J. A. Sullivan Corp. v. Commonwealth

494 N.E.2d 374, 397 Mass. 789, 1986 Mass. LEXIS 1674
CourtMassachusetts Supreme Judicial Court
DecidedJune 25, 1986
StatusPublished
Cited by206 cases

This text of 494 N.E.2d 374 (J. A. Sullivan Corp. v. Commonwealth) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. A. Sullivan Corp. v. Commonwealth, 494 N.E.2d 374, 397 Mass. 789, 1986 Mass. LEXIS 1674 (Mass. 1986).

Opinion

Nolan, J.

This is the defendant’s appeal from a judgment of the Superior Court in the amount of $154,463.53, plus interest and costs, in favor of the plaintiff, J. A. Sullivan Corporation (Sullivan), following a contract dispute between Sullivan and the defendant, the Commonwealth. We transferred the case here on our own motion and address the following issues: (1) whether, as a matter of law, Sullivan is precluded from recovering against the Commonwealth on quantum meruit; (2) whether, given the terms of the contract, the judge erred in awarding recovery to Sullivan in quantum meruit; (3) whether the judge erred in awarding damages to Sullivan where Sullivan failed to complete construction under the contract; (4) whether the judge erred in ruling that Sullivan was entitled to additional costs for ledge removal. After reviewing the trial judge’s findings and rulings under Mass. R. Civ. P. 52 (a), 365 Mass. 816 (1974), we affirm. We summarize the relevant facts drawn from the judge’s findings and other portions of the record.

In August, 1973, Sullivan and the Commonwealth, through the Bureau of Building Construction (bureau), entered into a contract for the construction of a building at Salem State College to house the physical education facilities. The original contract price was $5,598,000. The price was later increased to $5,703,457.87. Work commenced in September, 1973, and was scheduled to be completed in August, 1975. The Commonwealth retained the services of an architect, Edward I. Tedesco Associates, Inc., who along with the bureau agreed to extend the completion date on several occasions. On March 17, 1976, Sullivan informed a project architect from Tedesco that the project would be substantially completed by March 31, and requested that a “punch list” be compiled for the remainder of the work. A punch list is an itemized list of finish work, corrections, repairs, and services to be performed in order to complete a construction contract.

*791 On April 6, 1976, Sullivan notified a dean of Salem State College that it was awaiting a punch list, and that it expected to have the project completed by the end of April. On April 28, the project architect from Tedesco notified Sullivan that he was dissatisfied with the paucity of persons at the job site. Between April 6 and June 18, 1976, Tedesco compiled several punch lists covering different zones of the construction project, dated at different times. Some of the lists contained items from previous lists. The last punch list, dated June 18, 1976, was comprehensive, covering the entire project and containing some items that were not included on prior punch lists. John A. Sullivan, president of J. A. Sullivan Corporation, testified that it is a general practice in the construction industry to issue “monetized” punch lists (items are given a money value) to enable contractors to negotiate with subcontractors. The judge found that none of the punch lists which were sent to Sullivan from April to June, 1976, were monetized.

Sullivan continued working on items on the punch lists until the fall of 1976. On September 30, the architect compiled another punch list for the exterior and the roof of the project. In October, he sent another one for the entire project. This list was monetized by category only at a total value of $182,950.00.

On October 15, 1976, the bureau issued a Certificate of Use Occupancy, which provided that the contractor was relieved of responsibility for completion of work on the project except for the remaining items on the punch list. Fourteen days later the bureau complained to Sullivan about the insufficient number of workers at the site and stated that the bonding company would be notified if substantial progress towards completion was not accomplished within thirty days.

In November, Sullivan disputed the accuracy of the punch list which had accompanied the certificate of use occupancy and requested, among other things, a monetized punch list. Also at this time Sullivan submitted Requisition No. 34 for $318,976.15, for work performed between September 25, 1975, and October 31, 1976. No payment was made. In fact, the Commonwealth stated that it was withholding $29,300 in liquidated damages due to the plaintiff’s failure to complete *792 construction on time, $154,757.11 for direct payment requests made by subcontractors, and $130,000 representing work remaining to be done.

In December, 1976, another updated punch list was compiled by Tedesco and sent to the Commonwealth and Sullivan. Correspondence between the Commonwealth and Sullivan reflected the Commonwealth’s dissatisfaction with Sullivan’s performance, and Sullivan’s dispute with many items on the December punch list. Sullivan contended that many of the items had already been completed, and offered credit for those which could not be done.

