PDM Mechanical Contractors, Inc. v. Suffolk Construction Co.

618 N.E.2d 72, 35 Mass. App. Ct. 228, 1993 Mass. App. LEXIS 833
CourtMassachusetts Appeals Court
DecidedAugust 25, 1993
Docket91-P-1440
StatusPublished
Cited by18 cases

This text of 618 N.E.2d 72 (PDM Mechanical Contractors, Inc. v. Suffolk Construction Co.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
PDM Mechanical Contractors, Inc. v. Suffolk Construction Co., 618 N.E.2d 72, 35 Mass. App. Ct. 228, 1993 Mass. App. LEXIS 833 (Mass. Ct. App. 1993).

Opinion

Perretta, J.

These cross appeals arise out of a contract under which PDM Mechanical Contractors, Inc. (PDM), was to install plumbing and mechanical systems for Suffolk Construction Company, Inc. (Suffolk), in its construction of a multi-building apartment complex known as the Arboretum Project. After about six months and while work was in progress, Suffolk terminated PDM’s involvement with the project. PDM brought this action against Suffolk and its surety, Seaboard Surety Company (Seaboard), asserting claims for breach of contract, quantum meruit, and unfair acts under G. L. c. 93A, § 11. Suffolk counterclaimed, alleging a breach of contract by PDM. Because the jury found for both PDM and Suffolk on their breach of contract claims, the judge entered judgment for PDM on the quantum meruit recovery. Having reserved decision on the c. 93A claim for herself, the judge found that Suffolk’s unfair act caused PDM harm, but not money damages, and awarded PDM counsel fees and costs. We affirm.

1. Background. There was evidence to show that, in September of 1987, Suffolk and PDM exchanged letters of intent memorializing their agreement that PDM would engineer, prefabricate, and install interior plumbing and HVAC systems for Suffolk at the Arboretum project for an agreed price of $2,470,000. The parties also agreed that they would negotiate a formal contract and that PDM would provide a performance bond in a form acceptable to Suffolk. Although work began on the project, Suffolk did not submit a formal contract to PDM for execution until early February, 1988. Shortly after receiving the contract and while it was under review, PDM complained of Suffolk’s untimeliness in returning approved drawings and its failure to prepare the *230 buildings adequately for installation of the internal plumbing systems. On March 10, 1988, Suffolk terminated PDM’s involvement with the project, accusing it of poor workmanship, unsatisfactory design work, and failure to execute the contract and to provide a bond. Although communication concerning PDM’s work continued, Suffolk, on March 18, 1988, a Friday, notified PDM that it was to execute and deliver, by Monday, 11:00 a.m., the contract and the performance bond. When PDM could not meet the deadline for providing the performance bond, Suffolk terminated the contract and hired another subcontractor. Suffolk produced evidence to show that it was required to pay the new subcontractor $29,000 to correct some of PDM’s work.

2. PDM’s contract claim. In response to special questions, the jury found that the parties had entered into a contract, that each was in breach of the contract, that Suffolk’s damages were $29,000, that PDM’s damages were $1,272,866, that PDM had tried in good faith fully to perform its work, that it had substantially performed its work, and that the fair value of the labor and materials provided by PDM was $248,160. Because of the jury’s finding that PDM was in breach of contract, the judge dismissed its count for contract damages and entered judgment on PDM’s claim in quantum meruit for the amount determined by the jury to be the fair value of the labor and materials provided to Suffolk.

PDM argues that, because the jury responded affirmatively to the special question on the quantum meruit claim, whether it “[did] try in good faith to fully perform its work . . . and did substantially perform its work,” they also implicitly found that PDM’s breach was “de minimis” and not wilful. PDM contends that such a breach does not preclude a recovery for contract damages. This argument finds no support in either the law or the jury’s answers to the special questions. “The law has long been settled in this Commonwealth, in relation to building contracts, that a contractor cannot recover on the contract itself without showing complete and strict performance of all its terms, but that, failing in such complete performance of the contract, he may recover on a *231 quantum meruit, if he can prove both substantial performance of the contract and an endeavor on his part in good faith to perform fully, and the burden is upon him to prove both.” (Emphasis in original). Andre v. Maguire, 305 Mass. 515, 516 (1940). See also Hayeck Bldg. & Realty Co. v. Turcotte, 361 Mass. 785, 789 (1972).

