§ 39G — Completion of public works; semi-final and final estimates; payments; extra work; disputed items

Massachusetts § 39G
JurisdictionMassachusetts
Part IADMINISTRATION OF THE GOVERNMENT
Title IIILAWS RELATING TO STATE OFFICERS
Ch. 30GENERAL PROVISIONS RELATIVE TO STATE DEPARTMENTS, COMMISSIONS, OFFICERS AND EMPLOYEES

This text of Massachusetts § 39G (Completion of public works; semi-final and final estimates; payments; extra work; disputed items) is published on Counsel Stack Legal Research, covering Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mass. Gen. Laws ch. 30, § 39G (2026).

Text

Section 39G. Upon substantial completion of the work required by a contract with the commonwealth, or any agency or political subdivision thereof, for the construction, reconstruction, alteration, remodeling, repair or improvement of public ways, including bridges and other highway structures, sewers and, water mains, airports and other public works, the contractor shall present in writing to the awarding authority its certification that the work has been substantially completed. Within twenty-one days thereafter, the awarding authority shall present to the contractor either a written declaration that the work has been substantially completed or an itemized list of incomplete or unsatisfactory work items required by the contract sufficient to demonstrate that the work has not been substant

Free access — add to your briefcase to read the full text and ask questions with AI

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Massachusetts § 39G, Counsel Stack Legal Research, https://law.counselstack.com/statute/ma/39G.