On March 2, 1977, Sullivan received another updated, monetized punch list. This was the first list monetized on an item-by-item basis. Nine days later the Commonwealth informed Sullivan that its contract had been terminated. John A. Sullivan testified that at that time the total value of the punch list was $32,000.

The Commonwealth instructed Tedesco to draw up plans and specifications for a new contract and to include the uncompleted punch list items. The contract was submitted for bidding and was taken by T. G. Driscoll Construction Company.

On appeal, our review of the findings, rulings, and judgment of the trial judge, entered in this nonjury case on November 14, 1984, is governed by Mass. R. Civ. P. 52 (o), 365 Mass. 816 (1974), which provides that “[fjindings of fact shall not be set aside unless clearly erroneous.” “A finding is ‘clearly erroneous’ when although there is evidence to support it, the reviewing court on the entire evidence is left with the definite and firm conviction that a mistake has been committed.” United States v. United States Gypsum Co., 333 U.S. 364, 395 (1948). This court must also examine the findings and rulings to make sure that the conclusions are not inconsistent with legal standards. Marlow v. New Bedford, 369 Mass. 501, 508 (1976).

1. Claim for quantum meruit against the Commonwealth. We find no error in the judge’s ruling that a quantum meruit claim can lie against the Commonwealth in this case. See Albre Marble & Tile Co., Inc. v. Goverman, 353 Mass. 546 (1968). See also Arthur A. Johnson Corp. v. Commonwealth, 318 *793 Mass. 88, 89 (1945). The Commonwealth relies primarily on Lewis v. Commonwealth, 332 Mass. 4, 6 (1954), where this court said that “[t]here is no implied obligation upon the part of the Commonwealth to pay for the petitioner’s services merely because they might have been beneficial. . . .” The Commonwealth misses the point in Lewis, supra, which was that extra services rendered outside the contract were not compensable. There was no such claim here.

The Commonwealth’s argument is founded on the doctrine of sovereign immunity.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

GERALD LEAHY v. CORTNI TYLER & Others.
Massachusetts Appeals Court, 2025
Bulwer v. EchoNous, Inc.
D. Massachusetts, 2024
James B. Nutter & Co. v. Estate of Murphy
Massachusetts Supreme Judicial Court, 2018
Commonwealth v. Tremblay
Massachusetts Appeals Court, 2017
Balles v. Babcock Power Inc.
70 N.E.3d 905 (Massachusetts Supreme Judicial Court, 2017)
Petriello v. Indresano
87 Mass. App. Ct. 438 (Massachusetts Appeals Court, 2015)
Walter E. Fernald Corp. v. The Governor
31 N.E.3d 47 (Massachusetts Supreme Judicial Court, 2015)
Santangelo v. New York Life Insurance Co.
785 F.3d 65 (First Circuit, 2015)
Metropolitan Life Insurance v. Cotter
984 N.E.2d 835 (Massachusetts Supreme Judicial Court, 2013)
Lawarre v. Fifth Third Secs., Inc.
2012 Ohio 4016 (Ohio Court of Appeals, 2012)
Commonwealth v. Bresnahan
971 N.E.2d 218 (Massachusetts Supreme Judicial Court, 2012)
Commonwealth v. Pugh
969 N.E.2d 672 (Massachusetts Supreme Judicial Court, 2012)
Commerce Insurance v. Blackburn
964 N.E.2d 1005 (Massachusetts Appeals Court, 2012)
Valley Forge Insurance v. Field
670 F.3d 93 (First Circuit, 2012)
Brandao v. DoCanto
951 N.E.2d 979 (Massachusetts Appeals Court, 2011)
Backman v. SMIRNOV
751 F. Supp. 2d 304 (D. Massachusetts, 2010)
Astra USA, Inc. v. Bildman
455 Mass. 116 (Massachusetts Supreme Judicial Court, 2009)
Mike Glynn & Co. v. Hy-Brasil Restaurants, Inc.
914 N.E.2d 103 (Massachusetts Appeals Court, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
494 N.E.2d 374, 397 Mass. 789, 1986 Mass. LEXIS 1674, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-a-sullivan-corp-v-commonwealth-mass-1986.