Queens Land Builder v. Cal Garden CA2/7

CourtCalifornia Court of Appeal
DecidedFebruary 13, 2026
DocketB330797
StatusUnpublished

This text of Queens Land Builder v. Cal Garden CA2/7 (Queens Land Builder v. Cal Garden CA2/7) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Queens Land Builder v. Cal Garden CA2/7, (Cal. Ct. App. 2026).

Opinion

Filed 2/13/26 Queens Land Builder v. Cal Garden CA2/7 NOT TO BE PUBLISHED IN THE OFFICIAL REPORTS California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or ordered published for purposes of rule 8.1115.

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

SECOND APPELLATE DISTRICT

DIVISION SEVEN

QUEENS LAND BUILDER, INC., B330797

Plaintiff and Respondent, (Los Angeles County Super. Ct. No. 20GDCV00072) v.

CAL GARDEN, LLC et al.,

Defendants and Appellants.

APPEAL from a judgment of the Superior Court of Los Angeles County, Maurice A. Leiter, Judge. Affirmed. Zarmi Law and David Zarmi for Defendants and Appellants. Law Office of Steven P. Scandura, Steven P. Scandura; and Howard C. Posner for Plaintiff and Respondent. ________________________ INTRODUCTION

Cal Garden, LLC and Ming Gu (together, Cal Garden) appeal from a $1,678,371.79 judgment in favor of Queens Land Builder, Inc. In 2016, Cal Garden contracted with Queens Land to build a 20-unit condominium complex in the City of Arcadia. The project was completed in 2019, after substantial delays. The parties sued one another, primarily alleging breach of contract claims. After a bench trial, the court found in favor of Queens Land. On appeal, Cal Garden characterizes the trial court’s findings as legal in nature and based on undisputed evidence. But Cal Garden essentially challenges the trial court’s factual findings and invites us to reweigh the evidence. On appeal, we do not reweigh the evidence or make credibility determinations. Accordingly, we affirm.

FACTUAL AND PROCEDURAL BACKGROUND

A. The Contracts Gu is the majority shareholder of Cal Garden. Cal Garden purchased a lot in the City of Arcadia, which abutted two neighboring properties with concrete block walls on both sides. Queens Land is a construction company owned by Tie Gao. On February 26, 2016, Cal Garden hired Queens Land to build 20 condominiums with subterranean parking for $5.75 million (February 26 contract). The February 26 contract specified Queens Land was responsible for the “[m]ain structure, all water, electricity, gas, heat and landscaping facilities” and that it “will be responsible for [these items] till they are fit for move-in.” Queens Land promised to deliver the completed

2 property by May 1, 2017, which is 420 calendar days from the March 1, 2016 start date. The contract provided for a $1,000 bonus “for each day that the project is completed ahead of schedule” and a penalty of $1,000 for each day the project was delayed. The February 26 contract was written in both English and Mandarin because Gu’s primary language is Mandarin. Cal Garden provided the architectural plans, the engineering plans, and the building plans to Queens Land. Gao testified Queens Land had no input on the plans. On March 31, 2016, the parties signed another contract that specified a price of $6.9 million for the project (March 31 contract). Unlike the February 26 contract, this contract was not translated into Mandarin. Gao testified at trial that the March 31 contract provided for higher quality finishing work, and that the initial February 26 contract included “very simple, very common” finishes. Gu testified the parties generated the March 31 contract “for the purpose of getting a bigger line of credit with the bank.” Gu stated the parties intended the loan to be divided into a $5.75 million portion to pay Queens Land and the remaining $1.15 million would be split between Cal Garden and Queens Land to pay for expenses such as city fees, design fees, and staff expenses. The financing company approved the loan and paid out funds based upon Queens Land’s periodic requests and Cal Garden’s approval. The parties subsequently agreed to change the construction start date from March 1, 2016, to April 5, 2016, but retained the construction period of 420 days. Thus, the parties intended construction to finish in 2017. Shortly after construction began, Queens Land discovered the soils engineering report provided to

