Thomas Haverty Co. v. Jones

197 P. 105, 185 Cal. 285, 1921 Cal. LEXIS 544
CourtCalifornia Supreme Court
DecidedMarch 14, 1921
DocketL. A. No. 5711.
StatusPublished
Cited by43 cases

This text of 197 P. 105 (Thomas Haverty Co. v. Jones) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thomas Haverty Co. v. Jones, 197 P. 105, 185 Cal. 285, 1921 Cal. LEXIS 544 (Cal. 1921).

Opinion

SHAW, J.

The defendant appeals from the judgment and also from an order made after judgment denying his motion to set aside the judgment and render a judgment in his favor on the findings.

The complaint states a cause of action to recover the balance alleged to be due from defendant to plaintiff upon a contract for the construction of the plumbing, steam-heating, and ventilation plant in a four-story building erected by the defendant. The answer admitted the making of the contract, but denied that the same had been fully performed by the plaintiff, and also alleged that the performance was defective in many particulars, whereby he was damaged in a large sum of money, exceeding the amount claimed by the plaintiff, and also that certain damages had been caused to the building by the carelessness of the plaintiff in doing the work called for by the contract, whereby he was also damaged. He asked judgment for the amount of damages claimed in his answer. The same matters were also set up in a separate pleading designated as a cross-complaint.

The court found that the plaintiff had performed the work called for by the contract, except in certain particulars set forth at length in the findings, concerning which the court found that the specifications included in the contract were not directly followed. As to nine of these particulars the court found that the omissions could be remedied at a cost amounting in all to $99.21. With respect to certain other defects, the court found that they could not be rem *288 edied without a greater expense than their importance would justify, but that the resulting damage to the building amounted to only $2,180.88. With respect to these failures to fully perform the contract the court further found that they were not done willfully or fraudulently, but that the same were due to mistakes and misinterpretations of the contract by the plaintiff’s employees, or because the deviations from the specifications were believed to be necessary for the proper construction of the work * and beneficial to the defendant; that there was a substantial performance of the contract, and that the difference in value to the defendant by the failure in full performance and the damages caused thereby could be compensated by a deduction from the contract price. It also found that in the course of construction certain workmen of the plaintiff, without its orders, partially cut through some cantilevers in the basement of the building, and that the same could be repaired at an expense of $650.78. The balance due to the plaintiff upon the contract price, including the charges for extras furnished in pursuance of a provision of the contract, after deducting certain omissions which were agreed to, certain labor performed by the defendant himself, and the payments made by him before the beginning of the action, amounted to $10,775.64. From this sum the court deducted the sum allowed for the remediable defects, as aforesaid, the damages amounting to $2,180.88 arising from the irremediable defects, and $650.78, allowed for the cost of repairing the cantilevers, amounting in all to $2,930.87, leaving a balance of $7,844.77, for which sum judgment was rendered in favor of the plaintiff.

The principal point presented in the case is the question of the right of a building contractor to recover the contract price where he has not completely performed the contract. The law in this state on this subject has been considered in several recent decisions and is now comparatively well established.

The general rule on the subject of performance is that “Where a person agrees to do a thing for another for a specified sum of money to be paid on full performance, he is not entitled to any part of the sum until he has himself done the thing he agreed to do, unless full performance has been excused, prevented or delayed by the act of the *289 other party, or by operation of law, or by the act of God or the public enemy.” (Carlson v. Sheehan, 157 Cal. 696, [109 Pac. 30].) This, of course, refers to actions upon the contract for the contract price. The right to sue on an implied contract for the value of a partial performance is a different question and is not here involved. The rule just stated is that prevailing at common law. [1] It has now been greatly relaxed and it is settled, especially in the case of building contracts where the owner has taken possession of the building and is enjoying the fruits of the contractor’s work in the performance of the contract, that if there has been a substantial performance thereof by the contractor in good faith, where the failure to make full performance can be compensated in damages to be deducted from the price or allowed as a counterclaim, and the omissions and deviations were not willful or fraudulent and do not substantially affect the usefulness of the building for the purposes for which it was intended, the contractor may, in an action upon the contract, recover the amount unpaid of his contract price, less the amount allowed as damages for the failure in strict performance. (9 Corpus Juris, 739; 2 Elliott on Contracts, sec. 1607; 6 R. C. L. 967, 970; 1 Beach on Contracts, secs. 111, 112; 3 Page on Contracts, secs. 1385, 1387; Connell v. Higgins, 170 Cal. 556, [150 Pac. 769]; Jones etc. Co. v. Doble Co., 162 Cal. 505, [123 Pac. 290]; Smith v. Mathews etc. Co., 179 Cal. 801, [179 Pac. 205]; Rischard v. Miller, 182 Cal. 351, [188 Pac. 50]; Collins v. Ramish, 182 Cal. 359, [188 Pac. 552]; City Street Improvement Co. v. Kroh, 158 Cal. 325, [110 Pac. 933] ; Perry v. Quackenbush, 105 Cal. 308, [38 Pac. 740]; Harlan v. Stufflebeem, 87 Cal. 511, [25 Pac. 686].)

