Bryan Elevator Co. v. Law

160 P. 170, 31 Cal. App. 204, 1916 Cal. App. LEXIS 317
CourtCalifornia Court of Appeal
DecidedAugust 8, 1916
DocketCiv. No. 1465.
StatusPublished
Cited by7 cases

This text of 160 P. 170 (Bryan Elevator Co. v. Law) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bryan Elevator Co. v. Law, 160 P. 170, 31 Cal. App. 204, 1916 Cal. App. LEXIS 317 (Cal. Ct. App. 1916).

Opinion

*205 CHIPMAN, P. J.

In the first count of the complaint plaintiff seeks to recover the sum of sixteen thousand dollars upon a written contract entered into by plaintiff and defendant, January 20, 1905, for the construction and installation of an elevator plant and service by plaintiff for the Monadnock Building, San Francisco. The second count was for necessary repairs to the elevators, elevator equipments, and elevator hatchways in said building of the alleged value of $4,604.33. The third count is for elevator parts and supplies alleged to have 'been sold and delivered to defendant by plaintiff, for which defendant agreed to pay the sum of $2,053.10. Plaintiff had judgment on the first count for the sum of $13,375, with interest from May 1, 1908. The findings and judgment on the second and third counts were in favor of defendant.

Both parties appeal from the judgment. Defendant’s appeal is presented in this record and plaintiff’s appeal on the same transcript is presented in No. 1466. Defendant also appeals from the order denying his motion for a new trial. The cause was tried by the court without a jury. The issues tried may be understood from the findings of facts by the court:

“II.. That thereafter and on or about the 1st day of September, 1905, the said plaintiff entered upon and commenced the installation of said elevators, and proceeded with said installation as rapidly as the unfinished condition of said building would permit. That on or about the 18th day of April, 1906, and prior to the completion of the installation of said elevators, said building was injured and almost completely destroyed by earthquake and fire; that by reason of the damage suffered by said building, through said earthquake and fire, plaintiff was unable to continue with the performance of its said agreement for a long time thereafter; that as soon as said building was sufficiently repaired to make the work of installation of said elevators possible, the plaintiff continued the work of such installation; that plaintiff at all times, in good faith proceeded with the performance of the obligations imposed upon it by said agreement and furnished the materials and performed the labor required of it by said contract and honestly and faithfully performed said contract and completed the performance thereof on or about the 1st day of May, 1908, except as regards the controlling devices *206 furnished by said plaintiff on the five passenger elevators which were not satisfactory to defendant and on account of which said defendant declined to accept the same and removed them from the building, and in this behalf the court finds: That said controlling devices did not operate satisfactorily and defendant was justified in rejecting the same and in removing them from said building and putting in other controlling devices. The court also finds that although said defendant declined to accept the said controlling devices as furnished by plaintiff and was justified in removing them from said building and in putting in other controlling devices, said plaintiff substantially performed the said contract.

“III. That the agreement hereinabove ■ referred to was completed by said plaintiff on or about the 1st day of May, 1908, except that the defendant was not satisfied with the controllers on the said five passenger elevators and declined to accept the said controllers. That the length of time in completing said agreement by the said plaintiff was no greater than the amount of time said plaintiff was prevented from performing by the neglect of the said defendant in completing said building and by the earthquake and fire above referred to.

“IV. That in all regards, other than as above set forth, the plaintiff duly and faithfully performed all the conditions of said agreement above referred to on its part to be performed according to the terms of said agreement; that said plaintiff completely installed and equipped the elevators referred to in the said agreement in accordance with the plans and specifications attached to said agreement and made a part thereof, with the exception that the said defendant was not satisfied with said passenger elevator controllers or the elevator machines connected therewith and he declined to accept the same and removed all of said controllers and all of said elevator machines from said building and replaced the same with other elevator controllers and other elevator machines and installed said last mentioned controllers and machines in said building.

“That the reasonable market value of said elevator controllers and elevator machines so installed by said defendant was and is the sum of $15,156.00; and in this connection the court finds that the reasonable market value of said controllers go installed by defendant was and is the sum of $2625.00.

*207 • “But the court finds that defendant was not justified in rejecting the elevator machines so furnished hy plaintiff or any of them and was not justified in installing other elevator machines in place of them, and that said defendant could and did replace said controllers with controllers of a design, workmanship and efficiency satisfactory to him for the sum of $525.00 each or a total sum of $2625.00. . . .

“VI. That the sum of $21,375.00 is the reasonable value of the work done and the materials furnished by plaintiff in installing elevator machines and equipment for the defendant in said Monadnock Building, and the reasonable value of the materials furnished and accepted -and the installation work accepted and used by defendant and that said defendant has paid plaintiff the sum of $8,000.00 and has suffered damages on account of plaintiff’s failure to furnish controlling devices satisfactory to him in the sum of $2625.00; and that, after deducting from the contract price the said payment of $8,000.00 and the sum of $2625.00 to indemnify and compensate" the defendant for the damages so suffered by him, there is now due, owing and unpaid from said defendant to said plaintiff the sum of $13,375.00, together with interest thereon at the rate of 7% per annum from the 1st day of May, 1908. . . .

“And as conclusions of law from the foregoing facts, the court finds the plaintiff is entitled to judgment against the said defendant for the sum of $13,375.00, together with interest on said sum from the 1st day of May, 1908, at the rate of 7% per annum, amounting to $4228.72, and for its costs of suit herein expended.”

Plaintiff was properly to install, furnishing all the labor and materials therefor, four passenger elevators and one passenger elevator and safe lifter, and to alter the old passenger elevator then in use in the Bishop Building into a freight elevator, and to install two hydraulic ram sidewalk elevators, together with a flashlight signal system in accordance with certain plans and specifications made by Meyer & O’Brien, who were the architects of said building and of said work.

So far as this appeal reaches, the only -dispute we are to settle relates to the installation of the five passenger elevators. -And as to these the objection raised by defendant was to the unsatisfactory operation of the electrical controllers.

*208

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Scott Co. Inc. v. Rolkin
23 P.2d 1065 (California Court of Appeal, 1933)
Melton v. Story
298 P. 1032 (California Court of Appeal, 1931)
Allred v. Sheehan
202 P. 681 (California Court of Appeal, 1921)
Thomas Haverty Co. v. Jones
197 P. 105 (California Supreme Court, 1921)
Tiffany v. Pacific Sewer Pipe Co.
182 P. 428 (California Supreme Court, 1919)
Bruner v. Hegyi
183 P. 369 (California Court of Appeal, 1919)
Bryan Elevator Co. v. Law
160 P. 174 (California Court of Appeal, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
160 P. 170, 31 Cal. App. 204, 1916 Cal. App. LEXIS 317, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bryan-elevator-co-v-law-calctapp-1916.