Mike Glynn & Co. v. Hy-Brasil Restaurants, Inc.

914 N.E.2d 103, 75 Mass. App. Ct. 322, 2009 Mass. App. LEXIS 1179
CourtMassachusetts Appeals Court
DecidedSeptember 30, 2009
DocketNo. 08-P-303
StatusPublished
Cited by6 cases

This text of 914 N.E.2d 103 (Mike Glynn & Co. v. Hy-Brasil Restaurants, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mike Glynn & Co. v. Hy-Brasil Restaurants, Inc., 914 N.E.2d 103, 75 Mass. App. Ct. 322, 2009 Mass. App. LEXIS 1179 (Mass. Ct. App. 2009).

Opinion

Dreben, J.

This is an appeal by Hy-Brasil Restaurants, Inc. (Hy-Brasil), and Liam Tieman (Tieman) from a judgment entered after a jury-waived trial that held both defendants jointly and [323]*323severally liable on the basis of quantum meruit2 to pay the plaintiff-subcontractor for its services. We affirm with a slight modification.

Background. We take our facts from the findings of the trial judge, adding a few undisputed details from the record. Hy-Brasil rents property at 99 Broad Street in Boston, where it operates a restaurant and bar. Tiernan is the president of the defendant corporation. The other officers at the relevant time period were Tiernan’s wife, Susan Tiernan, and Michael Sherlock, who was subsequently removed after a quarrel with Tiernan. In 1996, Hy-Brasil entered into a contract with Howell Management (Howell) for the construction of a restaurant and bar on the property, and in September, 1996, the plaintiff, Mike Glynn & Company (Glynn),3 entered into a subcontract with Howell to do the plumbing, heating, and air conditioning work.4 Michael Glynn had known Tiernan and Sherlock for over thirty years, and Tiernan acknowledged that “in some way [he was] part of [the] decision” of having Glynn chosen as subcontractor. On October 27, 1996, Howell committed a breach of its contract with the plaintiff by failing to pay an invoice in full within ten days.5

The evidence was conflicting as to what happened thereafter. Glynn claimed that after his workers threatened to leave, Tier-nan told him that it was most important that the job be finished before the holidays and promised Glynn that either Tiernan personally, or Hy-Brasil, would pay him if he completed the job. Tiernan denied having had this conversation with Glynn. Although the judge concluded that there was no written or oral contract between the plaintiff and the defendants, he made the following findings:

“This court is satisfied that in performing the construction [324]*324work on the restaurant, Glynn expected compensation in return for his services. Whether he expected to be paid specifically by Hy-Brasil and Tientan remains an open question. This Court has concluded that there was no written or oral contract between the plaintiff and defendants in this case, and must use additional evidence to decide this issue. While it is disputed whether any express agreement was made, it is uncontested that the defendant accepted the services of the plaintiff with knowledge that the plaintiff expected to be paid by someone.
“The plaintiff contends that when Howell breached their initial contract, the plaintiff was prepared to walk off the job. Not only did Glynn then stay on the job; he hired additional workers, worked overtime, and focused almost entirely on the restaurant to complete it in time for the holiday season. Rather than leave the job with five thousand dollars in damages, Glynn stayed on the site and performed forty-two thousand dollars worth of work. This Court concludes that Glynn incurred an additional eight times the amount of damages as a result of some motivation from the defendants, who were the direct beneficiaries of the completion of the project.[6] It is significant to this Court that the parties involved knew each other for over thirty years, as the ‘trier must consider all relevant circumstances including the situation and the relationship of the parties.’ ” (Citation omitted.)

Although the defendants claimed they had paid Howell for work performed by Glynn, the defendants’ payments to Howell were not itemized, and the defendants offered no specific evidence that any such payments were for work performed by Glynn. At the time of trial Howell and Hy-Brasil were disputing a $69,164 balance on their contract in an independent action. The judge also found that the defendants

“accepted the fruits of Glynn’s labor without any showing that they made payments to anyone for these services. All of these inferences surrounding the actions of the parties after Howell stopped paying Glynn favor the plaintiff.”

