Pacific Allied v. Century Steel Products, Inc.

327 P.2d 547, 162 Cal. App. 2d 70, 1958 Cal. App. LEXIS 1831
CourtCalifornia Court of Appeal
DecidedJuly 10, 1958
DocketCiv. 22931
StatusPublished
Cited by9 cases

This text of 327 P.2d 547 (Pacific Allied v. Century Steel Products, Inc.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pacific Allied v. Century Steel Products, Inc., 327 P.2d 547, 162 Cal. App. 2d 70, 1958 Cal. App. LEXIS 1831 (Cal. Ct. App. 1958).

Opinion

LILLIE, J.

On April 17, 1954, the parties entered into a “Purchase Agreement,” whereby defendant agreed to build for plaintiff certain steel forms for storm drain construction. *73 A controversy arose over the guarantee therein, whereby defendant agreed to reimburse plaintiff for labor costs over a specified minimum. Plaintiff sued to recover excess labor costs of $3,304.31. The case was heard by the court without a jury and, after deducting certain amounts, the court rendered its judgment for $2,982.96. Defendant appeals therefrom and from the order denying its motion for new trial.

Viewing the evidence in the light most favorable to respondent, the following is a brief summary of the pertinent facts. At the insistence of defendant corporation, manufacturer of steel forms, plaintiff corporation, engaged in storm drain construction, agreed to try its forms if defendant would guarantee that as a result of their use plaintiff’s labor costs per square foot would not exceed four cents. The following guarantee was included in the purchase agreement:

“Item. 6 This entire purchase agreement is based upon the sellers guarantee that these forms and carrier when used by the buyer to complete that part of the reinforced concrete box conduit section of the Alameda-Toluea Park Storm Drain, Projects 166 and 167 for which they are designed and intended, will not exceed four cents per square foot (labor only) to place, strip and move the form of the exposed inside concrete surface. It being further mutually understood and agreed that the final cost of these forms and carrier to the buyer will be based upon actual labor costs per foot, a continuous report of which will be furnished the seller. It being understood that the moving of these forms will be done in accordance with the directions and guidance of the seller as initially set up, thereby satisfying the seller with the field methods employed so as to assure the most favorable results from a cost standpoint.
“Item. 9 While it is provided under Item 5 that the total price to be paid at time of delivery is $10,900.00, it is further and definitely understood and agreed that as is provided under Item 6 should the labor cost as defined therein, total more than four cents per squareft, (sic) the seller will immediately upon completion of the job and upon an itemized cost breakdown being submitted by the buyer, return to the buyer sufficient money to result in a total cost to the buyer on the direct labor involved for moving and setting forms of four cents per square foot.”

Prior to the execution of the contract McDonald, president of plaintiff, advised Fritz, president, and Schaper, vice presi *74 dent, of defendant, that a complete breakdown of cost would be kept on the work and explained its method of keeping costs, daily record, and posting to the weekly record against the item and the quantity of work done. He showed Sehaper the books and the method of keeping time cards and the distribution of items on the total job, of which Sehaper approved ; and advised him the records would be available to defendant at any time.

Plaintiff commenced work with defendant’s forms May 6, 1954. McDonald and Clark of plaintiff corporation were on the job daily. There was a constant communication between plaintiff and defendant during this time and they were in touch with each other almost every day. Prom the beginning, plaintiff kept a daily account of costs of that part of the job involving labor to “place, strip and move” the forms, being designated on its books and records as “8-4.” Daily time cards (Exhibit No. 5) showing dates, hours worked and names and number of men working on “8-4” were also kept. A compilation (Exhibit No. 4) taken from the books and records of plaintiff shows the time and money involved on “8-4,” dates of entries, locations of sections worked, square footage worked each day, total square footage and labor costs to each date and unit costs.

The work was finished August 13, 1954. On September 7th plaintiff wrote a letter to defendant demanding $3,304.31 excess labor costs, to which was attached the following “State- • ment of Cost ’ ’:

“Statement covering use of steel forms as provided for under purchase agreement between Century Steel Products, Inc., and Pacific Allied dated April 17, 1945:
63,677 sq. ft. contact surface area
.$ . .04 per sq. ft. as specified in agreement.
$2,547.08 total cost @ 4e per sq. ft.
$5,851.39 total actual labor cost to place, strip, and move steel forms.
$2,547.08 total cost @ 4c per sq. ft.
$3,304.31 excess cost as covered by letter of transmittal.”

Defendant refused to pay the amount and this action resulted.

The trial court made detailed findings of fact and concluded that plaintiff substantially performed all obligations to be *75 performed by it under the agreement and that strict compliance with the provisions relating to following directions and submission of an itemized cost breakdown were waived by the actions of the defendant.

Although objecting to specific findings as contrary to the evidence and law, appellant’s basic contention is that the provisions in the agreement referring to a “continuous report” and “itemized cost breakdown” must be strictly construed and constitute conditions precedent to recovery.

In determining the sufficiency of evidence to sustain questioned findings, an appellate court must accept as true all evidence tending to establish the correctness of the findings made, taking into account all inferences which might reasonably have been thought by the trial court to lead to the same conclusion and every substantial conflict in the testimony is to be resolved in their favor. (Burke v. Chrostowski, 46 Cal.2d 444 [296 P.2d 545]; McCarthy v. Tally, 46 Cal.2d 577 [297 P.2d 981]; McCreary v. Mercury Lumber Distributors, 124 Cal.App.2d 477 [268 P.2d 762].)

Appellant contends that the trial court’s finding that no certain instructions as to placing, stripping and moving the forms were given plaintiff by defendant and that such as were given were followed; and its conclusion that strict com-, pliance with any provision in reference thereto was waived by the action of defendant, were contrary to the evidence.

We find no error in the trial court’s finding or conclusion. There is nothing in the agreement requiring plaintiff to follow instructions in placing and stripping the forms. Item 6 refers only to moving: “It being understood that the moving of these forms will be done in accordance with the directions and guidance of the seller as initially set up. ...” The evidence discloses that no particular directions for moving were initially given by defendant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ticketmaster L.L.C. v. Prestige Entm't, Inc.
306 F. Supp. 3d 1164 (C.D. California, 2018)
Zawtocki v. Black Angus Steakhouses CA4/2
California Court of Appeal, 2016
JMR Construction Corp. v. Environmental Assessment & Remediation Management, Inc.
243 Cal. App. 4th 571 (California Court of Appeal, 2015)
1st Olympic Corp. v. Hawryluk
185 Cal. App. 2d 832 (California Court of Appeal, 1960)
Patrick J. Ruane, Inc. v. Parker
185 Cal. App. 2d 488 (California Court of Appeal, 1960)
Jozovich v. Central California Berry Growers Assn.
183 Cal. App. 2d 216 (California Court of Appeal, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
327 P.2d 547, 162 Cal. App. 2d 70, 1958 Cal. App. LEXIS 1831, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pacific-allied-v-century-steel-products-inc-calctapp-1958.