As explained in J. A. Sullivan Corp. v. Commonwealth, 397 Mass. 789, 793 (1986): “Quantum meruit is a theory of recovery, not a cause of action. It is a claim independent of an assertion for damages under the contract, although both claims have as a common basis the contract itself. Recovery under this theory is derived from the principles of equity and fairness and is allowed where there is substantial performance but not full completion of the contract. See generally 5 S. Williston, Contracts § 805 (3d ed. 1961).” (Emphasis in original.) This theory of recovery is particularly applicable in actions involving building contracts in order to avoid the harsh result of the long-established rule that there can be no recovery on a building contract in the absence of complete performance. See Bowen v. Kimbell, 203 Mass. 364, 370-371 (1909); Divito v. Uto, 253 Mass. 239, 242-243 (1925); Hayeck Bldg. & Realty Co. v. Turcotte, 361 Mass. at 789; J. A. Sullivan Corp. v. Commonwealth, 397 Mass. at 796.

Neither instructions nor special questions were put to the jury concerning the issues whether RDM’s breach was wilful or “de minimis.” It does not appear that any of the parties lodged an objection to the judge’s failure to include these issues in either her instructions or the special questions. See Service Publications, Inc. v. Goverman, 396 Mass. 567, 573 (1986). Moreover, and contrary to PDM’s argument, there is nothing in Service Publications, supra, which suggests that any finding of a “de minimis,” nonwilful breach by PDM would entitle it to contract damages rather than quantum meruit recovery. Rather, a “de minimis” breach would not necessarily preclude a finding of substantial performance of the contract and, therefore, recovery in quantum meruit. See Andre v. Maguire, 305 Mass. at 516; Albre Marble & Tile Co. v. Goverman, 353 Mass. 546, 550 (1968); J. A. Sullivan *232 Corp. v. Commonwealth, 397 Mass. at 797. We see no error in the judge’s refusal to enter judgment for PDM on its count for damages for breach of contract.

3. PDM’s quantum meruit recovery. On their cross appeals, Suffolk and Seaboard argue that it cannot be said on any view of the evidence that PDM sustained its burden of showing that it had substantially performed its work and had tried in good faith to complete the contract. We see no error in the judge’s denial of their motion for judgment notwithstanding the verdict on PDM’s quantum meruit claim.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

G4S Technology, LLC v. Massachusetts Technology Park Corp.
33 Mass. L. Rptr. 301 (Massachusetts Superior Court, 2016)
DeBettencourt v. Aronson
2011 Mass. App. Div. 27 (Mass. Dist. Ct., App. Div., 2011)
Tsitsilianos v. City of Worcester
20 Mass. L. Rptr. 396 (Massachusetts Superior Court, 2005)
Rosano-Davis, Inc. v. Sastre
2004 Mass. App. Div. 55 (Mass. Dist. Ct., App. Div., 2004)
Coughlin v. Gascombe
2000 Mass. App. Div. 321 (Mass. Dist. Ct., App. Div., 2000)
Procopio Construction Co. v. DiMarco
2000 Mass. App. Div. 166 (Mass. Dist. Ct., App. Div., 2000)
Quinn Bros. v. Whitehouse
737 A.2d 1127 (Supreme Court of New Hampshire, 1999)
Khaafid v. Fleet Bank
First Circuit, 1999
Swift v. Fitchburg Mutual Insurance
700 N.E.2d 288 (Massachusetts Appeals Court, 1998)
Orkin v. Rathje
First Circuit, 1995
Peabody N.E., Inc. v. Town of Marshfield
4 Mass. L. Rptr. 413 (Massachusetts Superior Court, 1995)
Minichillo v. Robert Cook & Sons, Inc.
3 Mass. L. Rptr. 181 (Massachusetts Superior Court, 1994)
Shepard's Pharmacy, Inc. v. Stop & Shop Companies, Inc.
640 N.E.2d 1112 (Massachusetts Appeals Court, 1994)
MRI Associates, Inc. v. Winchester Hospital
1 Mass. L. Rptr. 629 (Massachusetts Superior Court, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
618 N.E.2d 72, 35 Mass. App. Ct. 228, 1993 Mass. App. LEXIS 833, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pdm-mechanical-contractors-inc-v-suffolk-construction-co-massappct-1993.