Henning v. Security Bank

564 N.W.2d 398, 1997 Iowa Sup. LEXIS 195, 1997 WL 330971
CourtSupreme Court of Iowa
DecidedJune 18, 1997
Docket96-756
StatusPublished
Cited by12 cases

This text of 564 N.W.2d 398 (Henning v. Security Bank) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Henning v. Security Bank, 564 N.W.2d 398, 1997 Iowa Sup. LEXIS 195, 1997 WL 330971 (iowa 1997).

Opinion

LAVORATO, Justice.

A contractor walked off the job without paying his subcontractors even though the contractor was paid sufficient monies to pay them. Later, the homeowners paid the subcontractors and therefore paid twice for the same work and materials. The homeowners then sought reimbursement from their interim lender for allegedly promising to make sure that the subcontractors were paid by insisting on lien waivers from the contractor before any payment to him.

The district court ruled that the lender bank had no duty to reimburse the homeowners because the homeowners were not legally obligated to pay the subcontractors who had failed to preserve their mechanic’s lien rights under Iowa Code chapter 572 (1995). The homeowners’ appeal presents the following issue: In the absence of a contractual arrangement with the homeowners, do subcontractors have a common-law right of action based on implied contract or unjust enrichment against the homeowners for the work and materials they furnish? We conclude they do not and affirm.

Our review is governed by how the parties tried the case in the district court. Grinnell Mut. Reins. Co. v. State Farm Mut. Auto. Ins. Co., 558 N.W.2d 176, 178 (Iowa 1997). Because the parties tried the case at law, our review is for error. Id. Therefore the district court’s findings have the effect of a jury verdict and are binding on us if supported by substantial evidence. Id. Evidence is substantial if reasonable minds would accept it as adequate to reach the same findings. Id.

Substantial record evidence supports the following facts as found by the district court. Richard Burton Henning and Diane May Henning are husband and wife. In June 1994, the Hennings and Douglas C. Morris of Morris New Home Builders entered into a written contract whereby Morris agreed to build the Hennings a new home for $91,400. The parties later agreed upon changes that increased the cost to $106,155 by the time construction began the following fall.

Morris was the general contractor and had the responsibility to arrange for and pay all subcontractors. The Hennings had some direct dealings with some of the subcontractors. Nevertheless, Morris — not the Hen-nings — made all of the contractual arrangements for the work the subcontractors were to do.

After the Hennings and Morris executed their contract, the Hennings met with Lesa Udelhoven, the real estate loan officer of Security Bank. The meeting took place in late June. Udelhoven arranged the interim construction financing for the home Morris was to build. The bank agreed to loan the Hennings $79,000; the Hennings were to provide the balance of the construction cost.

The present controversy stems from this June meeting with Udelhoven. The Hen-nings testified that Udelhoven tried to explain mechanic’s liens and lien waivers, but they did not understand her explanation. The Hennings were sure, however, that *400 Udelhoven assured them they need not worry about hen waivers because the bank would take care of them. Kathleen Vanderpool, the listing realtor representing Morris, was at the meeting and corroborated the Hennings’ testimony on this point.

Udelhoven, however, testified that she made no such representation. Udelhoven also testified that she discussed and satisfactorily explained mechanic’s hens and hen waivers.

After the June meeting, Udelhoven sent the Hennings a letter outlining the bank’s participation in the transaction. The letter makes clear that the Hennings were to “[p]rovide[ ] hen waivers and receipts as requested by the bank.” Consistent with the letter, Udelhoven testified that the Hen-nings — not the bank — were to provide the hen waivers if any were obtained. Udelho-ven insisted that she asked the Hennings about hen waivers each time the bank was called upon to make a construction progress payment to Morris, but the Hennings never provided any.

By February 1995, the Hennings were aware that Morris’ financial condition was deteriorating. The Hennings were paying Morris; Morris, however, was not paying the subcontractors. When the Hennings told Udelhoven about Morris not paying the subcontractors, Udelhoven told them to seek the advice of an attorney. The Hennings did so.

The Morris-Hennings contract required the Hennings to make the following progress payments to Morris: “$15,000 down payment; $30,000 after foundation; $30,000 after framing; $18,000 after drywall; $13,155 after completion and acceptance.” The bank would pay the Hennings each progress payment, and the Hennings in turn would pay Morris. The last progress payment the bank made to the Hennings was on February 15, 1995 for $18,000. The Hennings in turn paid this amount to Morris. That left $13,155 to be paid on completion and acceptance.

Morris did no substantial work after the $18,000 payment. He left the job for good in March and has never claimed he was owed any further payment. When Morris left the job, the contract work was not finished.

However, there was $13,155 left in bank funds to finish the work. In their testimony, the Hennings conceded this amount would have been enough to finish the work in accordance with the contract. The $13,155, however, was not enough to pay the unpaid subcontractors and finish the work. The Hennings’ attorney advised them to settle with the subcontractors and “finish the contract.” The Hennings did so after borrowing additional money from the bank.

None of the subcontractors gave the Hen-nings an Iowa Code section 572.14(3) notice. Iowa Code section 572.14(2) provides that, in the case of an owner-occupied dwelling, a subcontractor who has perfected a mechanic’s lien can only enforce it to the extent of any sum of money the owner owes the contractor at the time the subcontractor gives the owner a written notice in the form specified in Iowa Code section 572.14(3). The Hennings’ home was at the time an owner-occupied dwelling. Notwithstanding the subcontractors’ failure to give the Hennings the section 572.14(3) notice, the Hennings paid the subcontractors with their own funds and with additional funds they borrowed from the bank.

Later, the Hennings brought this action against the bank and alleged two theories of recovery. They alleged the bank negligently misrepresented it would obtain lien waivers as loan funds were disbursed. They also alleged the bank was required to take care of the lien waivers as part of the loan agreement and good customer service. The Hen-nings sought recovery of (1) the payments they made to the subcontractors, (2) additional interest charges for the second bank loan to pay the subcontractors, and (3) attorney fees.

Following a bench trial, the district court found for the bank. The court made no findings as to the two theories of liability asserted by the Hennings. Instead, the court addressed the Hennings’ claim as one for indemnification and concluded the bank was not liable to the Hennings.

The Hennings appealed.

To understand the Hennings’ argument on appeal, we need to explore the district court’s *401 well-reasoned decision more fully.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mike Glynn & Co. v. Hy-Brasil Restaurants, Inc.
914 N.E.2d 103 (Massachusetts Appeals Court, 2009)
Jerry D. Longfellow Vs. Hal Sayler
Supreme Court of Iowa, 2007
Longfellow v. Sayler
737 N.W.2d 148 (Supreme Court of Iowa, 2007)
Harms v. City of Sibley
702 N.W.2d 91 (Supreme Court of Iowa, 2005)
Hansen v. Anderson, Wilmarth & Van Der Maaten
630 N.W.2d 818 (Supreme Court of Iowa, 2001)
Dj Painting, Inc. v. Baraw Enterprises, Inc.
776 A.2d 413 (Supreme Court of Vermont, 2001)
City of Dubuque v. Iowa Trust
587 N.W.2d 216 (Supreme Court of Iowa, 1998)
Metz v. Amoco Oil Co.
581 N.W.2d 597 (Supreme Court of Iowa, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
564 N.W.2d 398, 1997 Iowa Sup. LEXIS 195, 1997 WL 330971, Counsel Stack Legal Research, https://law.counselstack.com/opinion/henning-v-security-bank-iowa-1997.