Bowen v. Kimbell

203 Mass. 364
CourtMassachusetts Supreme Judicial Court
DecidedOctober 20, 1909
StatusPublished
Cited by58 cases

This text of 203 Mass. 364 (Bowen v. Kimbell) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bowen v. Kimbell, 203 Mass. 364 (Mass. 1909).

Opinion

Knowlton, C. J.

The plaintiff Dodge made a contract in writing to erect a large building for the defendants in North Adams. He received many payments under the contract, and afterwards brought this suit to recover the balance of the contract price. Having become a bankrupt, his trustee was permitted to come into court and prosecute the suit By agreement of parties the case was referred to a referee whose determination of all matters of fact was to be final, his decision of questions of law being subject to review by the court. He reported that the plaintiff was not entitled to recover, and judgment was ordered for the defendant on his report. The case comes before us on an appeal by the plaintiff, which presents for our consideration all questions of law that appear of record.

The declaration contains three counts, two upon the contract and one upon an account annexed. The plaintiff now concedes that he is not entitled to recover upon the contract, and he relies upon the common counts, which are open to him under the count upon the account annexed.

[368]*368The price fixed by the contract was $96,500. It was admitted that the defendants were entitled to an allowance of $90 for a saving in the price of face brick, and that payments have been made amounting to $87,195. Nine thousand eight hundred and fifteen dollars is the balance claimed in this action.

There were many particulars in which the defendants contended that the plaintiff failed to perform his contract. In regard to some of these the findings of the referee were for the plaintiff. But besides the plastering, of which we shall speak hereafter, there were ten different particulars in which it was found that the contract was not performed, for each of which the defendants would be entitled to an allowance, if they were obliged to pay at all. The deductions that ought to be made on account of these departures from the contract were found by the referee to amount in the aggregate to $4,071. It is not contended that any error of law entered into these findings.

The specifications in regard to the plastering provided, among other things, that the first coat for the whole building should be “ good lime and hair mortar and mixed when used in with adamant plaster, two bags of adamant to one hod of lime mortar.” They declared that “ This mixture must be strictly adhered to without any deviation whatever.” The findings on this point are as follows : “ The ‘ adamant ’ referred to in these specifications is a patented composition of the class commonly called hard plasters. It contains a considerable amount of plaster of Paris. It sets more quickly than lime and mortar plastering and gives a hardér surface, less liable to injury from blows of any kind, and is quite commonly used in modern office buildings. It is somewhat more expensive than lime and mortar plastering. I find that in plastering this building the plaintiff used less than half the adamant called for by the specifications. I find that this was an intentional departure from the contract in a substantial matter, which cannot be remedied afterwards without disproportionate expense. I further find that the composition of the plaster was not known to the architect until after the certificates given by him under the contract had all been issued. I therefore find that the plaintiff is not entitled to recover in this action. ... I find that the cost of removing the plastering in the building and replastering with plaster mixed in accordance with the specifications, in-[369]*369eluding the necessary retinting of walls, would be seven thousand dollars ($7,000). But I further find that the owner would not be justified in incurring such expense, and that the difference between the value of the building as actually plastered and as it would have been, if plastered in accordance with the specifications, is eight hundred dollars ($800).”

The plaintiff contends that the conclusion of the referee in this particular is erroneous in law, and that the judgment should be reversed. This contention seems to be two fold: first, that an intentional departure from the contract in a matter of this kind will not preclude the contractor from recovering on a quantum meruit; and, secondly, that, as matter of law, the referee could not find that there was not a substantial performance of the contract. It becomes necessary to consider the law of Massachusetts in these particulars.

It is to be noticed, first, that the question whether there was a substantial performance of the contract is to be determined in reference to the entire contract, and what was done or omitted under it, and not in reference to the plastering alone. The referee might well find that the plaintiff failed to perform the contract substantially, in view of all his departures from it, even if he would not have made that finding upon the defective plastering alone. The validity of the finding must be determined in reference to all the facts of the case. But as the referee indicates that this breach is the principal reason for his decision, we will consider this branch of the case by itself.