Discussion. 1. The defendants first argue that the plaintiff’s [325]*325claim is barred by the Statute of Frauds, that, in substance, Tier-nan acted as surety for Howell’s performance of its obligations to Glynn. As the trial judge pointed out, even on the alleged oral contract claim, the argument is without merit as the “main purpose” exception to the Statute of Frauds would apply here. The “consideration for the promise [was] in fact . . . mainly for [the defendants’] own economic advantage, rather than in order to benefit [Howell].” Barboza v. Liberty Contractors Co., 18 Mass. App. Ct. 971, 972 (1984), quoting from Restatement (Second) of Contracts § 116 (1979). Moreover, a claim for quantum meruit is not barred by the Statute of Frauds; indeed, often the reason recovery in quantum meruit is allowed is because an oral contract is unenforceable by reason of the Statute of Frauds.7 See Hastoupis v. Gargas, 9 Mass. App. Ct. 27, 35 (1980); 10 Williston, Contracts § 27.23, at 228 (Lord 4th ed. 1999).

2. In a diffuse argument, the defendants challenge the judge’s finding that they benefited from the work, claiming rather that Glynn was bound by his contract with Howell to finish before Thanksgiving, that he failed to do so, and that the defendants suffered damages as a result of the delay. They claim that no equities favor Glynn and that its sole remedy, not having filed a mechanics’ hen, is against Howell.8

Our review of the findings of the trial judge is governed by Mass.R.Civ.R 52(a), as amended, 423 Mass. 1402 (1996), which provides that “[findings of fact shall not be set aside unless clearly erroneous, and due regard shall be given to the opportunity of the trial court to judge of the credibility of the [326]*326witnesses.” Although the record contains some evidence favoring the defendants, e.g., that Glynn kept sending its invoices to Howell even after Howell ceased to pay, our review of the entire record does not lead us to conclude that the judge’s findings are clearly erroneous.9 To the contrary, they are supported by the evidence and do not leave us “with the definite and firm conviction that a mistake has been committed.” J.A. Sullivan Corp. v. Commonwealth, 397 Mass. 789, 792 (1986), quoting from United States v. United States Gypsum Co., 333 U.S. 364, 395 (1948).

Before discussing the reasons why we consider recovery appropriate in this case, we note that although the trial judge distinguished the plaintiff’s claim for unjust enrichment from that of quantum meruit, the terms are not as separate as he suggests (see note 2, supra). In the oft-cited case of Salomon v. Terra, 394 Mass. 857, 859 (1985) (Salomon), the court stated:

“A quasi contract or a contract implied in law is an obligation created by law ‘for reasons of justice, without any expression of assent and sometimes even against a clear expression of dissent.... [Considerations of equity and morality play a large part ... in constructing a quasi-contract . . . .’ 1 A. Corbin, Contracts § 19 (1963).[

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re: James F. McGuinness
D. Massachusetts, 2026
Ratchford v. Orange Lantern, Inc.
D. Massachusetts, 2024
D5 Iron Works, Inc. v. Danvers Fish & Game Club, Inc.
102 N.E.3d 427 (Massachusetts Appeals Court, 2018)
Suffolk Construction Co., Inc. v. Benchmark Mechanical Systems, Inc.
56 N.E.3d 138 (Massachusetts Supreme Judicial Court, 2016)
Scarpaci v. Lowe's Home Center, LLC
212 F. Supp. 3d 246 (D. Massachusetts, 2016)
Tufts University Cummings School of Veterinary Medicine v. Saffran
2011 Mass. App. Div. 111 (Mass. Dist. Ct., App. Div., 2011)

Cite This Page — Counsel Stack

Bluebook (online)
914 N.E.2d 103, 75 Mass. App. Ct. 322, 2009 Mass. App. LEXIS 1179, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mike-glynn-co-v-hy-brasil-restaurants-inc-massappct-2009.