In 9 Corpus Juris, 739, the rule is summarized as follows: “The hardship of the rule requiring strict performance in order to permit recovery on a contract generally, when applied to a builder who has undesignedly violated his contract, and the inequitable advantage that it gives to an owner who receives and retains the benefit of the builder’s labor and materials have led to its qualification; and it is generally held that, where the compensation is due only on the performance of the contract, a literal and strict performance is not required, and if the builder, acting in good faith and intending and attempting to perform his contract, does so, *290 he may recover the contract price notwithstanding slight and trivial defects or deviations in performance, for which compensation may he made, in all its material and substantial particulars, by an allowance to the owner; but the owner is entitled to an allowance for the damages he may suffer by reason of the failure to perform strictly, such as the cost or expense of putting the structure or work in the condition called for by the contract.” Many cases supporting the several statements in the text are cited in the footnotes. One of the dearest statements of the law on the subject is found in Handy v. Bliss, 204 Mass. 518, [134 Am. St. Rep. 673, 90 N.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Queens Land Builder v. Cal Garden CA2/7
California Court of Appeal, 2026
Charles Virzi Construction v. Studer CA4/3
California Court of Appeal, 2013
MURRAY'S IRON WORKS, INC. v. Boyce
71 Cal. Rptr. 3d 317 (California Court of Appeal, 2008)
Myers v. Western Realty & Construction, Inc.
635 P.2d 867 (Court of Appeals of Arizona, 1981)
Kossler v. Palm Springs Developments, Ltd.
101 Cal. App. 3d 88 (California Court of Appeal, 1980)
Tolstoy Constructor Co. v. Minter
78 Cal. App. 3d 665 (California Court of Appeal, 1978)
Votaw Precision Tool Co. v. Air Canada
60 Cal. App. 3d 52 (California Court of Appeal, 1976)
Weisz Trucking Co. v. Emil R. Wohl Construction
13 Cal. App. 3d 256 (California Court of Appeal, 1970)
Lowy v. United Pacific Insurance
429 P.2d 577 (California Supreme Court, 1967)
G & P Electric Co. v. Dumont Construction Co.
194 Cal. App. 2d 868 (California Court of Appeal, 1961)
1st Olympic Corp. v. Hawryluk
185 Cal. App. 2d 832 (California Court of Appeal, 1960)
Patrick J. Ruane, Inc. v. Parker
185 Cal. App. 2d 488 (California Court of Appeal, 1960)
Leboire v. Royce
349 P.2d 513 (California Supreme Court, 1960)
Lyon v. Giannoni
335 P.2d 690 (California Court of Appeal, 1959)
Mattei v. Hopper
330 P.2d 625 (California Supreme Court, 1958)
Shell v. Schmidt
330 P.2d 817 (California Court of Appeal, 1958)
Pacific Allied v. Century Steel Products, Inc.
327 P.2d 547 (California Court of Appeal, 1958)
Collins v. Vickter Manor, Inc.
306 P.2d 783 (California Supreme Court, 1957)

Cite This Page — Counsel Stack

Bluebook (online)
197 P. 105, 185 Cal. 285, 1921 Cal. LEXIS 544, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thomas-haverty-co-v-jones-cal-1921.