3 it by Cal Garden, which stated there was “no caving” of the soil upon excavation, was incorrect. Gao testified the soil at the lot was commonly known as “sugar sand” because it would flow back into any hole that was drilled.1 The condition of the soil required a different type of shoring system. The parties were therefore required to revise the engineering plans, resubmit the plans to the city for approval, and hire a different drilling company. The new engineering plan required I-beams to be pounded into the ground rather than inserted into a hole that had been dug. The pounding of the I-beams caused vibrations to spread to the neighboring properties, resulting in their concrete block walls sinking and other property damage. The neighbors complained to the city and sued. The project was delayed while the parties attempted to fix the problem. In June 2017, the parties signed a third contract entitled “Supplemental Contract on Construction of Cal Garden” (supplemental contract) with a $6.1 million contract price “[i]n consideration of the serious delay of the construction progress and over budget of the construction cost[s] . . . .” Under the supplemental contract, the parties agreed “to have the completion date specified under the original contract extended to October 31st, 2017, and [Cal Garden] will not claim the daily penalty fee of USD one thousand for the period from June 30, 2017 through October 31st, 2017 if [Queens Land] completes and turns over all items in this project before October 31st, 2017. In

1 Cal Gardens obtained a later soils report dated February 29, 2016, that indicated “boring found caving at 4 to 10 feet.” Gao testified he did not receive the new report prior to construction and was not told about the caving prior to excavation.

4 the meantime, [Cal Garden] agrees to raise construction cost from USD 5.75 million which is specified under the original contract to USD 6.1 million (which will include the additional cost of materials and labor for the work on drift sand in basements submitted by [Queens Land]).” The supplemental contract also provided for a $100,000 bonus to Queens Land if it completed the project before October 31, 2017. The supplemental contract specified that the terms of the February 26 contract remained in effect and that the supplemental contract overrode the February 26 contract to the extent there were any inconsistencies between the two. Gao testified the supplemental contract also provided that Cal Garden would be responsible for paying any higher costs for certain materials, such as tile, wood flooring, carpet, bathtubs, exterior walls, painting, and railing, if these costs exceeded the budget under the February 26 contract. The funds from the financing company ran out in November 2017, and the subcontractors stopped work because they were not paid. Gao and his wife made personal loans to Gu to ensure the subcontractors were paid and the project completed. Cal Garden does not dispute these loans were unpaid and their amounts. In 2018, the city “red tagged” the project twice and lifted the stop work order on July 17, 2018. Cal Garden hired Kevin Chang in May 2019 to oversee construction. A certificate of occupancy was issued by the city in September 2019. Cal Garden sold three units but was prevented from selling any others because Queens Land recorded a lien on the property, which forced Cal Garden to rent out the remaining units.

5 B. The Litigation Proceedings On January 17, 2020, Queens Land sued Cal Garden for breach of contract, enforcement of the mechanics lien, an accounting, and intentional interference with contractual relations.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Posner v. Grunwald-Marx, Inc.
363 P.2d 313 (California Supreme Court, 1961)
Gray v. Don Miller & Associates, Inc.
674 P.2d 253 (California Supreme Court, 1984)
Lowy v. United Pacific Insurance
429 P.2d 577 (California Supreme Court, 1967)
Clemmer v. Hartford Insurance Co.
587 P.2d 1098 (California Supreme Court, 1978)
Lenk v. Total-Western, Inc.
108 Cal. Rptr. 2d 34 (California Court of Appeal, 2001)
MURRAY'S IRON WORKS, INC. v. Boyce
71 Cal. Rptr. 3d 317 (California Court of Appeal, 2008)
In Re Marriage of Falcone & Fyke
164 Cal. App. 4th 814 (California Court of Appeal, 2008)
Dorman v. DWLC Corp.
35 Cal. App. 4th 1808 (California Court of Appeal, 1995)
Robbins v. Alibrandi
25 Cal. Rptr. 3d 387 (California Court of Appeal, 2005)
Thomas Haverty Co. v. Jones
197 P. 105 (California Supreme Court, 1921)
Regalado v. Callaghan CA
3 Cal. App. 5th 582 (California Court of Appeal, 2016)
Ryan v. Rosenfeld
395 P.3d 689 (California Supreme Court, 2017)
Jameson v. Desta
420 P.3d 746 (California Supreme Court, 2018)
Parsons v. Bristol Development Co.
402 P.2d 839 (California Supreme Court, 1965)
In re Martinez
210 Cal. App. 4th 800 (California Court of Appeal, 2012)
City of Santa Maria v. Adam
211 Cal. App. 4th 266 (California Court of Appeal, 2012)
Ciprari v. Ciprari (In re Ciprari)
242 Cal. Rptr. 3d 900 (California Court of Appeals, 5th District, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
Queens Land Builder v. Cal Garden CA2/7, Counsel Stack Legal Research, https://law.counselstack.com/opinion/queens-land-builder-v-cal-garden-ca27-calctapp-2026.