMR was awarded the net amount of $315,631, which included an offset for the retention funds JMR withheld under the subcontracts. In posttrial proceedings, the court issued an order determining JMR *577 was entitled to recover attorney fees in an amount to be determined for its successful defense of the cross-complaint. The court also awarded JMR $90,644.07 in expert witness fees pursuant to Code of Civil Procedure section 998 1 by concluding that JMR’s total monetary recovery ($315,631 plus an undetermined amount of attorney fees) had exceeded the $375,000 amount of its pretrial settlement offers. SureTec and EAR filed separate appeals.

EAR makes seven arguments on appeal. First, it asserts there was no substantial evidence to support the trial court’s finding it was liable to JMR for delays on the Project. Second, it argues the court erred by using the Eichleay method of calculating extended home office overhead damages. Third, it asserts the court erred by utilizing the modified total cost method of calculating disruption and delay damages. Fourth, it argues the court, in its statement of decision, failed to address essential matters of fact and law. Fifth, it contends the court erred in determining JMR was entitled to attorney fees in defending the cross-complaint. Sixth, it asserts JMR was not entitled to recover its expert witness fees pursuant to section 998. And seventh, it contends the court erred by denying its motion for new trial.

SureTec contends JMR cannot prevail against SureTec because JMR failed to declare EAR in default under the subcontracts, and JMR failed to notify SureTec of any such default. It also contends the order finding JMR entitled to attorney fees on EAR’S cross-complaint was improper as to SureTec. Further, it contests the award to JMR of expert witness fees under section 998. And it argues that SureTec’s liability must be limited to a maximum of $471,881, the ceiling of its liability under the performance bond on the plumbing subcontract.

In the published portion of this opinion, we conclude the court did not err in its utilization of the Eichleay method to calculate extended home office overhead damages and in its use of the modified total cost method of calculating JMR’s disruption and delay damages. We also hold the court did not err in finding SureTec liable under the performance bonds, concluding that neither JMR’s formal declaration of EAR’S default nor its formal notice to SureTec of EAR’S default was a condition precedent to JMR’s recovery under the bonds. In the unpublished portion of this opinion, we conclude (1) there was substantial evidence supporting the court’s finding that EAR was liable to JMR for Project delays; (2) the court’s statement of decision was not defective; (3) defendants’ challenges to the interim, nonfinal, postjudgment order determining that JMR was entitled to recover attorney fees in defending the cross-complaint are not cognizable at this time; (4) defendants’ challenges to the award of JMR’s expert witness fees under section 998 are meritorious; (5) EAR’S claim that the court abused its discretion in denying EAR’S motion *578 for new trial has no merit; and (6) SureTec’s request for an order that its maximum liability is $471,881 is not cognizable because it is a request for an advisory opinion. Accordingly we will affirm the judgment, reverse the order awarding expert witness fees, and remand the case for further postjudgment proceedings consistent with this opinion.

PROCEDURAL BACKGROUND

On April 29, 2010, JMR filed its complaint against EAR and SureTec. JMR alleged four causes of action: (1) breach of the plumbing subcontract; (2) enforcement and foreclosure on the performance bond for the plumbing subcontract; (3) breach of the electrical subcontract; and (4) enforcement and foreclosure on the performance bond for the electrical subcontract. The first and third causes of action were alleged against EAR, while the second and fourth causes of action were alleged against SureTec. 2 JMR alleged that EAR’S failure or refusal to perform its work under the two subcontracts in accordance with the Project’s schedule “caused project delay, acceleration, and related damages to JMR.” The alleged damages included “offset of JMR claims against the Owner, increased cost of JMR on-site performance costs and other loss of cost recovery and overhead on the Project.” In each of the four causes of action, JMR claimed its damages were in an amount “not less than $200,000.00.”

EAR filed a cross-complaint against JMR alleging breach of contract and common counts. It alleged in separate causes of action that JMR had breached the electrical subcontract and plumbing subcontract, and that as a result of these breaches, EAR had been damaged in an amount in excess of $108,913.31.

A five-day court trial took place in January 2012. After the parties submitted posttrial briefs in lieu of final argument, the court issued a ruling on April 30, 2012, finding in favor of JMR in the total amount of $379,318, which amount included a deduction of $121,893 that had been previously withheld from EAR under the subcontracts. The court further ordered that EAR take nothing on its cross-complaint.

Pursuant to the court’s request, JMR submitted a proposed statement of decision in which it withdrew one of its claims and adjusted the amount of another claim, resulting in revised damages award of $315,631. The damages were derived by (1) adding five damage figures in amounts of $29,249 (air *579 compressor), $132,168 (field overhead for delay), $15,440 (field overhead for Project closeout), $14,244 (markup for field overhead), $60,693 {Eichleay home office overhead), and $185,730 (damages during framing and drywall phase) and (2) subtracting from this amount $121,893 previously withheld under the subcontracts. On July 19, 2012, the court signed the statement of decision. On August 14, 2012, the court entered judgment in favor of JMR and against defendants in the amount of $315,631.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Duboff v. Schermer CA2/3
California Court of Appeal, 2026
Evleshin v. Meyer
California Court of Appeal, 2025
Patz v. City of San Diego
California Court of Appeal, 2025
Patz v. City of S.D.
California Court of Appeal, 2025
Blumberg v. Stroma Medical Corp. CA4/3
California Court of Appeal, 2025
Restoration Management Co. v. Lee CA1/2
California Court of Appeal, 2025
338 South Avenue 16 v. Meyer CA2/5
California Court of Appeal, 2024
Coziahr v. Otay Wat. Dist.
California Court of Appeal, 2024
Fromm v. Wells Fargo Bank CA2/5
California Court of Appeal, 2024
In re: Alex A. Khadavi
Ninth Circuit, 2023
Yoon v. Kim CA2/2
California Court of Appeal, 2023
Scrapit v. Del Angel Recycling Corp. CA2/1
California Court of Appeal, 2023
Pesic Zouves Fertility Center CA6
California Court of Appeal, 2022

Cite This Page — Counsel Stack

Bluebook (online)
243 Cal. App. 4th 571, 198 Cal. Rptr. 3d 47, 2015 Cal. App. LEXIS 1172, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jmr-construction-corp-v-environmental-assessment-remediation-calctapp-2015.