Formerly it was generally held in this country, as it is held in England, that a contractor could not recover under a building contract, unless there was a full and complete performance of it, or a waiver as to the parts not performed, and that he could not recover on a quantum, meruit after a partial performance from which the owner had received benefit, unless there had been such subsequent dealings between the parties as would create an implied contract to pay for what had been done. Smith v. Brady, 17 N. Y. 173,185. Ellis v. Hamlen, 3 Taunt. 52. Munro v. Butt, 8 E. & B. 738. Sumpter v. Hedges, [1898] 1 Q. B. 673, and cases cited. But in most of the American States a more liberal doctrine has been established in favor of contractors for the construction of buildings, and it is generally held that if a [370]*370contractor has attempted in good faith to perform his contract and has substantially performed it — although by inadvertence he has failed to perform it literally according to its terms — he may recover under the contract, with a proper deduction to the owner for the imperfections or omissions in the performance. Woodward v. Fuller, 80 N. Y. 312. Phillip v. Gallant, 62 N. Y. 256. Nolan v. Whitney, 88 N. Y. 648. Oberlies v. Bullinger, 132 N. Y. 598. Elliott v. Caldwell, 43 Minn. 357. Jones & Hotchkiss Co. v. Davenport, 74 Conn. 418. Pitcairn v. Philip Hiss Co. 113 Fed. Rep. 492. Page on Contracts, §§ 1603, 1604, and cases cited. It would seem that in cases of this kind, while the plaintiff recovers under the contract not the contract price but the contract price less the deduction, he ought to aver, not absolute performance, but only substantial performance of his contract and a right to recover only the balance after allowing the owner a proper sum for the failure to do the work exactly in the way required. Spence v. Ham, 163 N. Y. 220. The rule very generally adopted is that, to entitle the plaintiff to recover, he needs to show only that he proceeded in good faith in an effort to perform the contract, and that the result was a substantial performance of it, although there may be various imperfections or omissions that call for a considerable diminution of the contract price.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

G4S Technology LLC v. Massachusetts Technology Park Corp.
99 N.E.3d 728 (Massachusetts Supreme Judicial Court, 2018)
PDM Mechanical Contractors, Inc. v. Suffolk Construction Co.
618 N.E.2d 72 (Massachusetts Appeals Court, 1993)
Schmidt v. Kardos
1987 Mass. App. Div. 198 (Mass. Dist. Ct., App. Div., 1987)
Barnes v. Orange Foundry, Inc.
1982 Mass. App. Div. 266 (Mass. Dist. Ct., App. Div., 1982)
Creed v. Apog
376 N.E.2d 154 (Massachusetts Appeals Court, 1978)
C. C. & T. Construction Co. v. Coleman Bros.
330 N.E.2d 216 (Massachusetts Appeals Court, 1975)
V & V Construction Co. v. McGonagle
42 Mass. App. Dec. 121 (Mass. Dist. Ct., App. Div., 1968)
ALBRE MARBLE & TILE CO. INC. v. Goverman
233 N.E.2d 533 (Massachusetts Supreme Judicial Court, 1968)
Karas v. LeVay
38 Mass. App. Dec. 179 (Mass. Dist. Ct., App. Div., 1967)
Kirk Reid Company v. Fine
139 S.E.2d 829 (Supreme Court of Virginia, 1965)
Salem Glass Co. v. Joseph Rugo, Inc.
176 N.E.2d 30 (Massachusetts Supreme Judicial Court, 1961)
Lantz v. Chandler
164 N.E.2d 153 (Massachusetts Supreme Judicial Court, 1960)
Tribou v. Burrill
16 Mass. App. Dec. 63 (Mass. Dist. Ct., App. Div., 1958)
Lantz v. Chandler
17 Mass. App. Dec. 150 (Mass. Dist. Ct., App. Div., 1958)
Sacco v. Marks
15 Mass. App. Dec. 112 (Mass. Dist. Ct., App. Div., 1958)
Masse v. Smitherman Cotton Mills, Inc.
9 Mass. App. Dec. 31 (Mass. Dist. Ct., App. Div., 1955)
Morgan-National Woodworking Co. v. Cline
84 N.E.2d 460 (Massachusetts Supreme Judicial Court, 1949)
Meninno v. D'Antilio
12 Mass. App. Div. 11 (Mass. Dist. Ct., App. Div., 1947)
Nevins v. Ward
67 N.E.2d 673 (Massachusetts Supreme Judicial Court, 1946)
Russo v. Charles I. Hosmer, Inc.
44 N.E.2d 641 (Massachusetts Supreme Judicial Court, 1942)

Cite This Page — Counsel Stack

Bluebook (online)
203 Mass. 364, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bowen-v-kimbell-mass-1909.